on Tuesday, May 12th 2020, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा सं0 529/2017 के अन्तगत जनपद अल्मोड़ा के विधानसभा क्षेत्र सल्ट में महरौली चित्तौड़खाल मोटर मार्ग का नव निर्माण कार्य। (किमी0 3 से 11.975)
on Monday, September 28th 2020, 10:52:31 am
Technical Sanction
of ₹ 570.9 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 3495/535Yata-A/2020
on Monday, November 30th 2020, 6:30:00 pm
0.28%
Financial Progress
1st Expenditure
of ₹ 175065 (1.75 Lacs ) done.
Cummulative ₹ 1.75Lacs ( against 618.2Lacs )
on Sunday, February 28th 2021, 6:30:00 pm
0.30%
Financial Progress
2nd Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 1.85Lacs ( against 618.2Lacs )
on Tuesday, August 24th 2021, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, September 29th 2021, 6:30:00 pm
6.49%
Financial Progress
3rd Expenditure
of ₹ 3828832 (38.29 Lacs ) done.
Cummulative ₹ 40.14Lacs ( against 618.2Lacs )
on Friday, October 1st 2021, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, December 1st 2021, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 3rd time
on Sunday, December 26th 2021, 4:43:09 am
PWD UttarakahndPhoto (ID 3913) from Site Received
Uploader : Narendra Singh Rawat, Assistant Engineer Civil ,CD Kashipur
Landmark : Km 6
Remark : Constn of mahrauli chittorkhal m r
on Sunday, December 26th 2021, 4:52:32 am
PWD UttarakahndPhoto (ID 3914) from Site Received
Uploader : Narendra Singh Rawat, Assistant Engineer Civil ,CD Kashipur
Landmark : Km7
Remark : Mahrauli chittorkhal m r under constn.
on Sunday, December 26th 2021, 10:44:39 am
PWD UttarakahndPhoto (ID 4528) from Site Received
Uploader : Narendra Singh Rawat, Assistant Engineer Civil ,CD Kashipur
Landmark : Km 12
Remark : C/o mahrauli chittorkhal m r
on Sunday, December 26th 2021, 10:56:46 am
PWD UttarakahndPhoto (ID 4529) from Site Received
Uploader : Narendra Singh Rawat, Assistant Engineer Civil ,CD Kashipur
Landmark : Km 12
Remark : Dry Retaining Wall at km 12 pf mahrauli chittorkhal m r
on Saturday, February 26th 2022, 12:50:01 pm
PWD UttarakahndPhoto (ID 4532) from Site Received
Uploader : Narendra Singh Rawat, Assistant Engineer Civil ,CD Kashipur
Landmark : Km11.5000
Remark : Inspection by c e sir
on Friday, March 4th 2022, 6:30:00 pm
55%
Physical Progress
Physical Progress Reported at 4th time
on Wednesday, March 30th 2022, 6:30:00 pm
14.54%
Financial Progress
4th Expenditure
of ₹ 4973691 (49.74 Lacs ) done.
Cummulative ₹ 89.88Lacs ( against 618.2Lacs )
on Saturday, May 14th 2022, 1:50:52 pm
PWD UttarakahndPhoto (ID 7203) from Site Received
Uploader : Atar Singh, Additional Assistant Engineer Civil ,CD Ramnagar
Landmark : Km 8
Remark : Mahroli to chttokal m.r site visit
on Thursday, August 18th 2022, 7:39:50 am
PWD UttarakahndPhoto (ID 7210) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Km8 chainage 31/32
Remark : Width checking
on Thursday, August 18th 2022, 7:40:45 am
PWD UttarakahndPhoto (ID 7207) from Site Received
Uploader : Atar Singh, Additional Assistant Engineer Civil ,CD Ramnagar
Landmark : Km9×/s-8/32
Remark : Site visit. Mahroli to chttokal m.r
on Thursday, August 18th 2022, 7:51:17 am
PWD UttarakahndPhoto (ID 7209) from Site Received
Uploader : Atar Singh, Additional Assistant Engineer Civil ,CD Ramnagar
Landmark : Km9 8/17 mahroli to chttokal m.r
Remark : Mahroli to chttokal m.r
on Saturday, September 10th 2022, 5:47:51 am
PWD UttarakahndPhoto (ID 7868) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Chanage 11/27-28
Remark : Width checking of foundation
on Sunday, October 30th 2022, 6:30:00 pm
20.68%
Financial Progress
5th Expenditure
of ₹ 3796460 (37.96 Lacs ) done.
