8 months ago

on Wednesday, January 1st 2025, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद टिहरी गढ़वाल के विधानसभा क्षेत्र टिहरी में छडे नामे तोक से कुम्हारधार मो0 मार्ग का सुधारीकरण एवं डामरीकरण कार्य (द्वितीय चरण)

5 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
0.06%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 171.68Lacs )

5 months ago

on Sunday, March 30th 2025, 6:30:00 pm
0.06%
Financial Progress

2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 171.68Lacs )

3 months ago

on Monday, May 19th 2025, 6:30:00 pm
0.22%
Financial Progress

3rd Expenditure
of ₹ 27660 (0.28 Lacs ) done.
Cummulative ₹ 0.38Lacs ( against 171.68Lacs )

3 months ago

on Monday, May 19th 2025, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

2 months ago

on Tuesday, June 17th 2025, 12:03:44 pm
<span class="4">Picture Id:75611</span>
PWD Uttarakahnd
Photo (ID 75611) from Site Received
Uploader : Deepak Kumar Agarawal, Assistant Engineer Civil ,PD New Tehri
Landmark : Km. 1.400
Remark : Collection for G1 Poor quality of stone ballast

2 months ago

on Monday, June 23rd 2025, 6:30:00 pm
0.25%
Financial Progress

4th Expenditure
of ₹ 5752 (0.06 Lacs ) done.
Cummulative ₹ 0.43Lacs ( against 171.68Lacs )

2 months ago

on Wednesday, June 25th 2025, 9:40:10 am
<span class="4">Picture Id:78212</span>
PWD Uttarakahnd
Photo (ID 78212) from Site Received
Uploader : Deepak Kumar Agarawal, Assistant Engineer Civil ,PD New Tehri
Landmark : .75
Remark : Road work inspection. G1 work is in progress, this work is rejected in the entire length because work is not done as per specifications.

2 months ago

on Thursday, June 26th 2025, 10:03:57 am
<span class="4">Picture Id:78425</span>
PWD Uttarakahnd
Photo (ID 78425) from Site Received
Uploader : Manoj Singh Panwar, Assistant Engineer Civil ,8th Circle Tehri
Landmark : 0-200
Remark : Visit

2 months ago

on Thursday, June 26th 2025, 10:11:14 am
<span class="4">Picture Id:78427</span>
PWD Uttarakahnd
Photo (ID 78427) from Site Received
Uploader : Manoj Singh Panwar, Assistant Engineer Civil ,8th Circle Tehri
Landmark : 0.700
Remark : Visit

2 months ago

on Thursday, June 26th 2025, 10:47:58 am
<span class="4">Picture Id:78430</span>
PWD Uttarakahnd
Photo (ID 78430) from Site Received
Uploader : Manoj Singh Panwar, Assistant Engineer Civil ,8th Circle Tehri
Landmark : 0
Remark : Visit

2 months ago

on Sunday, June 29th 2025, 6:30:00 pm
23.67%
Financial Progress

5th Expenditure
of ₹ 4020000 (40.20 Lacs ) done.
Cummulative ₹ 40.63Lacs ( against 171.68Lacs )

a month ago

on Wednesday, July 16th 2025, 7:17:40 am
<span class="4">Picture Id:80105</span>
PWD Uttarakahnd
Photo (ID 80105) from Site Received
Uploader : Jai Prakash Bhatt, Additional Assistant Engineer Civil ,PD Haridwar
Landmark : Km2 ch 1.800
Remark : Work inspection by Executive Engineer

22 days ago

on Sunday, August 3rd 2025, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 2nd time

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable
refresh data by PWD Uttarakhand Engineeres | View code by HandsOnDataViz with Leaflet | © OpenStreetMap contributors