@
Refresh data
Refresh data

9 years ago

on Monday, July 25th 2016, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री जी घोषणा सं0 253/2014 के अन्तर्गत जनपद टिहरी गढ़वाल के विधानसभा टिहरी के अन्तर्गत राजकीय पालीटेक्निक कुमारधार से जाखणीधार तक मो0 मार्ग का नव निर्माण कार्य

9 years ago

on Tuesday, February 28th 2017, 6:30:00 pm
0.07%
Financial Progress

1st Expenditure
of ₹ 9700 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 140.59Lacs )

7 years ago

on Thursday, February 28th 2019, 6:30:00 pm
0.58%
Financial Progress

2nd Expenditure
of ₹ 72316 (0.72 Lacs ) done.
Cummulative ₹ 0.82Lacs ( against 140.59Lacs )

6 years ago

on Monday, August 19th 2019, 6:30:00 pm

Technical Sanction
of ₹ 140.59 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 5620/738c-8/19

3 years ago

on Thursday, July 21st 2022, 6:30:00 pm
5.03%
Financial Progress

3rd Expenditure
of ₹ 624657 (6.25 Lacs ) done.
Cummulative ₹ 7.07Lacs ( against 140.59Lacs )

3 years ago

on Tuesday, September 13th 2022, 6:30:00 pm
5.61%
Financial Progress

4th Expenditure
of ₹ 82728 (0.83 Lacs ) done.
Cummulative ₹ 7.89Lacs ( against 140.59Lacs )

3 years ago

on Thursday, October 13th 2022, 6:30:00 pm
5.69%
Financial Progress

5th Expenditure
of ₹ 9900 (0.10 Lacs ) done.
Cummulative ₹ 7.99Lacs ( against 140.59Lacs )

3 years ago

on Tuesday, January 3rd 2023, 6:30:00 pm
6.06%
Financial Progress

7th Expenditure
of ₹ 26050 (0.26 Lacs ) done.
Cummulative ₹ 8.51Lacs ( against 140.59Lacs )

3 years ago

on Tuesday, January 3rd 2023, 6:30:00 pm
5.87%
Financial Progress

6th Expenditure
of ₹ 26050 (0.26 Lacs ) done.
Cummulative ₹ 8.25Lacs ( against 140.59Lacs )

3 years ago

on Sunday, January 8th 2023, 6:30:00 pm
9.47%
Financial Progress

8th Expenditure
of ₹ 480236 (4.80 Lacs ) done.
Cummulative ₹ 13.32Lacs ( against 140.59Lacs )

3 years ago

on Tuesday, January 17th 2023, 6:18:56 am
<span class="4">Picture Id:15513</span>
PWD Uttarakahnd
Photo (ID 15513) from Site Received
Uploader : Deepak Kumar Agarawal, Assistant Engineer Civil ,PD New Tehri
Landmark : 1/27 - 1/28
Remark : Inspection for cross drainage site

3 years ago

on Tuesday, January 17th 2023, 8:28:08 am
<span class="4">Picture Id:15537</span>
PWD Uttarakahnd
Photo (ID 15537) from Site Received
Uploader : Deepak Kumar Agarawal, Assistant Engineer Civil ,PD New Tehri
Landmark : 1.500-1.650
Remark : New road - Hill side cutting

3 years ago

on Tuesday, January 17th 2023, 8:32:26 am
<span class="4">Picture Id:15538</span>
PWD Uttarakahnd
Photo (ID 15538) from Site Received
Uploader : Deepak Kumar Agarawal, Assistant Engineer Civil ,PD New Tehri
Landmark : 1.45-1.59
Remark : Hill side cutting for new road

3 years ago

on Thursday, February 2nd 2023, 6:30:00 pm
9.57%
Financial Progress

9th Expenditure
of ₹ 13460 (0.13 Lacs ) done.
Cummulative ₹ 13.45Lacs ( against 140.59Lacs )

3 years ago

on Friday, February 3rd 2023, 6:30:00 pm
9.63%
Financial Progress

10th Expenditure
of ₹ 9300 (0.09 Lacs ) done.
Cummulative ₹ 13.54Lacs ( against 140.59Lacs )

3 years ago

on Tuesday, February 7th 2023, 6:30:00 pm
11.28%
Financial Progress

11th Expenditure
of ₹ 231672 (2.32 Lacs ) done.
Cummulative ₹ 15.86Lacs ( against 140.59Lacs )

3 years ago

on Tuesday, February 14th 2023, 6:30:00 pm
14.84%
Financial Progress

12th Expenditure
of ₹ 499800 (5.00 Lacs ) done.
Cummulative ₹ 20.86Lacs ( against 140.59Lacs )

