Work Sanctioned
वित्तीय वर्ष 2021-22 में मा0 मुख्यमंत्री घोषणा सं0-351/2019 के अन्तर्गत जिला अल्मोड़ा के विधानसभा क्षेत्र सल्ट के अन्तर्गत जैनल से डोटियाल मुख्य मार्ग से कुन्हील तक 6.00 किमी0 मोटर मार्ग मार्ग का डामरीकरण कार्य।
on Wednesday, August 25th 2021, 5:17:46 am
Technical Sanction
of ₹ 202.27 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 6048/29C-01/2021-22
on Saturday, December 25th 2021, 7:26:20 am
PWD UttarakahndPhoto (ID 3903) from Site Received
Uploader : Narendra Singh Rawat, Assistant Engineer Civil ,CD Kashipur
Landmark : Km 4 kunheel
Remark : Slip at gahankha kunheel need to remove before g2
on Monday, January 31st 2022, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Saturday, May 14th 2022, 8:30:46 am
PWD UttarakahndPhoto (ID 5566) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 3
Remark : Measurement Work
on Saturday, May 14th 2022, 8:32:12 am
PWD UttarakahndPhoto (ID 5567) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 4
Remark : Measurement Work
on Wednesday, August 3rd 2022, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, August 31st 2022, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 3rd time
on Thursday, September 1st 2022, 7:07:13 am
PWD UttarakahndPhoto (ID 7649) from Site Received
Uploader : Gulam Mohammad, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : KM 3
Remark : Measurement
on Thursday, September 29th 2022, 6:30:00 pm
0.15%
Financial Progress
1st Expenditure
of ₹ 30943 (0.31 Lacs ) done.
Cummulative ₹ 0.31Lacs ( against 202.27Lacs )
on Thursday, October 6th 2022, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 4th time
on Friday, October 21st 2022, 12:17:12 pm
PWD UttarakahndPhoto (ID 8827) from Site Received
Uploader : Puneeta Rani, Assistant Engineer Civil ,1st Circle Almora
Landmark : Km1 ch 0.400
Remark : WBM(45-63mmS/b) work in progress
on Thursday, November 3rd 2022, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 5th time
on Saturday, November 12th 2022, 4:50:26 am
PWD UttarakahndPhoto (ID 9130) from Site Received
Uploader : Kundan Singh, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km 2 ch 0-2
Remark : Visit of CE Almora sir and checking super elevstion
on Saturday, November 12th 2022, 4:59:58 am
PWD UttarakahndPhoto (ID 9135) from Site Received
Uploader : Kundan Singh, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km 1 x/s 0/4
Remark : CE Almora sir checking crust thickness and gradation
on Saturday, November 12th 2022, 5:27:29 am
PWD UttarakahndPhoto (ID 9136) from Site Received
Uploader : Kundan Singh, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km1 X/s no4
Remark : Checking of gradation
on Saturday, November 12th 2022, 6:48:35 am
PWD UttarakahndPhoto (ID 9140) from Site Received
Uploader : Kundan Singh, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km 3 2/11
Remark : Gradation checking
on Saturday, November 12th 2022, 7:03:39 am
PWD UttarakahndPhoto (ID 9142) from Site Received
Uploader : Kundan Singh, Assistant Engineer Civil ,PD Bageshwar
Landmark : Km 3 Ch2/11
Remark : CE Almora sir checking gradation of G3
on Saturday, November 19th 2022, 6:38:43 am
PWD UttarakahndPhoto (ID 10135) from Site Received
Uploader : Puneeta Rani, Assistant Engineer Civil ,1st Circle Almora
Landmark : 4.725 -4.750
Remark : Road marking at HP Band
on Tuesday, November 22nd 2022, 10:04:09 am
PWD UttarakahndPhoto (ID 11119) from Site Received
Uploader : Puneeta Rani, Assistant Engineer Civil ,1st Circle Almora
Landmark : 4.950
Remark : Site inspection with E.E. Sir
on Tuesday, November 22nd 2022, 10:21:52 am
PWD UttarakahndPhoto (ID 11132) from Site Received
Uploader : Puneeta Rani, Assistant Engineer Civil ,1st Circle Almora
Landmark : 3.850
Remark : Site inspection by E.E.Sir
on Tuesday, November 29th 2022, 6:30:00 pm
12.24%
Financial Progress
2nd Expenditure
of ₹ 2445728 (24.46 Lacs ) done.
Cummulative ₹ 24.77Lacs ( against 202.27Lacs )
on Wednesday, November 30th 2022, 6:16:59 am
PWD UttarakahndPhoto (ID 12231) from Site Received
Uploader : Puneeta Rani, Assistant Engineer Civil ,1st Circle Almora
Landmark : 4.850
Remark : Kachcha drain in progress
on Monday, December 26th 2022, 8:30:39 am
PWD UttarakahndPhoto (ID 14706) from Site Received
Uploader : Puneeta Rani, Assistant Engineer Civil ,1st Circle Almora
Landmark : 3.750
Remark : पटरी भरान का कार्य प्रगति में
on Tuesday, January 31st 2023, 6:30:00 pm
54.14%
Financial Progress
3rd Expenditure
of ₹ 8473232 (84.73 Lacs ) done.
Cummulative ₹ 109.50Lacs ( against 202.27Lacs )
on Tuesday, February 28th 2023, 6:30:00 pm
54.16%
Financial Progress
4th Expenditure
of ₹ 5600 (0.06 Lacs ) done.
Cummulative ₹ 109.56Lacs ( against 202.27Lacs )
on Thursday, March 9th 2023, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 6th time
on Friday, June 2nd 2023, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 7th time
on Friday, June 2nd 2023, 6:30:00 pm
49.42%
Financial Progress
5th Expenditure
of ₹ -960038 (-9.60 Lacs ) done.
Cummulative ₹ 99.95Lacs ( against 202.27Lacs )
on Saturday, July 1st 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 8th time
on Thursday, August 3rd 2023, 6:30:00 pm
49.53%
Financial Progress
6th Expenditure
of ₹ 22146 (0.22 Lacs ) done.
Cummulative ₹ 100.18Lacs ( against 202.27Lacs )
on Tuesday, September 5th 2023, 6:30:00 pm
49.58%
Financial Progress
7th Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 100.28Lacs ( against 202.27Lacs )
on Friday, September 29th 2023, 6:30:00 pm
68.89%
Financial Progress
8th Expenditure
of ₹ 3905926 (39.06 Lacs ) done.
Cummulative ₹ 139.34Lacs ( against 202.27Lacs )
on Wednesday, November 8th 2023, 6:30:00 pm
69.56%
Financial Progress
9th Expenditure
of ₹ 135745 (1.36 Lacs ) done.
Cummulative ₹ 140.69Lacs ( against 202.27Lacs )
on Saturday, March 30th 2024, 6:30:00 pm
86.59%
Financial Progress
11th Expenditure
of ₹ 2990000 (29.90 Lacs ) done.
Cummulative ₹ 175.15Lacs ( against 202.27Lacs )
on Saturday, March 30th 2024, 6:30:00 pm
71.81%
Financial Progress
10th Expenditure
of ₹ 455852 (4.56 Lacs ) done.
Cummulative ₹ 145.25Lacs ( against 202.27Lacs )