Work Sanctioned
राज्य योजना के अन्तर्गत जनपद उत्तरकाशी के विधान सभा क्षेत्र यमुनोत्री के विकास खण्ड चिन्यालीसौड़ के अन्तर्गत पीपलमण्डी से स्यांसूमणी पुल तक मोटर मार्ग पर पी.सी. द्वारा सतह सुधार कार्य ।

2 years ago

on Friday, June 16th 2023, 5:01:10 am

Technical Sanction
of ₹ 273.8 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 3781/06 (36) याता.-(क्षे.का.)/2023

2 years ago

on Monday, July 24th 2023, 6:30:00 pm
1.66%
Financial Progress

1st Expenditure
of ₹ 489210 (4.89 Lacs ) done.
Cummulative ₹ 4.89Lacs ( against 294.34Lacs )

2 years ago

on Monday, July 24th 2023, 6:30:00 pm
3.32%
Financial Progress

2nd Expenditure
of ₹ 488501 (4.89 Lacs ) done.
Cummulative ₹ 9.78Lacs ( against 294.34Lacs )

2 years ago

on Sunday, July 30th 2023, 6:30:00 pm
3.32%
Financial Progress

3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 9.78Lacs ( against 294.34Lacs )

2 years ago

on Monday, September 25th 2023, 6:30:00 pm
20.57%
Financial Progress

6th Expenditure
of ₹ 4737634 (47.38 Lacs ) done.
Cummulative ₹ 60.56Lacs ( against 294.34Lacs )

2 years ago

on Monday, September 25th 2023, 6:30:00 pm
4.48%
Financial Progress

5th Expenditure
of ₹ 175514 (1.76 Lacs ) done.
Cummulative ₹ 13.18Lacs ( against 294.34Lacs )

2 years ago

on Monday, September 25th 2023, 6:30:00 pm
3.88%
Financial Progress

4th Expenditure
of ₹ 164680 (1.65 Lacs ) done.
Cummulative ₹ 11.42Lacs ( against 294.34Lacs )

2 years ago

on Thursday, September 28th 2023, 6:30:00 pm
20.57%
Financial Progress

7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 60.56Lacs ( against 294.34Lacs )

2 years ago

on Wednesday, October 4th 2023, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Monday, October 9th 2023, 5:08:48 am
<span class="4">Picture Id:24647</span>
PWD Uttarakahnd
Photo (ID 24647) from Site Received
Uploader : Lokendra Singh, Additional Assistant Engineer Civil ,CD Uttarkashi
Landmark : 10
Remark : Pipal mandi to syashumani m/r p.c worl

2 years ago

on Tuesday, October 10th 2023, 8:38:38 am
<span class="4">Picture Id:24739</span>
PWD Uttarakahnd
Photo (ID 24739) from Site Received
Uploader : Lokendra Singh, Additional Assistant Engineer Civil ,CD Uttarkashi
Landmark : Km 11
Remark : Seal coat .. pipal mandi to syashumani motar road

2 years ago

on Wednesday, October 11th 2023, 9:01:22 am
<span class="4">Picture Id:24818</span>
PWD Uttarakahnd
Photo (ID 24818) from Site Received
Uploader : Lokendra Singh, Additional Assistant Engineer Civil ,CD Uttarkashi
Landmark : 7
Remark : Seal coat .. at pipalmandi to syashumani work ...

2 years ago

on Wednesday, October 18th 2023, 6:30:00 pm
20.64%
Financial Progress

8th Expenditure
of ₹ 20000 (0.20 Lacs ) done.
Cummulative ₹ 60.76Lacs ( against 294.34Lacs )

2 years ago

on Sunday, October 29th 2023, 6:30:00 pm
20.78%
Financial Progress

9th Expenditure
of ₹ 40500 (0.41 Lacs ) done.
Cummulative ₹ 61.16Lacs ( against 294.34Lacs )

2 years ago

on Monday, October 30th 2023, 6:30:00 pm
20.78%
Financial Progress

10th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 61.16Lacs ( against 294.34Lacs )

2 years ago

on Wednesday, November 1st 2023, 6:30:00 pm
55%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Monday, November 6th 2023, 6:30:00 pm
43.95%
Financial Progress

11th Expenditure
of ₹ 6820661 (68.21 Lacs ) done.
Cummulative ₹ 129.37Lacs ( against 294.34Lacs )

2 years ago

on Tuesday, December 12th 2023, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Thursday, December 14th 2023, 6:30:00 pm
43.95%
Financial Progress

12th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 129.37Lacs ( against 294.34Lacs )

2 years ago

on Thursday, December 14th 2023, 6:30:00 pm
43.95%
Financial Progress

13th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 129.37Lacs ( against 294.34Lacs )

2 years ago

on Thursday, December 14th 2023, 6:30:00 pm
70.95%
Financial Progress

14th Expenditure
of ₹ 7948165 (79.48 Lacs ) done.
Cummulative ₹ 208.85Lacs ( against 294.34Lacs )