3 years ago

on Monday, February 27th 2023, 6:30:00 pm
17.11%
Financial Progress

13th Expenditure
of ₹ 320237 (3.20 Lacs ) done.
Cummulative ₹ 24.06Lacs ( against 140.59Lacs )

2 years ago

on Sunday, March 19th 2023, 6:30:00 pm
22.61%
Financial Progress

14th Expenditure
of ₹ 772894 (7.73 Lacs ) done.
Cummulative ₹ 31.79Lacs ( against 140.59Lacs )

2 years ago

on Monday, July 24th 2023, 6:30:00 pm
26.85%
Financial Progress

15th Expenditure
of ₹ 595374 (5.95 Lacs ) done.
Cummulative ₹ 37.74Lacs ( against 140.59Lacs )

2 years ago

on Tuesday, July 25th 2023, 6:30:00 pm
27.02%
Financial Progress

16th Expenditure
of ₹ 24719 (0.25 Lacs ) done.
Cummulative ₹ 37.99Lacs ( against 140.59Lacs )

2 years ago

on Wednesday, July 26th 2023, 6:30:00 pm
30.03%
Financial Progress

17th Expenditure
of ₹ 422880 (4.23 Lacs ) done.
Cummulative ₹ 42.22Lacs ( against 140.59Lacs )

2 years ago

on Sunday, August 20th 2023, 6:30:00 pm
30.14%
Financial Progress

18th Expenditure
of ₹ 15000 (0.15 Lacs ) done.
Cummulative ₹ 42.37Lacs ( against 140.59Lacs )

2 years ago

on Sunday, August 20th 2023, 6:30:00 pm
30.24%
Financial Progress

19th Expenditure
of ₹ 15000 (0.15 Lacs ) done.
Cummulative ₹ 42.52Lacs ( against 140.59Lacs )

2 years ago

on Monday, August 21st 2023, 6:30:00 pm
32.44%
Financial Progress

20th Expenditure
of ₹ 308896 (3.09 Lacs ) done.
Cummulative ₹ 45.61Lacs ( against 140.59Lacs )

2 years ago

on Tuesday, August 22nd 2023, 6:30:00 pm
32.44%
Financial Progress

21st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 45.61Lacs ( against 140.59Lacs )

2 years ago

on Wednesday, August 23rd 2023, 6:30:00 pm
33.10%
Financial Progress

24th Expenditure
of ₹ 1800 (0.02 Lacs ) done.
Cummulative ₹ 46.54Lacs ( against 140.59Lacs )

2 years ago

on Wednesday, August 23rd 2023, 6:30:00 pm
33.09%
Financial Progress

23rd Expenditure
of ₹ 48000 (0.48 Lacs ) done.
Cummulative ₹ 46.52Lacs ( against 140.59Lacs )

2 years ago

on Wednesday, August 23rd 2023, 6:30:00 pm
32.75%
Financial Progress

22nd Expenditure
of ₹ 43000 (0.43 Lacs ) done.
Cummulative ₹ 46.04Lacs ( against 140.59Lacs )

2 years ago

on Wednesday, August 30th 2023, 6:30:00 pm
34.86%
Financial Progress

25th Expenditure
of ₹ 247623 (2.48 Lacs ) done.
Cummulative ₹ 49.01Lacs ( against 140.59Lacs )

2 years ago

on Wednesday, August 30th 2023, 6:30:00 pm
36.63%
Financial Progress

26th Expenditure
of ₹ 248980 (2.49 Lacs ) done.
Cummulative ₹ 51.50Lacs ( against 140.59Lacs )

2 years ago

on Monday, September 25th 2023, 6:30:00 pm
36.63%
Financial Progress

27th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 51.50Lacs ( against 140.59Lacs )

2 years ago

on Tuesday, September 26th 2023, 6:30:00 pm
37.05%
Financial Progress

28th Expenditure
of ₹ 59000 (0.59 Lacs ) done.
Cummulative ₹ 52.09Lacs ( against 140.59Lacs )

2 years ago

on Thursday, October 5th 2023, 6:30:00 pm
75%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Thursday, December 21st 2023, 6:33:24 am
<span class="4">Picture Id:33235</span>
PWD Uttarakahnd
Photo (ID 33235) from Site Received
Uploader : Deepak Kumar Agarawal, Assistant Engineer Civil ,PD New Tehri
Landmark : X section 1/29-1/30
Remark : कुम्हारधार पॉलिटेक्निक से जखनीधार मोटर मार्ग पर चल रहे कार्य का निरीक्षण किया।

