on Tuesday, December 22nd 2015, 6:30:00 pm
Work Sanctioned
ग्राम सभा सांदर में सड़क निर्माण।
on Sunday, September 18th 2016, 6:30:00 pm
Technical Sanction
of ₹ 14.9 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 3402/1C
on Tuesday, February 28th 2017, 6:30:00 pm
0.37%
Financial Progress
1st Expenditure
of ₹ 18223 (0.18 Lacs ) done.
Cummulative ₹ 0.18Lacs ( against 48.95Lacs )
on Friday, November 30th 2018, 6:30:00 pm
21.07%
Financial Progress
2nd Expenditure
of ₹ 1013026 (10.13 Lacs ) done.
Cummulative ₹ 10.31Lacs ( against 48.95Lacs )
on Sunday, December 23rd 2018, 6:30:00 pm
Technical Sanction
of ₹ 34.05 Lacs
2nd Technical Sanction of Work after survey,detailed design and analysis by Latter No. 297/1C (Camp)
on Thursday, October 31st 2019, 6:30:00 pm
30.54%
Financial Progress
3rd Expenditure
of ₹ 463460 (4.63 Lacs ) done.
Cummulative ₹ 14.95Lacs ( against 48.95Lacs )
on Monday, August 31st 2020, 6:30:00 pm
45.78%
Financial Progress
4th Expenditure
of ₹ 746323 (7.46 Lacs ) done.
Cummulative ₹ 22.41Lacs ( against 48.95Lacs )
on Sunday, March 27th 2022, 6:30:00 pm
51.36%
Financial Progress
5th Expenditure
of ₹ 273251 (2.73 Lacs ) done.
Cummulative ₹ 25.14Lacs ( against 48.95Lacs )
on Wednesday, March 29th 2023, 6:30:00 pm
74.40%
Financial Progress
6th Expenditure
of ₹ 1127719 (11.28 Lacs ) done.
Cummulative ₹ 36.42Lacs ( against 48.95Lacs )
on Tuesday, January 30th 2024, 6:30:00 pm
88.97%
Financial Progress
7th Expenditure
of ₹ 713105 (7.13 Lacs ) done.
Cummulative ₹ 43.55Lacs ( against 48.95Lacs )
on Wednesday, April 24th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time