Work Sanctioned
कर्णप्रयाग-नौटी-पैठाणी मोटर मार्ग के कि॰मी॰ 25 में दीवार निर्माण का कार्य।
on Tuesday, June 15th 2021, 1:36:08 pm
Technical Sanction
of ₹ 1.5 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 952/29C
on Friday, July 30th 2021, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, August 29th 2021, 7:18:38 am
PWD UttarakahndPhoto (ID 1134) from Site Received
Uploader : Prateek Aggarwal, Additional Assistant Engineer Civil ,PD Haridwar
Landmark : Nil
Remark : Work in progress
on Tuesday, August 31st 2021, 5:31:09 am
PWD UttarakahndPhoto (ID 1162) from Site Received
Uploader : Amit Kumar Patel, Executive Engineer Civil ,CD Kapkot
Landmark : KNP km 25
Remark : District plan work
on Saturday, October 30th 2021, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, December 2nd 2021, 6:30:00 pm
95.12%
Financial Progress
1st Expenditure
of ₹ 142678 (1.43 Lacs ) done.
Cummulative ₹ 1.43Lacs ( against 1.5Lacs )
on Tuesday, March 29th 2022, 6:30:00 pm
99.88%
Financial Progress
2nd Expenditure
of ₹ 7144 (0.07 Lacs ) done.
Cummulative ₹ 1.50Lacs ( against 1.5Lacs )