Work Sanctioned
माननीय मुख्यमंत्री घोषणा संख्या 1060/2021 के अन्तर्गत जनपद चमोली के विधानसभा क्षेत्र कर्णप्रयाग में विकासखण्ड कर्णप्राग के रामबोरी से ग्राम सेम तक मोटर मार्ग का निर्माण कार्य।। (द्वितीय चरण ,स्टेज-।)
on Tuesday, November 26th 2024, 6:30:00 pm
21.31%
Financial Progress
1st Expenditure
of ₹ 2280350 (22.80 Lacs ) done.
Cummulative ₹ 22.80Lacs ( against 107Lacs )
on Thursday, November 28th 2024, 6:30:00 pm
24.41%
Financial Progress
4th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 26.12Lacs ( against 107Lacs )
on Thursday, November 28th 2024, 6:30:00 pm
24.41%
Financial Progress
3rd Expenditure
of ₹ 298603 (2.99 Lacs ) done.
Cummulative ₹ 26.12Lacs ( against 107Lacs )
on Thursday, November 28th 2024, 6:30:00 pm
21.62%
Financial Progress
2nd Expenditure
of ₹ 32922 (0.33 Lacs ) done.
Cummulative ₹ 23.13Lacs ( against 107Lacs )
on Tuesday, December 3rd 2024, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, December 22nd 2024, 6:30:00 pm
25.78%
Financial Progress
8th Expenditure
of ₹ 92365 (0.92 Lacs ) done.
Cummulative ₹ 27.59Lacs ( against 107Lacs )
on Sunday, December 22nd 2024, 6:30:00 pm
24.92%
Financial Progress
7th Expenditure
of ₹ 23023 (0.23 Lacs ) done.
Cummulative ₹ 26.66Lacs ( against 107Lacs )
on Sunday, December 22nd 2024, 6:30:00 pm
24.71%
Financial Progress
6th Expenditure
of ₹ 21568 (0.22 Lacs ) done.
Cummulative ₹ 26.43Lacs ( against 107Lacs )
on Sunday, December 22nd 2024, 6:30:00 pm
24.50%
Financial Progress
5th Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 26.22Lacs ( against 107Lacs )
on Friday, December 27th 2024, 6:30:00 pm
25.78%
Financial Progress
9th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 27.59Lacs ( against 107Lacs )
on Tuesday, December 31st 2024, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, January 20th 2025, 6:30:00 pm
26.60%
Financial Progress
10th Expenditure
of ₹ 87615 (0.88 Lacs ) done.
Cummulative ₹ 28.46Lacs ( against 107Lacs )
on Tuesday, January 21st 2025, 6:30:00 pm
39.33%
Financial Progress
11th Expenditure
of ₹ 1362369 (13.62 Lacs ) done.
Cummulative ₹ 42.09Lacs ( against 107Lacs )
on Friday, January 31st 2025, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 3rd time
on Thursday, February 13th 2025, 6:30:00 pm
39.42%
Financial Progress
12th Expenditure
of ₹ 9650 (0.10 Lacs ) done.
Cummulative ₹ 42.18Lacs ( against 107Lacs )
on Monday, February 17th 2025, 6:30:00 pm
39.57%
Financial Progress
13th Expenditure
of ₹ 15228 (0.15 Lacs ) done.
Cummulative ₹ 42.34Lacs ( against 107Lacs )
on Thursday, February 27th 2025, 6:30:00 pm
54.66%
Financial Progress
14th Expenditure
of ₹ 1614594 (16.15 Lacs ) done.
Cummulative ₹ 58.48Lacs ( against 107Lacs )
on Friday, February 28th 2025, 6:30:00 pm
55%
Physical Progress
Physical Progress Reported at 4th time
on Thursday, March 27th 2025, 6:30:00 pm
54.75%
Financial Progress
15th Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 58.58Lacs ( against 107Lacs )
on Friday, March 28th 2025, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 5th time
on Wednesday, May 7th 2025, 6:30:00 pm
55.21%
Financial Progress
16th Expenditure
of ₹ 48885 (0.49 Lacs ) done.
Cummulative ₹ 59.07Lacs ( against 107Lacs )
on Thursday, May 15th 2025, 6:30:00 pm
68.34%
Financial Progress
17th Expenditure
of ₹ 1404790 (14.05 Lacs ) done.
Cummulative ₹ 73.12Lacs ( against 107Lacs )
on Wednesday, June 25th 2025, 6:30:00 pm
73.02%
Financial Progress
18th Expenditure
of ₹ 500819 (5.01 Lacs ) done.
Cummulative ₹ 78.13Lacs ( against 107Lacs )
on Wednesday, July 9th 2025, 6:30:00 pm
73.96%
Financial Progress
20th Expenditure
of ₹ 49560 (0.50 Lacs ) done.
Cummulative ₹ 79.14Lacs ( against 107Lacs )
on Wednesday, July 9th 2025, 6:30:00 pm
73.50%
Financial Progress
19th Expenditure
of ₹ 51688 (0.52 Lacs ) done.
Cummulative ₹ 78.64Lacs ( against 107Lacs )
on Wednesday, July 30th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 6th time
on Tuesday, August 12th 2025, 6:30:00 pm
78.08%
Financial Progress
22nd Expenditure
of ₹ 47717 (0.48 Lacs ) done.
Cummulative ₹ 83.55Lacs ( against 107Lacs )
on Tuesday, August 12th 2025, 6:30:00 pm
77.64%
Financial Progress
21st Expenditure
of ₹ 393014 (3.93 Lacs ) done.
Cummulative ₹ 83.07Lacs ( against 107Lacs )