Work Sanctioned
जनपद अल्मोड़ा के विधान सभा क्षेत्र सल्ट के अन्तर्गत सौधार-पनुवाद्योखन मोटर मार्ग में डामरीकरण एवं सुधारीकरण का कार्य।
on Wednesday, December 13th 2023, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 1st time
on Saturday, December 30th 2023, 5:55:43 am
PWD UttarakahndPhoto (ID 33958) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : Km1 HM 4 -6
Remark : Drain work in progress
on Saturday, December 30th 2023, 6:35:11 am
PWD UttarakahndPhoto (ID 33982) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : Km 5 HM 4-6
Remark : Slip clearance work in progress.
on Sunday, February 11th 2024, 6:30:00 pm
13.59%
Financial Progress
1st Expenditure
of ₹ 3692302 (36.92 Lacs ) done.
Cummulative ₹ 36.92Lacs ( against 271.73Lacs )
on Saturday, March 30th 2024, 6:30:00 pm
58.57%
Financial Progress
2nd Expenditure
of ₹ 12222043 (122.22 Lacs ) done.
Cummulative ₹ 159.14Lacs ( against 271.73Lacs )
on Tuesday, April 23rd 2024, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, May 30th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Thursday, June 6th 2024, 6:30:00 pm
73.33%
Financial Progress
3rd Expenditure
of ₹ 4011000 (40.11 Lacs ) done.
Cummulative ₹ 199.25Lacs ( against 271.73Lacs )
on Wednesday, June 26th 2024, 4:19:38 am
PWD UttarakahndPhoto (ID 46675) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : O.00 Panwadokhan
Remark : PC work completed
on Wednesday, June 26th 2024, 4:27:51 am
PWD UttarakahndPhoto (ID 46676) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 1.750 Near Panuwadokhan
Remark : Kutcha drain & patri filling work completed
on Wednesday, June 26th 2024, 4:35:20 am
PWD UttarakahndPhoto (ID 46677) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 3.00
Remark : Damage wall repaired
on Wednesday, June 26th 2024, 4:39:57 am
PWD UttarakahndPhoto (ID 46679) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 2.900
Remark : Retaning wall constricted
on Wednesday, June 26th 2024, 4:45:08 am
PWD UttarakahndPhoto (ID 46680) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 4.600
Remark : Kutcha drain work near H P band
on Wednesday, June 26th 2024, 4:50:10 am
PWD UttarakahndPhoto (ID 46682) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 6.200
Remark : New sliding zone developed
on Wednesday, June 26th 2024, 4:55:52 am
PWD UttarakahndPhoto (ID 46683) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 7.525
Remark : Kutcha Drain work
on Wednesday, June 26th 2024, 5:01:43 am
PWD UttarakahndPhoto (ID 46686) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 8.550
Remark : Patri filling ,kutcha drain ,R/wall repair work
on Wednesday, June 26th 2024, 5:09:01 am
PWD UttarakahndPhoto (ID 46695) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 10.950
Remark : Damaged Causeway repair work
on Wednesday, June 26th 2024, 5:12:31 am
PWD UttarakahndPhoto (ID 46703) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 12.100 Bankota villeage
Remark : Painting work completed of 36 m span steel girder bridge
on Wednesday, June 26th 2024, 5:22:57 am
PWD UttarakahndPhoto (ID 46714) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 10.150
Remark : Damaged R/wall repair work
on Wednesday, June 26th 2024, 5:49:05 am
PWD UttarakahndPhoto (ID 46749) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 0.675
Remark : PC work,Drain,Patri filling work
on Friday, June 28th 2024, 6:30:00 pm
88.06%
Financial Progress
4th Expenditure
of ₹ 4002688 (40.03 Lacs ) done.
Cummulative ₹ 239.28Lacs ( against 271.73Lacs )
on Monday, July 22nd 2024, 9:27:19 am
PWD UttarakahndPhoto (ID 50997) from Site Received
Uploader : Jagdish Chandra Pandey, Assistant Engineer Civil ,PD Ranikhet
Landmark : 6.640
Remark : Road washout in km -7 on dated 15.7.2024 now work is started to communicate traffic. site visited today by SE sir
on Wednesday, October 30th 2024, 6:30:00 pm
95.88%
Financial Progress
5th Expenditure
of ₹ 2125365 (21.25 Lacs ) done.
Cummulative ₹ 260.53Lacs ( against 271.73Lacs )