on Wednesday, January 1st 2025, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद टिहरी गढ़वाल के विधानसभा क्षेत्र टिहरी में छडे नामे तोक से कुम्हारधार मो0 मार्ग का सुधारीकरण एवं डामरीकरण कार्य (द्वितीय चरण)
on Sunday, March 23rd 2025, 6:30:00 pm
0.06%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 171.68Lacs )
on Sunday, March 30th 2025, 6:30:00 pm
0.06%
Financial Progress
2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 171.68Lacs )
on Monday, May 19th 2025, 6:30:00 pm
0.22%
Financial Progress
3rd Expenditure
of ₹ 27660 (0.28 Lacs ) done.
Cummulative ₹ 0.38Lacs ( against 171.68Lacs )
on Monday, May 19th 2025, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, June 17th 2025, 12:03:44 pm
PWD UttarakahndPhoto (ID 75611) from Site Received
Uploader : Deepak Kumar Agarawal, Assistant Engineer Civil ,PD New Tehri
Landmark : Km. 1.400
Remark : Collection for G1 Poor quality of stone ballast
on Monday, June 23rd 2025, 6:30:00 pm
0.25%
Financial Progress
4th Expenditure
of ₹ 5752 (0.06 Lacs ) done.
Cummulative ₹ 0.43Lacs ( against 171.68Lacs )
on Wednesday, June 25th 2025, 9:40:10 am
PWD UttarakahndPhoto (ID 78212) from Site Received
Uploader : Deepak Kumar Agarawal, Assistant Engineer Civil ,PD New Tehri
Landmark : .75
Remark : Road work inspection.
G1 work is in progress, this work is rejected in the entire length because work is not done as per specifications.
on Thursday, June 26th 2025, 10:03:57 am
PWD UttarakahndPhoto (ID 78425) from Site Received
Uploader : Manoj Singh Panwar, Assistant Engineer Civil ,8th Circle Tehri
Landmark : 0-200
Remark : Visit
on Thursday, June 26th 2025, 10:11:14 am
PWD UttarakahndPhoto (ID 78427) from Site Received
Uploader : Manoj Singh Panwar, Assistant Engineer Civil ,8th Circle Tehri
Landmark : 0.700
Remark : Visit
on Thursday, June 26th 2025, 10:47:58 am
PWD UttarakahndPhoto (ID 78430) from Site Received
Uploader : Manoj Singh Panwar, Assistant Engineer Civil ,8th Circle Tehri
Landmark : 0
Remark : Visit
on Sunday, June 29th 2025, 6:30:00 pm
23.67%
Financial Progress
5th Expenditure
of ₹ 4020000 (40.20 Lacs ) done.
Cummulative ₹ 40.63Lacs ( against 171.68Lacs )
on Wednesday, July 16th 2025, 7:17:40 am
PWD UttarakahndPhoto (ID 80105) from Site Received
Uploader : Jai Prakash Bhatt, Additional Assistant Engineer Civil ,PD Haridwar
Landmark : Km2 ch 1.800
Remark : Work inspection by Executive Engineer
on Sunday, August 3rd 2025, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 2nd time