10 years ago

on Thursday, June 4th 2015, 6:30:00 pm
Work Sanctioned
जनपद टिहरी गढ़वाल के विधानसभा क्षेत्र प्रतापनगर के अन्तर्गत कण्डियालगांव से दिन्याली देवी मो0 मार्ग का निर्माण कार्य

9 years ago

on Monday, February 29th 2016, 6:30:00 pm
0.19%
Financial Progress

1st Expenditure
of ₹ 9700 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 50.85Lacs )

9 years ago

on Friday, September 30th 2016, 6:30:00 pm
0.35%
Financial Progress

2nd Expenditure
of ₹ 8000 (0.08 Lacs ) done.
Cummulative ₹ 0.18Lacs ( against 50.85Lacs )

9 years ago

on Monday, October 31st 2016, 6:30:00 pm
0.62%
Financial Progress

3rd Expenditure
of ₹ 13868 (0.14 Lacs ) done.
Cummulative ₹ 0.32Lacs ( against 50.85Lacs )

8 years ago

on Wednesday, January 31st 2018, 6:30:00 pm
12.24%
Financial Progress

4th Expenditure
of ₹ 590975 (5.91 Lacs ) done.
Cummulative ₹ 6.23Lacs ( against 50.85Lacs )

7 years ago

on Wednesday, February 28th 2018, 6:30:00 pm
14.00%
Financial Progress

5th Expenditure
of ₹ 89332 (0.89 Lacs ) done.
Cummulative ₹ 7.12Lacs ( against 50.85Lacs )

7 years ago

on Thursday, May 31st 2018, 6:30:00 pm
21.80%
Financial Progress

6th Expenditure
of ₹ 396550 (3.97 Lacs ) done.
Cummulative ₹ 11.08Lacs ( against 50.85Lacs )

7 years ago

on Saturday, June 30th 2018, 6:30:00 pm
22.04%
Financial Progress

7th Expenditure
of ₹ 12500 (0.13 Lacs ) done.
Cummulative ₹ 11.21Lacs ( against 50.85Lacs )

7 years ago

on Friday, August 31st 2018, 6:30:00 pm
22.19%
Financial Progress

8th Expenditure
of ₹ 7243 (0.07 Lacs ) done.
Cummulative ₹ 11.28Lacs ( against 50.85Lacs )

7 years ago

on Wednesday, October 31st 2018, 6:30:00 pm
29.20%
Financial Progress

9th Expenditure
of ₹ 356720 (3.57 Lacs ) done.
Cummulative ₹ 14.85Lacs ( against 50.85Lacs )

6 years ago

on Thursday, February 28th 2019, 6:30:00 pm
41.87%
Financial Progress

10th Expenditure
of ₹ 643998 (6.44 Lacs ) done.
Cummulative ₹ 21.29Lacs ( against 50.85Lacs )

5 years ago

on Sunday, May 31st 2020, 6:30:00 pm
49.06%
Financial Progress

11th Expenditure
of ₹ 365750 (3.66 Lacs ) done.
Cummulative ₹ 24.95Lacs ( against 50.85Lacs )

5 years ago

on Monday, August 31st 2020, 6:30:00 pm
49.28%
Financial Progress

12th Expenditure
of ₹ 11020 (0.11 Lacs ) done.
Cummulative ₹ 25.06Lacs ( against 50.85Lacs )

5 years ago

on Saturday, October 31st 2020, 6:30:00 pm
51.13%
Financial Progress

13th Expenditure
of ₹ 94100 (0.94 Lacs ) done.
Cummulative ₹ 26.00Lacs ( against 50.85Lacs )

2 years ago

on Sunday, March 26th 2023, 6:30:00 pm
55.12%
Financial Progress

14th Expenditure
of ₹ 203000 (2.03 Lacs ) done.
Cummulative ₹ 28.03Lacs ( against 50.85Lacs )

a year ago

on Tuesday, March 19th 2024, 6:30:00 pm
55.89%
Financial Progress

15th Expenditure
of ₹ 39000 (0.39 Lacs ) done.
Cummulative ₹ 28.42Lacs ( against 50.85Lacs )

a year ago

on Thursday, September 12th 2024, 6:30:00 pm
56.67%
Financial Progress

16th Expenditure
of ₹ 39949 (0.40 Lacs ) done.
Cummulative ₹ 28.82Lacs ( against 50.85Lacs )

9 months ago

on Wednesday, December 4th 2024, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 1st time

9 months ago

on Friday, December 6th 2024, 6:30:00 pm
56%

Physical Progress
Physical Progress Reported at 2nd time

2 months ago

on Sunday, June 29th 2025, 6:30:00 pm
56.67%
Financial Progress

17th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 28.82Lacs ( against 50.85Lacs )

2 months ago

on Sunday, July 6th 2025, 6:30:00 pm
68.57%
Financial Progress

25th Expenditure
of ₹ 29580 (0.30 Lacs ) done.
Cummulative ₹ 34.87Lacs ( against 50.85Lacs )

2 months ago

on Sunday, July 6th 2025, 6:30:00 pm
67.99%
Financial Progress

24th Expenditure
of ₹ 136900 (1.37 Lacs ) done.
Cummulative ₹ 34.57Lacs ( against 50.85Lacs )

2 months ago

on Sunday, July 6th 2025, 6:30:00 pm
65.30%
Financial Progress

23rd Expenditure
of ₹ 52000 (0.52 Lacs ) done.
Cummulative ₹ 33.21Lacs ( against 50.85Lacs )

2 months ago

on Sunday, July 6th 2025, 6:30:00 pm
64.28%
Financial Progress

22nd Expenditure
of ₹ 83000 (0.83 Lacs ) done.
Cummulative ₹ 32.69Lacs ( against 50.85Lacs )

2 months ago

on Sunday, July 6th 2025, 6:30:00 pm
62.65%
Financial Progress

21st Expenditure
of ₹ 105850 (1.06 Lacs ) done.
Cummulative ₹ 31.86Lacs ( against 50.85Lacs )

2 months ago

on Sunday, July 6th 2025, 6:30:00 pm
60.56%
Financial Progress

20th Expenditure
of ₹ 83000 (0.83 Lacs ) done.
Cummulative ₹ 30.80Lacs ( against 50.85Lacs )

2 months ago

on Sunday, July 6th 2025, 6:30:00 pm
58.93%
Financial Progress

19th Expenditure
of ₹ 76000 (0.76 Lacs ) done.
Cummulative ₹ 29.97Lacs ( against 50.85Lacs )

2 months ago

on Sunday, July 6th 2025, 6:30:00 pm
57.44%
Financial Progress

18th Expenditure
of ₹ 39000 (0.39 Lacs ) done.
Cummulative ₹ 29.21Lacs ( against 50.85Lacs )