Refresh data
Refresh data

2 years ago

on Sunday, July 23rd 2023, 6:30:00 pm
Work Sanctioned
राज्य याजना के अन्तर्गत जनपद रुद्रप्रयाग के विधान सभा क्षेत्र केदारनाथ के विकास खण्ड, ऊखीमठ में तोणीधार-पैलिंग मोटर मार्ग के कि॰मी॰ 1.00 से 6.00 में मध्य सुधारीकरण एवं पी॰सी॰ द्वारा डामरीकरण का कार्य।

2 years ago

on Monday, October 16th 2023, 5:23:46 am

Technical Sanction
of ₹ 470.35 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 7624/07(273) Yata (Ukhimath) Pauri/2023

2 years ago

on Sunday, November 19th 2023, 6:30:00 pm
0.95%
Financial Progress

1st Expenditure
of ₹ 448000 (4.48 Lacs ) done.
Cummulative ₹ 4.48Lacs ( against 470.35Lacs )

2 years ago

on Friday, December 15th 2023, 6:30:00 pm
1.16%
Financial Progress

2nd Expenditure
of ₹ 96000 (0.96 Lacs ) done.
Cummulative ₹ 5.44Lacs ( against 470.35Lacs )

2 years ago

on Wednesday, December 20th 2023, 6:30:00 pm
3.08%
Financial Progress

3rd Expenditure
of ₹ 907000 (9.07 Lacs ) done.
Cummulative ₹ 14.51Lacs ( against 470.35Lacs )

2 years ago

on Thursday, January 18th 2024, 6:30:00 pm
8.52%
Financial Progress

4th Expenditure
of ₹ 2556000 (25.56 Lacs ) done.
Cummulative ₹ 40.07Lacs ( against 470.35Lacs )

2 years ago

on Friday, January 19th 2024, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Sunday, February 25th 2024, 6:30:00 pm
18.81%
Financial Progress

5th Expenditure
of ₹ 4838000 (48.38 Lacs ) done.
Cummulative ₹ 88.45Lacs ( against 470.35Lacs )

a year ago

on Wednesday, March 13th 2024, 6:30:00 pm
18.85%
Financial Progress

6th Expenditure
of ₹ 21000 (0.21 Lacs ) done.
Cummulative ₹ 88.66Lacs ( against 470.35Lacs )

a year ago

on Thursday, March 14th 2024, 6:30:00 pm
26.37%
Financial Progress

7th Expenditure
of ₹ 3538000 (35.38 Lacs ) done.
Cummulative ₹ 124.04Lacs ( against 470.35Lacs )

a year ago

on Sunday, May 5th 2024, 6:30:00 pm
26.40%
Financial Progress

9th Expenditure
of ₹ 6210 (0.06 Lacs ) done.
Cummulative ₹ 124.16Lacs ( against 470.35Lacs )

a year ago

on Sunday, May 5th 2024, 6:30:00 pm
26.38%
Financial Progress

8th Expenditure
of ₹ 5782 (0.06 Lacs ) done.
Cummulative ₹ 124.10Lacs ( against 470.35Lacs )

a year ago

on Tuesday, May 7th 2024, 6:30:00 pm
27.04%
Financial Progress

10th Expenditure
of ₹ 300000 (3.00 Lacs ) done.
Cummulative ₹ 127.16Lacs ( against 470.35Lacs )

a year ago

on Sunday, May 19th 2024, 6:30:00 pm
27.09%
Financial Progress

11th Expenditure
of ₹ 24240 (0.24 Lacs ) done.
Cummulative ₹ 127.40Lacs ( against 470.35Lacs )

a year ago

on Thursday, May 23rd 2024, 6:30:00 pm
27.09%
Financial Progress

12th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 127.40Lacs ( against 470.35Lacs )

a year ago

on Sunday, May 26th 2024, 6:30:00 pm
27.12%
Financial Progress

13th Expenditure
of ₹ 14278 (0.14 Lacs ) done.
Cummulative ₹ 127.55Lacs ( against 470.35Lacs )

a year ago

on Friday, May 31st 2024, 6:30:00 pm
30.13%
Financial Progress

14th Expenditure
of ₹ 1416000 (14.16 Lacs ) done.
Cummulative ₹ 141.71Lacs ( against 470.35Lacs )

