Work Sanctioned
राज्य योजना के अन्तर्गत जनपद उत्तरकाशी के विधान सभा क्षेत्र यमुनोत्री के विकास खण्ड चिन्यालीसौड़ के अन्तर्गत पीपलमण्डी से स्यांसूमणी पुल तक मोटर मार्ग पर पी.सी. द्वारा सतह सुधार कार्य ।
on Friday, June 16th 2023, 5:01:10 am
Technical Sanction
of ₹ 273.8 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 3781/06 (36) याता.-(क्षे.का.)/2023
on Monday, July 24th 2023, 6:30:00 pm
1.66%
Financial Progress
1st Expenditure
of ₹ 489210 (4.89 Lacs ) done.
Cummulative ₹ 4.89Lacs ( against 294.34Lacs )
on Monday, July 24th 2023, 6:30:00 pm
3.32%
Financial Progress
2nd Expenditure
of ₹ 488501 (4.89 Lacs ) done.
Cummulative ₹ 9.78Lacs ( against 294.34Lacs )
on Sunday, July 30th 2023, 6:30:00 pm
3.32%
Financial Progress
3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 9.78Lacs ( against 294.34Lacs )
on Monday, September 25th 2023, 6:30:00 pm
20.57%
Financial Progress
6th Expenditure
of ₹ 4737634 (47.38 Lacs ) done.
Cummulative ₹ 60.56Lacs ( against 294.34Lacs )
on Monday, September 25th 2023, 6:30:00 pm
4.48%
Financial Progress
5th Expenditure
of ₹ 175514 (1.76 Lacs ) done.
Cummulative ₹ 13.18Lacs ( against 294.34Lacs )
on Monday, September 25th 2023, 6:30:00 pm
3.88%
Financial Progress
4th Expenditure
of ₹ 164680 (1.65 Lacs ) done.
Cummulative ₹ 11.42Lacs ( against 294.34Lacs )
on Thursday, September 28th 2023, 6:30:00 pm
20.57%
Financial Progress
7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 60.56Lacs ( against 294.34Lacs )
on Wednesday, October 4th 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Monday, October 9th 2023, 5:08:48 am
PWD UttarakahndPhoto (ID 24647) from Site Received
Uploader : Lokendra Singh, Additional Assistant Engineer Civil ,CD Uttarkashi
Landmark : 10
Remark : Pipal mandi to syashumani m/r p.c worl
on Tuesday, October 10th 2023, 8:38:38 am
PWD UttarakahndPhoto (ID 24739) from Site Received
Uploader : Lokendra Singh, Additional Assistant Engineer Civil ,CD Uttarkashi
Landmark : Km 11
Remark : Seal coat .. pipal mandi to syashumani motar road
on Wednesday, October 11th 2023, 9:01:22 am
PWD UttarakahndPhoto (ID 24818) from Site Received
Uploader : Lokendra Singh, Additional Assistant Engineer Civil ,CD Uttarkashi
Landmark : 7
Remark : Seal coat .. at pipalmandi to syashumani work ...
on Wednesday, October 18th 2023, 6:30:00 pm
20.64%
Financial Progress
8th Expenditure
of ₹ 20000 (0.20 Lacs ) done.
Cummulative ₹ 60.76Lacs ( against 294.34Lacs )
on Sunday, October 29th 2023, 6:30:00 pm
20.78%
Financial Progress
9th Expenditure
of ₹ 40500 (0.41 Lacs ) done.
Cummulative ₹ 61.16Lacs ( against 294.34Lacs )
on Monday, October 30th 2023, 6:30:00 pm
20.78%
Financial Progress
10th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 61.16Lacs ( against 294.34Lacs )
on Wednesday, November 1st 2023, 6:30:00 pm
55%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, November 6th 2023, 6:30:00 pm
43.95%
Financial Progress
11th Expenditure
of ₹ 6820661 (68.21 Lacs ) done.
Cummulative ₹ 129.37Lacs ( against 294.34Lacs )
on Tuesday, December 12th 2023, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 3rd time
on Thursday, December 14th 2023, 6:30:00 pm
43.95%
Financial Progress
12th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 129.37Lacs ( against 294.34Lacs )
on Thursday, December 14th 2023, 6:30:00 pm
43.95%
Financial Progress
13th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 129.37Lacs ( against 294.34Lacs )
on Thursday, December 14th 2023, 6:30:00 pm
70.95%
Financial Progress
14th Expenditure
of ₹ 7948165 (79.48 Lacs ) done.
Cummulative ₹ 208.85Lacs ( against 294.34Lacs )
on Tuesday, January 23rd 2024, 6:30:00 pm
71.67%
Financial Progress
15th Expenditure
of ₹ 210085 (2.10 Lacs ) done.