2 years ago

on Tuesday, January 23rd 2024, 6:30:00 pm
71.67%
Financial Progress

15th Expenditure
of ₹ 210085 (2.10 Lacs ) done.
Cummulative ₹ 210.95Lacs ( against 294.34Lacs )

2 years ago

on Monday, February 5th 2024, 6:30:00 pm
72.51%
Financial Progress

16th Expenditure
of ₹ 247691 (2.48 Lacs ) done.
Cummulative ₹ 213.43Lacs ( against 294.34Lacs )

2 years ago

on Wednesday, February 21st 2024, 6:30:00 pm
79.63%
Financial Progress

17th Expenditure
of ₹ 2096992 (20.97 Lacs ) done.
Cummulative ₹ 234.40Lacs ( against 294.34Lacs )

2 years ago

on Sunday, February 25th 2024, 6:30:00 pm
79.65%
Financial Progress

18th Expenditure
of ₹ 3188 (0.03 Lacs ) done.
Cummulative ₹ 234.43Lacs ( against 294.34Lacs )

2 years ago

on Sunday, February 25th 2024, 6:30:00 pm
79.66%
Financial Progress

19th Expenditure
of ₹ 3785 (0.04 Lacs ) done.
Cummulative ₹ 234.47Lacs ( against 294.34Lacs )

a year ago

on Friday, March 15th 2024, 6:30:00 pm
83.04%
Financial Progress

20th Expenditure
of ₹ 996850 (9.97 Lacs ) done.
Cummulative ₹ 244.43Lacs ( against 294.34Lacs )

a year ago

on Wednesday, March 20th 2024, 6:30:00 pm
83.89%
Financial Progress

21st Expenditure
of ₹ 248508 (2.49 Lacs ) done.
Cummulative ₹ 246.92Lacs ( against 294.34Lacs )

a year ago

on Wednesday, March 20th 2024, 6:30:00 pm
86.45%
Financial Progress

24th Expenditure
of ₹ 248508 (2.49 Lacs ) done.
Cummulative ₹ 254.44Lacs ( against 294.34Lacs )

a year ago

on Wednesday, March 20th 2024, 6:30:00 pm
83.92%
Financial Progress

22nd Expenditure
of ₹ 8337 (0.08 Lacs ) done.
Cummulative ₹ 247.00Lacs ( against 294.34Lacs )

a year ago

on Wednesday, March 20th 2024, 6:30:00 pm
85.60%
Financial Progress

23rd Expenditure
of ₹ 495592 (4.96 Lacs ) done.
Cummulative ₹ 251.96Lacs ( against 294.34Lacs )

a year ago

on Monday, June 17th 2024, 6:30:00 pm
86.95%
Financial Progress

26th Expenditure
of ₹ 112637 (1.13 Lacs ) done.
Cummulative ₹ 255.93Lacs ( against 294.34Lacs )

a year ago

on Monday, June 17th 2024, 6:30:00 pm
86.57%
Financial Progress

25th Expenditure
of ₹ 35476 (0.35 Lacs ) done.
Cummulative ₹ 254.80Lacs ( against 294.34Lacs )

a year ago

on Monday, August 19th 2024, 6:30:00 pm
87.83%
Financial Progress

27th Expenditure
of ₹ 260611 (2.61 Lacs ) done.
Cummulative ₹ 258.53Lacs ( against 294.34Lacs )

a year ago

on Sunday, September 8th 2024, 6:30:00 pm
87.92%
Financial Progress

28th Expenditure
of ₹ 24640 (0.25 Lacs ) done.
Cummulative ₹ 258.78Lacs ( against 294.34Lacs )

a year ago

on Monday, September 23rd 2024, 6:30:00 pm
89.58%
Financial Progress

30th Expenditure
of ₹ 245080 (2.45 Lacs ) done.
Cummulative ₹ 263.68Lacs ( against 294.34Lacs )

a year ago

on Monday, September 23rd 2024, 6:30:00 pm
88.75%
Financial Progress

29th Expenditure
of ₹ 245335 (2.45 Lacs ) done.
Cummulative ₹ 261.23Lacs ( against 294.34Lacs )

a year ago

on Sunday, September 29th 2024, 6:30:00 pm
90.40%
Financial Progress

31st Expenditure
of ₹ 241428 (2.41 Lacs ) done.
Cummulative ₹ 266.10Lacs ( against 294.34Lacs )

9 months ago

on Tuesday, December 3rd 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 4th time

7 months ago

on Thursday, January 23rd 2025, 6:30:00 pm
90.87%
Financial Progress

32nd Expenditure
of ₹ 136319 (1.36 Lacs ) done.
Cummulative ₹ 267.46Lacs ( against 294.34Lacs )

2 months ago

on Monday, June 30th 2025, 6:30:00 pm
91.80%
Financial Progress

33rd Expenditure
of ₹ 273442 (2.73 Lacs ) done.
Cummulative ₹ 270.19Lacs ( against 294.34Lacs )