3 years ago

on Thursday, January 6th 2022, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद रूद्रप्रयाग के विधानसभा क्षेत्र रूद्रप्रयाग के विकासखण्ड अगस्त्यमुनि में डूंगरा (बच्छणस्यूं) से आरस्यूं तक मोटर मार्ग का नव निर्माण (द्वितीय चरण स्टेज-।)

3 years ago

on Tuesday, March 15th 2022, 6:47:51 am

Technical Sanction
of ₹ 97.5 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 834/1C

2 years ago

on Tuesday, January 24th 2023, 6:30:00 pm
0.08%
Financial Progress

1st Expenditure
of ₹ 7570 (0.08 Lacs ) done.
Cummulative ₹ 0.08Lacs ( against 97.51Lacs )

2 years ago

on Monday, January 30th 2023, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Monday, February 27th 2023, 6:30:00 pm
0.27%
Financial Progress

2nd Expenditure
of ₹ 18876 (0.19 Lacs ) done.
Cummulative ₹ 0.26Lacs ( against 97.51Lacs )

2 years ago

on Wednesday, March 29th 2023, 6:30:00 pm
35.40%
Financial Progress

3rd Expenditure
of ₹ 3425124 (34.25 Lacs ) done.
Cummulative ₹ 34.52Lacs ( against 97.51Lacs )

2 years ago

on Wednesday, April 19th 2023, 6:30:00 pm
40%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Tuesday, May 30th 2023, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Tuesday, May 30th 2023, 6:30:00 pm
36.95%
Financial Progress

4th Expenditure
of ₹ 151512 (1.52 Lacs ) done.
Cummulative ₹ 36.03Lacs ( against 97.51Lacs )

2 years ago

on Thursday, June 29th 2023, 6:30:00 pm
67.16%
Financial Progress

5th Expenditure
of ₹ 2946078 (29.46 Lacs ) done.
Cummulative ₹ 65.49Lacs ( against 97.51Lacs )

2 years ago

on Monday, September 25th 2023, 6:30:00 pm
67.27%
Financial Progress

6th Expenditure
of ₹ 9910 (0.10 Lacs ) done.
Cummulative ₹ 65.59Lacs ( against 97.51Lacs )

2 years ago

on Tuesday, October 24th 2023, 6:30:00 pm
69.07%
Financial Progress

7th Expenditure
of ₹ 176203 (1.76 Lacs ) done.
Cummulative ₹ 67.35Lacs ( against 97.51Lacs )

2 years ago

on Monday, October 30th 2023, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Wednesday, December 13th 2023, 6:30:00 pm
70.04%
Financial Progress

8th Expenditure
of ₹ 94754 (0.95 Lacs ) done.
Cummulative ₹ 68.30Lacs ( against 97.51Lacs )

a year ago

on Tuesday, January 30th 2024, 6:30:00 pm
91.53%
Financial Progress

9th Expenditure
of ₹ 2094758 (20.95 Lacs ) done.
Cummulative ₹ 89.25Lacs ( against 97.51Lacs )

a year ago

on Wednesday, February 28th 2024, 6:30:00 pm
93.17%
Financial Progress

10th Expenditure
of ₹ 160500 (1.60 Lacs ) done.
Cummulative ₹ 90.85Lacs ( against 97.51Lacs )

9 months ago

on Sunday, August 25th 2024, 6:30:00 pm
93.25%
Financial Progress

11th Expenditure
of ₹ 7437 (0.07 Lacs ) done.
Cummulative ₹ 90.93Lacs ( against 97.51Lacs )

2 months ago

on Monday, March 3rd 2025, 6:30:00 pm
95.05%
Financial Progress

12th Expenditure
of ₹ 175447 (1.75 Lacs ) done.
Cummulative ₹ 92.68Lacs ( against 97.51Lacs )

a month ago

on Monday, April 14th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 5th time