Refresh data
on Thursday, March 30th 2023, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा संख्या 709/2017 के अन्तर्गत जनपद रूद्रप्रयाग के विधानसभा क्षेत्र रूद्रप्रयाग के विकासखण्ड अगस्त्यमुनि में खांकरा बरसूडी मोटर मार्ग से राजकीय इण्टर कालेज तक मोटर मार्ग के नव निर्माण (द्वितीय चरण स्टेज-।।)
on Wednesday, May 17th 2023, 12:55:53 pm
Technical Sanction
of ₹ 117.16 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2487/554Yata-7/2023
on Friday, September 29th 2023, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 1st time
on Monday, October 30th 2023, 6:30:00 pm
35.94%
Financial Progress
1st Expenditure
of ₹ 4210552 (42.11 Lacs ) done.
Cummulative ₹ 42.11Lacs ( against 117.16Lacs )
on Monday, October 30th 2023, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, November 20th 2023, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 3rd time
on Wednesday, November 29th 2023, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 4th time
on Saturday, December 30th 2023, 6:30:00 pm
36.00%
Financial Progress
2nd Expenditure
of ₹ 7107 (0.07 Lacs ) done.
Cummulative ₹ 42.18Lacs ( against 117.16Lacs )
on Wednesday, January 17th 2024, 6:30:00 pm
56.05%
Financial Progress
3rd Expenditure
of ₹ 2349346 (23.49 Lacs ) done.
Cummulative ₹ 65.67Lacs ( against 117.16Lacs )
on Monday, March 25th 2024, 6:30:00 pm
71.27%
Financial Progress
4th Expenditure
of ₹ 1782668 (17.83 Lacs ) done.
Cummulative ₹ 83.50Lacs ( against 117.16Lacs )
on Saturday, March 30th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 5th time
on Monday, April 29th 2024, 6:30:00 pm
81.64%
Financial Progress
5th Expenditure
of ₹ 1214825 (12.15 Lacs ) done.
Cummulative ₹ 95.64Lacs ( against 117.16Lacs )
on Tuesday, May 14th 2024, 6:30:00 pm
93.28%
Financial Progress
6th Expenditure
of ₹ 1364597 (13.65 Lacs ) done.
Cummulative ₹ 109.29Lacs ( against 117.16Lacs )
on Monday, March 24th 2025, 6:30:00 pm
96.90%
Financial Progress
7th Expenditure
of ₹ 423704 (4.24 Lacs ) done.
Cummulative ₹ 113.53Lacs ( against 117.16Lacs )