Refresh data
on Tuesday, February 26th 2019, 6:30:00 pm
Work Sanctioned
सल्ट में जैनल-देघाट मुख्य मार्ग से डुंगरी तक मोटर मार्ग का सुधारीकरण।
on Monday, June 3rd 2019, 6:30:00 pm
Technical Sanction
of ₹ 26.63 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1516/4C
on Saturday, February 29th 2020, 6:30:00 pm
0.30%
Financial Progress
1st Expenditure
of ₹ 7882 (0.08 Lacs ) done.
Cummulative ₹ 0.08Lacs ( against 26.63Lacs )
on Sunday, May 31st 2020, 6:30:00 pm
34.09%
Financial Progress
2nd Expenditure
of ₹ 900000 (9.00 Lacs ) done.
Cummulative ₹ 9.08Lacs ( against 26.63Lacs )
on Saturday, October 31st 2020, 6:30:00 pm
58.30%
Financial Progress
3rd Expenditure
of ₹ 644594 (6.45 Lacs ) done.
Cummulative ₹ 15.52Lacs ( against 26.63Lacs )
on Monday, August 2nd 2021, 6:30:00 pm
60.77%
Financial Progress
4th Expenditure
of ₹ 65883 (0.66 Lacs ) done.
Cummulative ₹ 16.18Lacs ( against 26.63Lacs )
on Tuesday, July 25th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time