Cummulative ₹ 210.95Lacs ( against 294.34Lacs )
on Monday, February 5th 2024, 6:30:00 pm
72.51%
Financial Progress
16th Expenditure
of ₹ 247691 (2.48 Lacs ) done.
Cummulative ₹ 213.43Lacs ( against 294.34Lacs )
on Wednesday, February 21st 2024, 6:30:00 pm
79.63%
Financial Progress
17th Expenditure
of ₹ 2096992 (20.97 Lacs ) done.
Cummulative ₹ 234.40Lacs ( against 294.34Lacs )
on Sunday, February 25th 2024, 6:30:00 pm
79.65%
Financial Progress
18th Expenditure
of ₹ 3188 (0.03 Lacs ) done.
Cummulative ₹ 234.43Lacs ( against 294.34Lacs )
on Sunday, February 25th 2024, 6:30:00 pm
79.66%
Financial Progress
19th Expenditure
of ₹ 3785 (0.04 Lacs ) done.
Cummulative ₹ 234.47Lacs ( against 294.34Lacs )
on Friday, March 15th 2024, 6:30:00 pm
83.04%
Financial Progress
20th Expenditure
of ₹ 996850 (9.97 Lacs ) done.
Cummulative ₹ 244.43Lacs ( against 294.34Lacs )
on Wednesday, March 20th 2024, 6:30:00 pm
83.89%
Financial Progress
21st Expenditure
of ₹ 248508 (2.49 Lacs ) done.
Cummulative ₹ 246.92Lacs ( against 294.34Lacs )
on Wednesday, March 20th 2024, 6:30:00 pm
86.45%
Financial Progress
24th Expenditure
of ₹ 248508 (2.49 Lacs ) done.
Cummulative ₹ 254.44Lacs ( against 294.34Lacs )
on Wednesday, March 20th 2024, 6:30:00 pm
83.92%
Financial Progress
22nd Expenditure
of ₹ 8337 (0.08 Lacs ) done.
Cummulative ₹ 247.00Lacs ( against 294.34Lacs )
on Wednesday, March 20th 2024, 6:30:00 pm
85.60%
Financial Progress
23rd Expenditure
of ₹ 495592 (4.96 Lacs ) done.
Cummulative ₹ 251.96Lacs ( against 294.34Lacs )
on Monday, June 17th 2024, 6:30:00 pm
86.95%
Financial Progress
26th Expenditure
of ₹ 112637 (1.13 Lacs ) done.
Cummulative ₹ 255.93Lacs ( against 294.34Lacs )
on Monday, June 17th 2024, 6:30:00 pm
86.57%
Financial Progress
25th Expenditure
of ₹ 35476 (0.35 Lacs ) done.
Cummulative ₹ 254.80Lacs ( against 294.34Lacs )
on Monday, August 19th 2024, 6:30:00 pm
87.83%
Financial Progress
27th Expenditure
of ₹ 260611 (2.61 Lacs ) done.
Cummulative ₹ 258.53Lacs ( against 294.34Lacs )
on Sunday, September 8th 2024, 6:30:00 pm
87.92%
Financial Progress
28th Expenditure
of ₹ 24640 (0.25 Lacs ) done.
Cummulative ₹ 258.78Lacs ( against 294.34Lacs )
on Monday, September 23rd 2024, 6:30:00 pm
89.58%
Financial Progress
30th Expenditure
of ₹ 245080 (2.45 Lacs ) done.
Cummulative ₹ 263.68Lacs ( against 294.34Lacs )
on Monday, September 23rd 2024, 6:30:00 pm
88.75%
Financial Progress
29th Expenditure
of ₹ 245335 (2.45 Lacs ) done.
Cummulative ₹ 261.23Lacs ( against 294.34Lacs )
on Sunday, September 29th 2024, 6:30:00 pm
90.40%
Financial Progress
31st Expenditure
of ₹ 241428 (2.41 Lacs ) done.
Cummulative ₹ 266.10Lacs ( against 294.34Lacs )
on Tuesday, December 3rd 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 4th time
on Thursday, January 23rd 2025, 6:30:00 pm
90.87%
Financial Progress
32nd Expenditure
of ₹ 136319 (1.36 Lacs ) done.
Cummulative ₹ 267.46Lacs ( against 294.34Lacs )
on Monday, June 30th 2025, 6:30:00 pm
91.80%
Financial Progress
33rd Expenditure
of ₹ 273442 (2.73 Lacs ) done.
Cummulative ₹ 270.19Lacs ( against 294.34Lacs )