12 years ago

on Friday, December 13th 2013, 6:30:00 pm
Work Sanctioned
माननीय मुख्यमन्त्री घोषणा संख्या 238/2013 के अन्तर्गत जनपद उत्तरकाशी के विकास खण्ड नौगांव में भंकोली से छमरोटा मोटर मार्ग का निर्माण।

11 years ago

on Friday, February 28th 2014, 6:30:00 pm
0.18%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 55.62Lacs )

11 years ago

on Tuesday, December 16th 2014, 6:30:00 pm

Technical Sanction
of ₹ 55.62 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. E.E letter No 1696/1C

9 years ago

on Monday, February 29th 2016, 6:30:00 pm
2.35%
Financial Progress

2nd Expenditure
of ₹ 120981 (1.21 Lacs ) done.
Cummulative ₹ 1.31Lacs ( against 55.62Lacs )

9 years ago

on Sunday, July 31st 2016, 6:30:00 pm
3.89%
Financial Progress

3rd Expenditure
of ₹ 85383 (0.85 Lacs ) done.
Cummulative ₹ 2.16Lacs ( against 55.62Lacs )

9 years ago

on Friday, September 30th 2016, 6:30:00 pm
6.06%
Financial Progress

4th Expenditure
of ₹ 120899 (1.21 Lacs ) done.
Cummulative ₹ 3.37Lacs ( against 55.62Lacs )

2 years ago

on Thursday, June 29th 2023, 6:30:00 pm
6.24%
Financial Progress

5th Expenditure
of ₹ 10080 (0.10 Lacs ) done.
Cummulative ₹ 3.47Lacs ( against 55.62Lacs )

a year ago

on Thursday, July 11th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

6 months ago

on Thursday, February 27th 2025, 6:30:00 pm
6.24%
Financial Progress

6th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 3.47Lacs ( against 55.62Lacs )

5 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
6.30%
Financial Progress

7th Expenditure
of ₹ 3225 (0.03 Lacs ) done.
Cummulative ₹ 3.51Lacs ( against 55.62Lacs )

5 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
6.42%
Financial Progress

8th Expenditure
of ₹ 6531 (0.07 Lacs ) done.
Cummulative ₹ 3.57Lacs ( against 55.62Lacs )

5 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
6.54%
Financial Progress

9th Expenditure
of ₹ 6450 (0.06 Lacs ) done.
Cummulative ₹ 3.64Lacs ( against 55.62Lacs )

5 months ago

on Tuesday, March 25th 2025, 6:30:00 pm
8.30%
Financial Progress

10th Expenditure
of ₹ 97970 (0.98 Lacs ) done.
Cummulative ₹ 4.62Lacs ( against 55.62Lacs )

5 months ago

on Wednesday, March 26th 2025, 6:30:00 pm
9.40%
Financial Progress

11th Expenditure
of ₹ 61360 (0.61 Lacs ) done.
Cummulative ₹ 5.23Lacs ( against 55.62Lacs )

5 months ago

on Wednesday, March 26th 2025, 6:30:00 pm
9.68%
Financial Progress

12th Expenditure
of ₹ 15257 (0.15 Lacs ) done.
Cummulative ₹ 5.38Lacs ( against 55.62Lacs )

5 months ago

on Sunday, March 30th 2025, 6:30:00 pm
9.68%
Financial Progress

13th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 5.38Lacs ( against 55.62Lacs )