on Friday, December 13th 2013, 6:30:00 pm
Work Sanctioned
मु0मं0घो0 संख्या 376/2012 के अन्तर्गत नाकोट बैण्ड से खोला तक मोटर मार्ग का नव निर्माण।
on Friday, February 28th 2014, 6:30:00 pm
0.22%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 45Lacs )
on Friday, August 6th 2021, 5:22:04 am
PWD UttarakahndPhoto (ID 493) from Site Received
Uploader : Ashok Kumar Maikhuri, JE Civil (Samvida) ,TD Chakrata
Landmark : 0.00 Nakot
Remark : Visit of alignment dispute
on Friday, August 6th 2021, 5:24:35 am
PWD UttarakahndPhoto (ID 494) from Site Received
Uploader : Ashok Kumar Maikhuri, JE Civil (Samvida) ,TD Chakrata
Landmark : 0.00 Nakot
Remark : Alignment dispute