on Monday, January 23rd 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद अल्मोड़ा के विधान सभा क्षेत्र रानीखेत के अन्तर्गत स्व0 श्री जय दत्त बैला स्वतन्त्रंता सैनानी राजकीय स्नाकोत्तर महाविद्यालय रानीखेत में क्षतिग्रस्त सी0सी0 पर इन्टर लाकिगं टाईल्स लगाने का कार्य।
on Friday, June 23rd 2023, 5:10:59 am
PWD UttarakahndPhoto (ID 21656) from Site Received
Uploader : Kundan Singh, Assistant Engineer Civil ,PD Bageshwar
Landmark : Near Library of degree college Ranikhet
Remark : Checking compacted thickness of GSB, G2 & G3 below interlocking tiles.
on Friday, June 23rd 2023, 5:16:04 am
PWD UttarakahndPhoto (ID 21657) from Site Received
Uploader : Kundan Singh, Assistant Engineer Civil ,PD Bageshwar
Landmark : Near library of degree college ranikhet
Remark : Interlocking tiles work in progress near Iibrary of degree college Ranikhet
on Saturday, July 1st 2023, 12:04:23 am
PWD UttarakahndPhoto (ID 22052) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : 1 job
Remark : Degree college ranikhet cc and tile work
on Saturday, July 1st 2023, 12:06:17 am
PWD UttarakahndPhoto (ID 22054) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : 1 job
Remark : Degree college ranikhet cc and tile work
on Saturday, July 1st 2023, 12:08:10 am
PWD UttarakahndPhoto (ID 22055) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : 1 job
Remark : Degree college ranikhet cc and tile work
on Friday, August 4th 2023, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 1st time
on Friday, September 29th 2023, 6:30:00 pm
92.73%
Financial Progress
1st Expenditure
of ₹ 4117030 (41.17 Lacs ) done.
Cummulative ₹ 41.17Lacs ( against 44.4Lacs )
on Thursday, October 5th 2023, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, December 6th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Monday, May 27th 2024, 6:30:00 pm
99.04%
Financial Progress
2nd Expenditure
of ₹ 280391 (2.80 Lacs ) done.
Cummulative ₹ 43.97Lacs ( against 44.4Lacs )
on Monday, June 3rd 2024, 6:30:00 pm
105.57%
Financial Progress
3rd Expenditure
of ₹ 290000 (2.90 Lacs ) done.
Cummulative ₹ 46.87Lacs ( against 44.4Lacs )
on Tuesday, June 25th 2024, 1:36:21 am
PWD UttarakahndPhoto (ID 46518) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : 1job(degree collage ranikhet)
Remark : Work completed
on Tuesday, June 25th 2024, 1:37:53 am
PWD UttarakahndPhoto (ID 46520) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : 1 job (degree collage ranikhet)
Remark : Work completed
on Tuesday, June 25th 2024, 1:39:21 am
PWD UttarakahndPhoto (ID 46522) from Site Received
Uploader : Umesh Lal Sah, Additional Assistant Engineer Civil ,PD Ranikhet
Landmark : 1 jpb
Remark : Work completed
on Sunday, March 30th 2025, 6:30:00 pm
99.27%
Financial Progress
4th Expenditure
of ₹ -280000 (-2.80 Lacs ) done.
Cummulative ₹ 44.07Lacs ( against 44.4Lacs )