Cummulative ₹ 127.84Lacs ( against 618.2Lacs )
on Saturday, December 3rd 2022, 6:14:59 am
PWD UttarakahndPhoto (ID 12424) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Ch 6/31-32
Remark : Width checking at HP Band
on Tuesday, December 27th 2022, 5:10:06 am
PWD UttarakahndPhoto (ID 15278) from Site Received
Uploader : Atar Singh, Additional Assistant Engineer Civil ,CD Ramnagar
Landmark : Km 7 x/s 6/2 scupper work in progress
Remark : Scupper work in progress
on Tuesday, December 27th 2022, 5:11:35 am
PWD UttarakahndPhoto (ID 14738) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Chainage 10/24
Remark : Steel checking
on Monday, January 2nd 2023, 6:30:00 pm
20.72%
Financial Progress
6th Expenditure
of ₹ 23077 (0.23 Lacs ) done.
Cummulative ₹ 128.07Lacs ( against 618.2Lacs )
on Tuesday, January 3rd 2023, 6:30:00 pm
75%
Physical Progress
Physical Progress Reported at 5th time
on Monday, January 23rd 2023, 9:33:02 am
PWD UttarakahndPhoto (ID 15719) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Ch 5/37-38
Remark : Measurement checking
on Monday, January 23rd 2023, 11:07:10 am
PWD UttarakahndPhoto (ID 15723) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Ch 11/11
Remark : Width checking
on Tuesday, January 31st 2023, 6:30:00 pm
20.72%
Financial Progress
7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 128.07Lacs ( against 618.2Lacs )
on Tuesday, January 31st 2023, 6:30:00 pm
20.73%
Financial Progress
8th Expenditure
of ₹ 9556 (0.10 Lacs ) done.
Cummulative ₹ 128.17Lacs ( against 618.2Lacs )
on Tuesday, February 28th 2023, 6:30:00 pm
20.75%
Financial Progress
9th Expenditure
of ₹ 14000 (0.14 Lacs ) done.
Cummulative ₹ 128.31Lacs ( against 618.2Lacs )
on Thursday, March 30th 2023, 6:30:00 pm
32.60%
Financial Progress
10th Expenditure
of ₹ 7320447 (73.20 Lacs ) done.
Cummulative ₹ 201.51Lacs ( against 618.2Lacs )
on Tuesday, April 4th 2023, 7:21:40 am
PWD UttarakahndPhoto (ID 19088) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Chanaige 5/20-21
Remark : Steel checking
on Friday, June 2nd 2023, 6:30:00 pm
85%
Physical Progress
Physical Progress Reported at 6th time
on Saturday, June 24th 2023, 5:32:41 am
PWD UttarakahndPhoto (ID 21686) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Ch11/25-26
Remark : Muck disposal point
on Saturday, June 24th 2023, 5:40:42 am
PWD UttarakahndPhoto (ID 21687) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Ch 11/3
Remark : Measurement checking
on Saturday, June 24th 2023, 5:43:02 am
PWD UttarakahndPhoto (ID 21694) from Site Received
Uploader : Atar Singh, Additional Assistant Engineer Civil ,CD Ramnagar
Landmark : 10/13
Remark : Muck disposal no2
on Saturday, June 24th 2023, 6:49:36 am
PWD UttarakahndPhoto (ID 21701) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Ch 6/35-36
Remark : Work
on Saturday, June 24th 2023, 6:53:27 am
PWD UttarakahndPhoto (ID 21703) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Ch6/37-38
Remark : Muck disposal point
on Saturday, June 24th 2023, 7:05:21 am
PWD UttarakahndPhoto (ID 21705) from Site Received
Uploader : Satnam Singh, Assistant Engineer Civil ,CD Kashipur
Landmark : Ch 5/21-22
Remark : Measurement checking
on Thursday, August 3rd 2023, 6:30:00 pm
32.63%
Financial Progress
11th Expenditure
of ₹ 21000 (0.21 Lacs ) done.
Cummulative ₹ 201.72Lacs ( against 618.2Lacs )
on Thursday, August 3rd 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 7th time
on Tuesday, September 5th 2023, 6:30:00 pm
32.73%
Financial Progress
12th Expenditure
of ₹ 63085 (0.63 Lacs ) done.
Cummulative ₹ 202.35Lacs ( against 618.2Lacs )
on Friday, September 29th 2023, 6:30:00 pm
50.48%
Financial Progress
13th Expenditure
of ₹ 10972129 (109.72 Lacs ) done.