a year ago

on Wednesday, June 19th 2024, 6:30:00 pm
30.19%
Financial Progress

15th Expenditure
of ₹ 31500 (0.32 Lacs ) done.
Cummulative ₹ 142.02Lacs ( against 470.35Lacs )

a year ago

on Monday, June 24th 2024, 6:30:00 pm
35.98%
Financial Progress

16th Expenditure
of ₹ 2723500 (27.23 Lacs ) done.
Cummulative ₹ 169.26Lacs ( against 470.35Lacs )

a year ago

on Tuesday, June 25th 2024, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Thursday, June 27th 2024, 7:32:16 am
<span class="4">Picture Id:47701</span>
PWD Uttarakahnd
Photo (ID 47701) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 1.150
Remark : G1 work

a year ago

on Thursday, June 27th 2024, 7:34:39 am
<span class="4">Picture Id:47711</span>
PWD Uttarakahnd
Photo (ID 47711) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 1.250
Remark : W.B.M work

a year ago

on Thursday, June 27th 2024, 7:37:45 am
<span class="4">Picture Id:47713</span>
PWD Uttarakahnd
Photo (ID 47713) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 2.625
Remark : W.B.M Work

a year ago

on Thursday, June 27th 2024, 7:38:44 am
<span class="4">Picture Id:47716</span>
PWD Uttarakahnd
Photo (ID 47716) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 2.850
Remark : W.B.M work

a year ago

on Thursday, June 27th 2024, 7:41:43 am
<span class="4">Picture Id:47727</span>
PWD Uttarakahnd
Photo (ID 47727) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 3.625
Remark : W.B.M Work

a year ago

on Thursday, June 27th 2024, 7:47:56 am
<span class="4">Picture Id:47728</span>
PWD Uttarakahnd
Photo (ID 47728) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 3.325
Remark : W.B.M work

a year ago

on Thursday, June 27th 2024, 7:52:02 am
<span class="4">Picture Id:47733</span>
PWD Uttarakahnd
Photo (ID 47733) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 4.950
Remark : B/w work

a year ago

on Thursday, June 27th 2024, 7:53:21 am
<span class="4">Picture Id:47737</span>
PWD Uttarakahnd
Photo (ID 47737) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 5.125km
Remark : Defect cutting work

a year ago

on Thursday, June 27th 2024, 7:56:06 am
<span class="4">Picture Id:47741</span>
PWD Uttarakahnd
Photo (ID 47741) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 5.100km
Remark : Defect cutting work

a year ago

on Thursday, June 27th 2024, 6:30:00 pm
45%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Wednesday, July 24th 2024, 6:30:00 pm
35.98%
Financial Progress

17th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 169.26Lacs ( against 470.35Lacs )

a year ago

on Monday, July 29th 2024, 6:30:00 pm
43.43%
Financial Progress

18th Expenditure
of ₹ 3504027 (35.04 Lacs ) done.
Cummulative ₹ 204.30Lacs ( against 470.35Lacs )

a year ago

on Wednesday, August 21st 2024, 6:30:00 pm
43.43%
Financial Progress

19th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 204.30Lacs ( against 470.35Lacs )

a year ago

on Thursday, August 22nd 2024, 6:30:00 pm
48.97%
Financial Progress

20th Expenditure
of ₹ 2601731 (26.02 Lacs ) done.
Cummulative ₹ 230.31Lacs ( against 470.35Lacs )

a year ago

on Thursday, August 22nd 2024, 6:30:00 pm
48.99%
Financial Progress

22nd Expenditure
of ₹ 4602 (0.05 Lacs ) done.
Cummulative ₹ 230.43Lacs ( against 470.35Lacs )

a year ago

on Thursday, August 22nd 2024, 6:30:00 pm
48.98%
Financial Progress

21st Expenditure
of ₹ 6879 (0.07 Lacs ) done.
Cummulative ₹ 230.38Lacs ( against 470.35Lacs )

a year ago

on Monday, August 26th 2024, 6:30:00 pm
55%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Tuesday, August 27th 2024, 6:30:00 pm
49.03%
Financial Progress

