4 years ago

on Tuesday, August 10th 2021, 6:30:00 pm
Work Sanctioned
वित्तीय वर्ष 2021-22 में मा0 मुख्यमंत्री घोषणा सं0-351/2019 के अन्तर्गत जिला अल्मोड़ा के विधानसभा क्षेत्र सल्ट के अन्तर्गत जैनल से डोटियाल मुख्य मार्ग से कुन्हील तक 6.00 किमी0 मोटर मार्ग मार्ग का डामरीकरण कार्य।

4 years ago

on Wednesday, August 25th 2021, 5:17:46 am

Technical Sanction
of ₹ 202.27 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 6048/29C-01/2021-22

4 years ago

on Saturday, December 25th 2021, 7:26:20 am
<span class="4">Picture Id:3903</span>
PWD Uttarakahnd
Photo (ID 3903) from Site Received
Uploader : Narendra Singh Rawat, Assistant Engineer Civil ,CD Kashipur
Landmark : Km 4 kunheel
Remark : Slip at gahankha kunheel need to remove before g2

4 years ago

on Monday, January 31st 2022, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Saturday, May 14th 2022, 8:30:46 am
<span class="4">Picture Id:5566</span>
PWD Uttarakahnd
Photo (ID 5566) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 3
Remark : Measurement Work

3 years ago

on Saturday, May 14th 2022, 8:32:12 am
<span class="4">Picture Id:5567</span>
PWD Uttarakahnd
Photo (ID 5567) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 4
Remark : Measurement Work

3 years ago

on Wednesday, August 3rd 2022, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 2nd time

3 years ago

on Wednesday, August 31st 2022, 6:30:00 pm
40%

Physical Progress
Physical Progress Reported at 3rd time

3 years ago

on Thursday, September 1st 2022, 7:07:13 am
<span class="4">Picture Id:7649</span>
PWD Uttarakahnd
Photo (ID 7649) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 3
Remark : Measurement

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
0.15%
Financial Progress

1st Expenditure
of ₹ 30943 (0.31 Lacs ) done.
Cummulative ₹ 0.31Lacs ( against 202.27Lacs )

3 years ago

on Thursday, October 6th 2022, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 4th time

3 years ago

on Friday, October 21st 2022, 12:17:12 pm
<span class="4">Picture Id:8827</span>
PWD Uttarakahnd
Photo (ID 8827) from Site Received
Uploader : Puneeta Rani, Assistant Engineer Civil ,1st Circle Almora
Landmark : Km1 ch 0.400
Remark : WBM(45-63mmS/b) work in progress

3 years ago

on Thursday, November 3rd 2022, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 5th time

3 years ago

on Saturday, November 12th 2022, 4:50:26 am
<span class="4">Picture Id:9130</span>
PWD Uttarakahnd
Photo (ID 9130) from Site Received
Uploader : Kundan Singh, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km 2 ch 0-2
Remark : Visit of CE Almora sir and checking super elevstion

3 years ago

on Saturday, November 12th 2022, 4:59:58 am
<span class="4">Picture Id:9135</span>
PWD Uttarakahnd
Photo (ID 9135) from Site Received
Uploader : Kundan Singh, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km 1 x/s 0/4
Remark : CE Almora sir checking crust thickness and gradation

3 years ago

on Saturday, November 12th 2022, 5:27:29 am
<span class="4">Picture Id:9136</span>
PWD Uttarakahnd
Photo (ID 9136) from Site Received
Uploader : Kundan Singh, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km1 X/s no4
Remark : Checking of gradation

3 years ago

on Saturday, November 12th 2022, 6:48:35 am
<span class="4">Picture Id:9140</span>
PWD Uttarakahnd
Photo (ID 9140) from Site Received
Uploader : Kundan Singh, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km 3 2/11
Remark : Gradation checking

3 years ago

on Saturday, November 12th 2022, 7:03:39 am
<span class="4">Picture Id:9142</span>
PWD Uttarakahnd
Photo (ID 9142) from Site Received
Uploader : Kundan Singh, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km 3 Ch2/11
Remark : CE Almora sir checking gradation of G3

