Refresh data
Refresh data

2 years ago

on Tuesday, January 30th 2024, 6:30:00 pm
Work Sanctioned
सड़क सुरक्षा के अन्तर्गत जनपद उत्तरकाशी के विधानसभा क्षेत्र यमुनोत्री के अन्तर्गत सिलक्यारा बनगांव चापड़ा सरोट मोटर मार्ग पर रोड़़ सेफ्टी का कार्य एवं सड़क सुरक्षा के अन्तर्गत जनपद उत्तरकाशी के विधानसभा क्षेत्र यमुनोत्री मे ब्रहमखाल जुणगा कुमारकोट मोटर मार्ग (प्रमुख जिला सड़क-3 एम.डी.आर. 218) के किमी0 0.00 से 16 तक आवश्यक स्थानों पर क्रैश बैरियर एवं डेलीनेटर आदि लगाने का कार्य

2 years ago

on Monday, March 4th 2024, 6:30:00 pm
15%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Sunday, April 14th 2024, 6:30:00 pm
45%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Sunday, May 19th 2024, 6:30:00 pm
0.56%
Financial Progress

1st Expenditure
of ₹ 114916 (1.15 Lacs ) done.
Cummulative ₹ 1.15Lacs ( against 204.74Lacs )

a year ago

on Wednesday, May 29th 2024, 6:30:00 pm
23.45%
Financial Progress

2nd Expenditure
of ₹ 4686488 (46.86 Lacs ) done.
Cummulative ₹ 48.01Lacs ( against 204.74Lacs )

a year ago

on Tuesday, July 2nd 2024, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Sunday, July 28th 2024, 6:30:00 pm
23.55%
Financial Progress

3rd Expenditure
of ₹ 20302 (0.20 Lacs ) done.
Cummulative ₹ 48.22Lacs ( against 204.74Lacs )

10 months ago

on Wednesday, November 6th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 4th time

10 months ago

on Tuesday, December 3rd 2024, 6:30:00 pm
45.52%
Financial Progress

4th Expenditure
of ₹ 4499028 (44.99 Lacs ) done.
Cummulative ₹ 93.21Lacs ( against 204.74Lacs )

8 months ago

on Monday, January 20th 2025, 6:30:00 pm
45.89%
Financial Progress

5th Expenditure
of ₹ 75520 (0.76 Lacs ) done.
Cummulative ₹ 93.96Lacs ( against 204.74Lacs )

8 months ago

on Sunday, January 26th 2025, 6:30:00 pm
45.93%
Financial Progress

6th Expenditure
of ₹ 7080 (0.07 Lacs ) done.
Cummulative ₹ 94.03Lacs ( against 204.74Lacs )

8 months ago

on Sunday, January 26th 2025, 6:30:00 pm
45.96%
Financial Progress

7th Expenditure
of ₹ 7080 (0.07 Lacs ) done.
Cummulative ₹ 94.10Lacs ( against 204.74Lacs )

8 months ago

on Monday, January 27th 2025, 6:30:00 pm
73.19%
Financial Progress

8th Expenditure
of ₹ 5573848 (55.74 Lacs ) done.
Cummulative ₹ 149.84Lacs ( against 204.74Lacs )

6 months ago

on Sunday, March 30th 2025, 6:30:00 pm
91.40%
Financial Progress

9th Expenditure
of ₹ 3728570 (37.29 Lacs ) done.
Cummulative ₹ 187.13Lacs ( against 204.74Lacs )

2 months ago

on Thursday, July 17th 2025, 6:30:00 pm
100.00%
Financial Progress

10th Expenditure
of ₹ 1760763 (17.61 Lacs ) done.
Cummulative ₹ 204.74Lacs ( against 204.74Lacs )