23rd Expenditure
of ₹ 18880 (0.19 Lacs ) done.
Cummulative ₹ 230.62Lacs ( against 470.35Lacs )

a year ago

on Thursday, September 19th 2024, 6:30:00 pm
49.03%
Financial Progress

24th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 230.62Lacs ( against 470.35Lacs )

a year ago

on Tuesday, September 24th 2024, 6:30:00 pm
49.04%
Financial Progress

25th Expenditure
of ₹ 2600 (0.03 Lacs ) done.
Cummulative ₹ 230.64Lacs ( against 470.35Lacs )

a year ago

on Tuesday, September 24th 2024, 6:30:00 pm
49.84%
Financial Progress

26th Expenditure
of ₹ 377904 (3.78 Lacs ) done.
Cummulative ₹ 234.42Lacs ( against 470.35Lacs )

a year ago

on Tuesday, September 24th 2024, 6:30:00 pm
49.94%
Financial Progress

27th Expenditure
of ₹ 48000 (0.48 Lacs ) done.
Cummulative ₹ 234.90Lacs ( against 470.35Lacs )

a year ago

on Thursday, September 26th 2024, 6:30:00 pm
53.53%
Financial Progress

28th Expenditure
of ₹ 1688247 (16.88 Lacs ) done.
Cummulative ₹ 251.78Lacs ( against 470.35Lacs )

10 months ago

on Monday, October 21st 2024, 9:04:17 am
<span class="4">Picture Id:57646</span>
PWD Uttarakahnd
Photo (ID 57646) from Site Received
Uploader : Manoj Kumar Bhatt, Executive Engineer Civil ,TD Berinaag
Landmark : 3.750
Remark : Premix Carpet work under state sector in km4 3.750

10 months ago

on Monday, October 21st 2024, 9:25:28 am
<span class="4">Picture Id:57648</span>
PWD Uttarakahnd
Photo (ID 57648) from Site Received
Uploader : Manoj Kumar Bhatt, Executive Engineer Civil ,TD Berinaag
Landmark : 3.800
Remark : Premix Carpet thickness found 21 mm at km 4 ch 3.800 ok

10 months ago

on Monday, October 21st 2024, 9:32:25 am
<span class="4">Picture Id:57650</span>
PWD Uttarakahnd
Photo (ID 57650) from Site Received
Uploader : Manoj Kumar Bhatt, Executive Engineer Civil ,TD Berinaag
Landmark : 3.800
Remark : Premix Carpet width 3.80 m at km 4 ch 3.810 ok

10 months ago

on Tuesday, November 5th 2024, 6:30:00 pm
60.97%
Financial Progress

29th Expenditure
of ₹ 3500000 (35.00 Lacs ) done.
Cummulative ₹ 286.78Lacs ( against 470.35Lacs )

9 months ago

on Thursday, November 21st 2024, 6:30:00 pm
60.97%
Financial Progress

30th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 286.78Lacs ( against 470.35Lacs )

9 months ago

on Monday, December 2nd 2024, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 5th time

9 months ago

on Wednesday, December 4th 2024, 7:52:55 am
<span class="4">Picture Id:60359</span>
PWD Uttarakahnd
Photo (ID 60359) from Site Received
Uploader : Mukesh Prasad Painuly, Additional Assistant Engineer Civil ,CD Ukhimath
Landmark : 3.750
Remark : Improvement work of tonidhar Pailing mr

9 months ago

on Wednesday, December 4th 2024, 7:58:26 am
<span class="4">Picture Id:60362</span>
PWD Uttarakahnd
Photo (ID 60362) from Site Received
Uploader : Mukesh Prasad Painuly, Additional Assistant Engineer Civil ,CD Ukhimath
Landmark : 4.200
Remark : Improvement work of tonidhar Pailing mr

9 months ago

on Wednesday, December 4th 2024, 8:01:54 am
<span class="4">Picture Id:60363</span>
PWD Uttarakahnd
Photo (ID 60363) from Site Received
Uploader : Mukesh Prasad Painuly, Additional Assistant Engineer Civil ,CD Ukhimath
Landmark : 4.900
Remark : Improvement work of tonidhar Pailing mr

9 months ago

on Wednesday, December 4th 2024, 8:04:03 am
<span class="4">Picture Id:60365</span>
PWD Uttarakahnd
Photo (ID 60365) from Site Received
Uploader : Mukesh Prasad Painuly, Additional Assistant Engineer Civil ,CD Ukhimath
Landmark : 4.900
Remark : Improvement work

