10 years ago

on Thursday, June 18th 2015, 6:30:00 pm
Work Sanctioned
मुख्यमंत्री घोषणा के अन्तर्गत जनपद रूद्रप्रयाग के विधानसभा क्षेत्र केदारनाथ के विकासखण्ड अगस्त्यमुनि में मणिगुह मोटर मार्ग से स्याल डोभा होते हुए खाली खमोली तक मोटर मार्ग का नव निर्माण (घो0 सं0 834/2015)

6 years ago

on Monday, January 6th 2020, 6:30:00 pm

Technical Sanction
of ₹ 0.72 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 92/1C

5 years ago

on Sunday, May 31st 2020, 6:30:00 pm
2.11%
Financial Progress

1st Expenditure
of ₹ 39984 (0.40 Lacs ) done.
Cummulative ₹ 0.40Lacs ( against 18.93Lacs )

3 years ago

on Monday, May 30th 2022, 6:30:00 pm
2.54%
Financial Progress

2nd Expenditure
of ₹ 8122 (0.08 Lacs ) done.
Cummulative ₹ 0.48Lacs ( against 18.93Lacs )

3 years ago

on Monday, June 20th 2022, 6:30:00 pm
5.13%
Financial Progress

3rd Expenditure
of ₹ 49038 (0.49 Lacs ) done.
Cummulative ₹ 0.97Lacs ( against 18.93Lacs )

2 years ago

on Tuesday, April 18th 2023, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 1st time