Cummulative ₹ 312.07Lacs ( against 618.2Lacs )
on Thursday, January 4th 2024, 6:30:00 pm
53.80%
Financial Progress
14th Expenditure
of ₹ 2052084 (20.52 Lacs ) done.
Cummulative ₹ 332.59Lacs ( against 618.2Lacs )
on Friday, January 26th 2024, 6:30:00 pm
53.87%
Financial Progress
15th Expenditure
of ₹ 41432 (0.41 Lacs ) done.
Cummulative ₹ 333.01Lacs ( against 618.2Lacs )
on Tuesday, January 30th 2024, 6:30:00 pm
54.13%
Financial Progress
16th Expenditure
of ₹ 163135 (1.63 Lacs ) done.
Cummulative ₹ 334.64Lacs ( against 618.2Lacs )
on Friday, March 1st 2024, 9:43:38 am
PWD UttarakahndPhoto (ID 36473) from Site Received
Uploader : Mahendra Pal, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 8hm 6-8
Remark : Site visit with SE sir
on Monday, March 11th 2024, 6:30:00 pm
54.24%
Financial Progress
17th Expenditure
of ₹ 66835 (0.67 Lacs ) done.
Cummulative ₹ 335.31Lacs ( against 618.2Lacs )
on Saturday, March 30th 2024, 6:30:00 pm
54.72%
Financial Progress
18th Expenditure
of ₹ 296138 (2.96 Lacs ) done.
Cummulative ₹ 338.27Lacs ( against 618.2Lacs )
on Saturday, March 30th 2024, 6:30:00 pm
74.73%
Financial Progress
19th Expenditure
of ₹ 12372000 (123.72 Lacs ) done.
Cummulative ₹ 461.99Lacs ( against 618.2Lacs )
on Sunday, May 12th 2024, 6:30:00 pm
76.31%
Financial Progress
20th Expenditure
of ₹ 975000 (9.75 Lacs ) done.
Cummulative ₹ 471.74Lacs ( against 618.2Lacs )
on Thursday, June 6th 2024, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 8th time
on Wednesday, June 26th 2024, 6:30:00 pm
78.18%
Financial Progress
21st Expenditure
of ₹ 1159015 (11.59 Lacs ) done.
Cummulative ₹ 483.33Lacs ( against 618.2Lacs )
on Friday, June 28th 2024, 6:30:00 pm
79.13%
Financial Progress
22nd Expenditure
of ₹ 584757 (5.85 Lacs ) done.
Cummulative ₹ 489.18Lacs ( against 618.2Lacs )
on Monday, July 1st 2024, 6:30:00 pm
81.95%
Financial Progress
23rd Expenditure
of ₹ 1743772 (17.44 Lacs ) done.
Cummulative ₹ 506.62Lacs ( against 618.2Lacs )
on Monday, September 2nd 2024, 6:30:00 pm
82.05%
Financial Progress
24th Expenditure
of ₹ 59059 (0.59 Lacs ) done.
Cummulative ₹ 507.21Lacs ( against 618.2Lacs )
on Tuesday, September 3rd 2024, 6:30:00 pm
93%
Physical Progress
Physical Progress Reported at 9th time
on Sunday, September 29th 2024, 6:30:00 pm
83.62%
Financial Progress
25th Expenditure
of ₹ 971082 (9.71 Lacs ) done.
Cummulative ₹ 516.92Lacs ( against 618.2Lacs )
on Sunday, September 29th 2024, 6:30:00 pm
85.12%
Financial Progress
26th Expenditure
of ₹ 930582 (9.31 Lacs ) done.
Cummulative ₹ 526.22Lacs ( against 618.2Lacs )
on Monday, December 2nd 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 10th time
on Tuesday, March 11th 2025, 6:30:00 pm
88.44%
Financial Progress
27th Expenditure
of ₹ 2050601 (20.51 Lacs ) done.
Cummulative ₹ 546.73Lacs ( against 618.2Lacs )
on Sunday, March 30th 2025, 6:30:00 pm
93.32%
Financial Progress
28th Expenditure
of ₹ 3014861 (30.15 Lacs ) done.
Cummulative ₹ 576.88Lacs ( against 618.2Lacs )
on Thursday, June 26th 2025, 6:30:00 pm
93.43%
Financial Progress
29th Expenditure
of ₹ 72217 (0.72 Lacs ) done.
Cummulative ₹ 577.60Lacs ( against 618.2Lacs )