9 months ago

on Wednesday, December 4th 2024, 8:07:21 am
<span class="4">Picture Id:60366</span>
PWD Uttarakahnd
Photo (ID 60366) from Site Received
Uploader : Mukesh Prasad Painuly, Additional Assistant Engineer Civil ,CD Ukhimath
Landmark : 4.850
Remark : Improvement work

9 months ago

on Wednesday, December 4th 2024, 8:15:58 am
<span class="4">Picture Id:60371</span>
PWD Uttarakahnd
Photo (ID 60371) from Site Received
Uploader : Mukesh Prasad Painuly, Additional Assistant Engineer Civil ,CD Ukhimath
Landmark : 5.200
Remark : Improvement work

9 months ago

on Wednesday, December 4th 2024, 8:26:52 am
<span class="4">Picture Id:60374</span>
PWD Uttarakahnd
Photo (ID 60374) from Site Received
Uploader : Mukesh Prasad Painuly, Additional Assistant Engineer Civil ,CD Ukhimath
Landmark : 1.850
Remark : Protection work

8 months ago

on Tuesday, December 24th 2024, 6:30:00 pm
61.06%
Financial Progress

31st Expenditure
of ₹ 41822 (0.42 Lacs ) done.
Cummulative ₹ 287.20Lacs ( against 470.35Lacs )

8 months ago

on Thursday, December 26th 2024, 6:30:00 pm
70.70%
Financial Progress

32nd Expenditure
of ₹ 4535326 (45.35 Lacs ) done.
Cummulative ₹ 332.56Lacs ( against 470.35Lacs )

8 months ago

on Thursday, December 26th 2024, 6:30:00 pm
70.82%
Financial Progress

33rd Expenditure
of ₹ 53000 (0.53 Lacs ) done.
Cummulative ₹ 333.09Lacs ( against 470.35Lacs )

8 months ago

on Thursday, December 26th 2024, 6:30:00 pm
70.88%
Financial Progress

34th Expenditure
of ₹ 27685 (0.28 Lacs ) done.
Cummulative ₹ 333.36Lacs ( against 470.35Lacs )

8 months ago

on Sunday, December 29th 2024, 6:30:00 pm
78.63%
Financial Progress

37th Expenditure
of ₹ 3550397 (35.50 Lacs ) done.
Cummulative ₹ 369.82Lacs ( against 470.35Lacs )

8 months ago

on Sunday, December 29th 2024, 6:30:00 pm
71.08%
Financial Progress

36th Expenditure
of ₹ 36900 (0.37 Lacs ) done.
Cummulative ₹ 334.32Lacs ( against 470.35Lacs )

8 months ago

on Sunday, December 29th 2024, 6:30:00 pm
71.00%
Financial Progress

35th Expenditure
of ₹ 58949 (0.59 Lacs ) done.
Cummulative ₹ 333.95Lacs ( against 470.35Lacs )

8 months ago

on Tuesday, December 31st 2024, 6:30:00 pm
78.66%
Financial Progress

38th Expenditure
of ₹ 14160 (0.14 Lacs ) done.
Cummulative ₹ 369.97Lacs ( against 470.35Lacs )

7 months ago

on Thursday, January 16th 2025, 5:09:13 am
<span class="4">Picture Id:62810</span>
PWD Uttarakahnd
Photo (ID 62810) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 0.275km
Remark : W.b.m work

7 months ago

on Thursday, January 16th 2025, 5:51:30 am
<span class="4">Picture Id:62814</span>
PWD Uttarakahnd
Photo (ID 62814) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 0.925km
Remark : Road safety work

7 months ago

on Thursday, January 16th 2025, 6:02:45 am
<span class="4">Picture Id:62815</span>
PWD Uttarakahnd
Photo (ID 62815) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 0.975km
Remark : Parapet work

7 months ago

on Thursday, January 16th 2025, 6:33:52 am
<span class="4">Picture Id:62821</span>
PWD Uttarakahnd
Photo (ID 62821) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 4.025 km
Remark : Road safety work

7 months ago

on Thursday, January 16th 2025, 6:38:14 am
<span class="4">Picture Id:62822</span>
PWD Uttarakahnd
Photo (ID 62822) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 4.250km
Remark : Delineator work

7 months ago

on Saturday, January 25th 2025, 7:59:39 am
<span class="4">Picture Id:63280</span>
PWD Uttarakahnd
Photo (ID 63280) from Site Received
Uploader : Manoj Kumar Bhatt, Executive Engineer Civil ,TD Berinaag
Landmark : C c pavement at location ch 3.450km
Remark : Width found 6m at mid point of cc pavement ok tonidhar nailing motor road