3 years ago

on Saturday, November 19th 2022, 6:38:43 am
<span class="4">Picture Id:10135</span>
PWD Uttarakahnd
Photo (ID 10135) from Site Received
Uploader : Puneeta Rani, Assistant Engineer Civil ,1st Circle Almora
Landmark : 4.725 -4.750
Remark : Road marking at HP Band

3 years ago

on Tuesday, November 22nd 2022, 10:04:09 am
<span class="4">Picture Id:11119</span>
PWD Uttarakahnd
Photo (ID 11119) from Site Received
Uploader : Puneeta Rani, Assistant Engineer Civil ,1st Circle Almora
Landmark : 4.950
Remark : Site inspection with E.E. Sir

3 years ago

on Tuesday, November 22nd 2022, 10:21:52 am
<span class="4">Picture Id:11132</span>
PWD Uttarakahnd
Photo (ID 11132) from Site Received
Uploader : Puneeta Rani, Assistant Engineer Civil ,1st Circle Almora
Landmark : 3.850
Remark : Site inspection by E.E.Sir

3 years ago

on Tuesday, November 29th 2022, 6:30:00 pm
12.24%
Financial Progress

2nd Expenditure
of ₹ 2445728 (24.46 Lacs ) done.
Cummulative ₹ 24.77Lacs ( against 202.27Lacs )

3 years ago

on Wednesday, November 30th 2022, 6:16:59 am
<span class="4">Picture Id:12231</span>
PWD Uttarakahnd
Photo (ID 12231) from Site Received
Uploader : Puneeta Rani, Assistant Engineer Civil ,1st Circle Almora
Landmark : 4.850
Remark : Kachcha drain in progress

3 years ago

on Monday, December 26th 2022, 8:30:39 am
<span class="4">Picture Id:14706</span>
PWD Uttarakahnd
Photo (ID 14706) from Site Received
Uploader : Puneeta Rani, Assistant Engineer Civil ,1st Circle Almora
Landmark : 3.750
Remark : पटरी भरान का कार्य प्रगति में

3 years ago

on Tuesday, January 31st 2023, 6:30:00 pm
54.14%
Financial Progress

3rd Expenditure
of ₹ 8473232 (84.73 Lacs ) done.
Cummulative ₹ 109.50Lacs ( against 202.27Lacs )

3 years ago

on Tuesday, February 28th 2023, 6:30:00 pm
54.16%
Financial Progress

4th Expenditure
of ₹ 5600 (0.06 Lacs ) done.
Cummulative ₹ 109.56Lacs ( against 202.27Lacs )

2 years ago

on Thursday, March 9th 2023, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 6th time

2 years ago

on Friday, June 2nd 2023, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 7th time

2 years ago

on Friday, June 2nd 2023, 6:30:00 pm
49.42%
Financial Progress

5th Expenditure
of ₹ -960038 (-9.60 Lacs ) done.
Cummulative ₹ 99.95Lacs ( against 202.27Lacs )

2 years ago

on Saturday, July 1st 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 8th time

2 years ago

on Thursday, August 3rd 2023, 6:30:00 pm
49.53%
Financial Progress

6th Expenditure
of ₹ 22146 (0.22 Lacs ) done.
Cummulative ₹ 100.18Lacs ( against 202.27Lacs )

2 years ago

on Tuesday, September 5th 2023, 6:30:00 pm
49.58%
Financial Progress

7th Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 100.28Lacs ( against 202.27Lacs )

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
68.89%
Financial Progress

8th Expenditure
of ₹ 3905926 (39.06 Lacs ) done.
Cummulative ₹ 139.34Lacs ( against 202.27Lacs )

2 years ago

on Wednesday, November 8th 2023, 6:30:00 pm
69.56%
Financial Progress

9th Expenditure
of ₹ 135745 (1.36 Lacs ) done.
Cummulative ₹ 140.69Lacs ( against 202.27Lacs )

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
86.59%
Financial Progress

11th Expenditure
of ₹ 2990000 (29.90 Lacs ) done.
Cummulative ₹ 175.15Lacs ( against 202.27Lacs )

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
71.81%
Financial Progress

10th Expenditure
of ₹ 455852 (4.56 Lacs ) done.
Cummulative ₹ 145.25Lacs ( against 202.27Lacs )