Work Sanctioned
राज्य योजना के अन्तर्गत जनपद रूद्रप्रयाग के विधानसभा क्षेत्र केदारनाथ के अन्तर्गत विकासखण्ड अगस्तमुनी में चन्द्रापुरी गुगली आसों जयकण्डी मोटर मार्ग का सुधार एंव डामरीकरण कार्य।
on Sunday, October 27th 2024, 8:43:22 am
PWD UttarakahndPhoto (ID 58242) from Site Received
Uploader : Satyendra Singh Rana, Junior Engineer Civil ,CD Ukhimath
Landmark : 1.700km
Remark : PC work
on Sunday, December 29th 2024, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, January 15th 2025, 4:58:15 am
PWD UttarakahndPhoto (ID 62732) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 4.350km
Remark : R/w work
on Wednesday, January 15th 2025, 5:20:22 am
PWD UttarakahndPhoto (ID 62734) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 4.400km
Remark : Cutting work
on Wednesday, January 15th 2025, 5:23:25 am
PWD UttarakahndPhoto (ID 62736) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 4.450km
Remark : R/w work
on Wednesday, January 15th 2025, 5:25:55 am
PWD UttarakahndPhoto (ID 62740) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 5.150 km
Remark : R/w work
on Wednesday, January 15th 2025, 5:34:30 am
PWD UttarakahndPhoto (ID 62745) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 4.525km
Remark : R/w work
on Wednesday, January 15th 2025, 5:37:05 am
PWD UttarakahndPhoto (ID 62746) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 4.625km
Remark : R/w work
on Tuesday, January 28th 2025, 6:30:00 pm
0.06%
Financial Progress
1st Expenditure
of ₹ 31500 (0.32 Lacs ) done.
Cummulative ₹ 0.32Lacs ( against 535.1Lacs )
on Tuesday, January 28th 2025, 6:30:00 pm
3.91%
Financial Progress
2nd Expenditure
of ₹ 2060312 (20.60 Lacs ) done.
Cummulative ₹ 20.92Lacs ( against 535.1Lacs )
on Wednesday, February 19th 2025, 6:39:28 am
PWD UttarakahndPhoto (ID 64698) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 3.825km
Remark : Defect cutting work
on Monday, February 24th 2025, 6:30:00 pm
3.92%
Financial Progress
3rd Expenditure
of ₹ 7600 (0.08 Lacs ) done.
Cummulative ₹ 20.99Lacs ( against 535.1Lacs )
on Wednesday, March 5th 2025, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 2nd time
on Friday, March 14th 2025, 6:30:00 pm
3.96%
Financial Progress
4th Expenditure
of ₹ 20605 (0.21 Lacs ) done.
Cummulative ₹ 21.20Lacs ( against 535.1Lacs )
on Thursday, March 20th 2025, 6:30:00 pm
7.71%
Financial Progress
5th Expenditure
of ₹ 2003498 (20.03 Lacs ) done.
Cummulative ₹ 41.24Lacs ( against 535.1Lacs )
on Sunday, March 23rd 2025, 6:30:00 pm
7.74%
Financial Progress
6th Expenditure
of ₹ 19285 (0.19 Lacs ) done.
Cummulative ₹ 41.43Lacs ( against 535.1Lacs )
on Thursday, March 27th 2025, 6:30:00 pm
7.80%
Financial Progress
7th Expenditure
of ₹ 28556 (0.29 Lacs ) done.
Cummulative ₹ 41.71Lacs ( against 535.1Lacs )
on Friday, March 28th 2025, 6:30:00 pm
7.80%
Financial Progress
8th Expenditure
of ₹ 2212 (0.02 Lacs ) done.
Cummulative ₹ 41.74Lacs ( against 535.1Lacs )
on Monday, March 31st 2025, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 3rd time
on Wednesday, April 2nd 2025, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 4th time
on Saturday, April 19th 2025, 7:15:59 am
PWD UttarakahndPhoto (ID 67666) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 2.225km
Remark : R/w work
on Tuesday, April 29th 2025, 6:30:00 pm
12.67%
Financial Progress
9th Expenditure
of ₹ 2608541 (26.09 Lacs ) done.
Cummulative ₹ 67.82Lacs ( against 535.1Lacs )
on Sunday, May 18th 2025, 6:30:00 pm
12.73%
Financial Progress
10th Expenditure
of ₹ 31500 (0.32 Lacs ) done.
Cummulative ₹ 68.14Lacs ( against 535.1Lacs )
on Friday, May 30th 2025, 6:30:00 pm
14.94%
Financial Progress
11th Expenditure
of ₹ 1178919 (11.79 Lacs ) done.
Cummulative ₹ 79.93Lacs ( against 535.1Lacs )
on Tuesday, June 24th 2025, 6:30:00 pm
14.95%
Financial Progress
12th Expenditure
of ₹ 8496 (0.08 Lacs ) done.
Cummulative ₹ 80.01Lacs ( against 535.1Lacs )
on Thursday, July 10th 2025, 6:30:00 pm
14.98%
Financial Progress
13th Expenditure
of ₹ 16992 (0.17 Lacs ) done.
Cummulative ₹ 80.18Lacs ( against 535.1Lacs )
on Monday, July 14th 2025, 5:18:56 am
PWD UttarakahndPhoto (ID 79981) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 4.050
Remark : Scupper work
on Monday, July 14th 2025, 5:32:42 am
PWD UttarakahndPhoto (ID 79982) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 5.100
Remark : Wbm work
on Monday, July 28th 2025, 6:30:00 pm
24.88%
Financial Progress
14th Expenditure
of ₹ 5293514 (52.94 Lacs ) done.
Cummulative ₹ 133.12Lacs ( against 535.1Lacs )
on Thursday, July 31st 2025, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 5th time
on Saturday, August 2nd 2025, 6:30:00 pm
45%
Physical Progress
Physical Progress Reported at 6th time
on Wednesday, August 20th 2025, 7:08:42 am
PWD UttarakahndPhoto (ID 81655) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 5.175
Remark : Crash barrier work
on Wednesday, August 20th 2025, 7:27:43 am
PWD UttarakahndPhoto (ID 81656) from Site Received
Uploader : Anuj Bhardwaj, Assistant Engineer Civil ,CD Ukhimath
Landmark : 5.175
Remark : Wbm work