7 months ago

on Tuesday, January 28th 2025, 6:30:00 pm
89.13%
Financial Progress

39th Expenditure
of ₹ 4924946 (49.25 Lacs ) done.
Cummulative ₹ 419.22Lacs ( against 470.35Lacs )

7 months ago

on Wednesday, January 29th 2025, 6:30:00 pm
89.19%
Financial Progress

40th Expenditure
of ₹ 29895 (0.30 Lacs ) done.
Cummulative ₹ 419.51Lacs ( against 470.35Lacs )

6 months ago

on Monday, February 24th 2025, 6:30:00 pm
89.26%
Financial Progress

41st Expenditure
of ₹ 31500 (0.32 Lacs ) done.
Cummulative ₹ 419.83Lacs ( against 470.35Lacs )

6 months ago

on Wednesday, March 5th 2025, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 6th time

5 months ago

on Thursday, March 20th 2025, 6:30:00 pm
96.89%
Financial Progress

42nd Expenditure
of ₹ 3591407 (35.91 Lacs ) done.
Cummulative ₹ 455.74Lacs ( against 470.35Lacs )

5 months ago

on Thursday, March 20th 2025, 6:30:00 pm
97.02%
Financial Progress

43rd Expenditure
of ₹ 58892 (0.59 Lacs ) done.
Cummulative ₹ 456.33Lacs ( against 470.35Lacs )

5 months ago

on Thursday, March 27th 2025, 5:56:15 am
<span class="4">Picture Id:66588</span>
PWD Uttarakahnd
Photo (ID 66588) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 0.625km
Remark : Pc work

5 months ago

on Friday, March 28th 2025, 6:30:00 pm
97.10%
Financial Progress

44th Expenditure
of ₹ 36344 (0.36 Lacs ) done.
Cummulative ₹ 456.70Lacs ( against 470.35Lacs )

5 months ago

on Friday, March 28th 2025, 6:30:00 pm
97.15%
Financial Progress

46th Expenditure
of ₹ 17725 (0.18 Lacs ) done.
Cummulative ₹ 456.93Lacs ( against 470.35Lacs )

5 months ago

on Friday, March 28th 2025, 6:30:00 pm
97.11%
Financial Progress

45th Expenditure
of ₹ 5900 (0.06 Lacs ) done.
Cummulative ₹ 456.76Lacs ( against 470.35Lacs )

5 months ago

on Monday, March 31st 2025, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 7th time

3 months ago

on Wednesday, May 14th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 8th time

2 months ago

on Wednesday, June 18th 2025, 6:37:53 am
<span class="4">Picture Id:75740</span>
PWD Uttarakahnd
Photo (ID 75740) from Site Received
Uploader : Mukesh Prasad Painuly, Additional Assistant Engineer Civil ,CD Ukhimath
Landmark : 0.275
Remark : Inspection by SE sir of Tonidhar Pailing MR

2 months ago

on Wednesday, June 18th 2025, 6:47:01 am
<span class="4">Picture Id:75743</span>
PWD Uttarakahnd
Photo (ID 75743) from Site Received
Uploader : Mukesh Prasad Painuly, Additional Assistant Engineer Civil ,CD Ukhimath
Landmark : 0.330
Remark : Crash Barrier

2 months ago

on Wednesday, June 18th 2025, 6:59:58 am
<span class="4">Picture Id:75766</span>
PWD Uttarakahnd
Photo (ID 75766) from Site Received
Uploader : Mukesh Prasad Painuly, Additional Assistant Engineer Civil ,CD Ukhimath
Landmark : 0.425
Remark : Inspection of crest of Tonidhar Pailing mr

a month ago

on Wednesday, July 16th 2025, 6:30:00 pm
97.22%
Financial Progress

47th Expenditure
of ₹ 32450 (0.32 Lacs ) done.
Cummulative ₹ 457.26Lacs ( against 470.35Lacs )

a month ago

on Monday, July 21st 2025, 6:30:00 pm
97.22%
Financial Progress

48th Expenditure
of ₹ 2832 (0.03 Lacs ) done.
Cummulative ₹ 457.29Lacs ( against 470.35Lacs )