2 years ago

on Thursday, December 21st 2023, 7:00:33 am
<span class="4">Picture Id:33247</span>
PWD Uttarakahnd
Photo (ID 33247) from Site Received
Uploader : Deepak Kumar Agarawal, Assistant Engineer Civil ,PD New Tehri
Landmark : X section 1/24-1/26
Remark : कुम्हारधार पॉलिटेक्निक जाखनीधार मो मार्ग नवनिर्माण कार्य पर निरीक्षण।

2 years ago

on Tuesday, March 5th 2024, 6:30:00 pm
78%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Thursday, March 7th 2024, 6:30:00 pm
37.05%
Financial Progress

29th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 52.09Lacs ( against 140.59Lacs )

a year ago

on Sunday, March 24th 2024, 6:30:00 pm
46.00%
Financial Progress

32nd Expenditure
of ₹ 420592 (4.21 Lacs ) done.
Cummulative ₹ 64.67Lacs ( against 140.59Lacs )

a year ago

on Sunday, March 24th 2024, 6:30:00 pm
41.15%
Financial Progress

30th Expenditure
of ₹ 576438 (5.76 Lacs ) done.
Cummulative ₹ 57.86Lacs ( against 140.59Lacs )

a year ago

on Sunday, March 24th 2024, 6:30:00 pm
43.01%
Financial Progress

31st Expenditure
of ₹ 260960 (2.61 Lacs ) done.
Cummulative ₹ 60.47Lacs ( against 140.59Lacs )

a year ago

on Sunday, March 24th 2024, 6:30:00 pm
54.27%
Financial Progress

34th Expenditure
of ₹ 427996 (4.28 Lacs ) done.
Cummulative ₹ 76.30Lacs ( against 140.59Lacs )

a year ago

on Sunday, March 24th 2024, 6:30:00 pm
51.23%
Financial Progress

33rd Expenditure
of ₹ 735081 (7.35 Lacs ) done.
Cummulative ₹ 72.02Lacs ( against 140.59Lacs )

a year ago

on Sunday, March 24th 2024, 6:30:00 pm
76.63%
Financial Progress

37th Expenditure
of ₹ 148487 (1.48 Lacs ) done.
Cummulative ₹ 107.74Lacs ( against 140.59Lacs )

a year ago

on Sunday, March 24th 2024, 6:30:00 pm
75.58%
Financial Progress

36th Expenditure
of ₹ 26100 (0.26 Lacs ) done.
Cummulative ₹ 106.25Lacs ( against 140.59Lacs )

a year ago

on Sunday, March 24th 2024, 6:30:00 pm
75.39%
Financial Progress

35th Expenditure
of ₹ 2968857 (29.69 Lacs ) done.
Cummulative ₹ 105.99Lacs ( against 140.59Lacs )

a year ago

on Tuesday, March 26th 2024, 6:30:00 pm
84.76%
Financial Progress

39th Expenditure
of ₹ 570471 (5.70 Lacs ) done.
Cummulative ₹ 119.16Lacs ( against 140.59Lacs )

a year ago

on Tuesday, March 26th 2024, 6:30:00 pm
80.70%
Financial Progress

38th Expenditure
of ₹ 571673 (5.72 Lacs ) done.
Cummulative ₹ 113.45Lacs ( against 140.59Lacs )

a year ago

on Friday, March 29th 2024, 6:30:00 pm
86.48%
Financial Progress

40th Expenditure
of ₹ 242299 (2.42 Lacs ) done.
Cummulative ₹ 121.58Lacs ( against 140.59Lacs )

a year ago

on Wednesday, July 10th 2024, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Monday, August 19th 2024, 6:30:00 pm
86.53%
Financial Progress

42nd Expenditure
of ₹ 4140 (0.04 Lacs ) done.
Cummulative ₹ 121.65Lacs ( against 140.59Lacs )

a year ago

on Monday, August 19th 2024, 6:30:00 pm
86.50%
Financial Progress

41st Expenditure
of ₹ 2714 (0.03 Lacs ) done.
Cummulative ₹ 121.61Lacs ( against 140.59Lacs )

a year ago

on Monday, August 19th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Friday, August 30th 2024, 6:30:00 pm
88.03%
Financial Progress

43rd Expenditure
of ₹ 211451 (2.11 Lacs ) done.
Cummulative ₹ 123.77Lacs ( against 140.59Lacs )

10 months ago

on Tuesday, November 19th 2024, 6:30:00 pm
88.17%
Financial Progress

44th Expenditure
of ₹ 18815 (0.19 Lacs ) done.
Cummulative ₹ 123.95Lacs ( against 140.59Lacs )

6 months ago

on Friday, March 14th 2025, 6:30:00 pm
88.52%
Financial Progress

45th Expenditure
of ₹ 49383 (0.49 Lacs ) done.
Cummulative ₹ 124.45Lacs ( against 140.59Lacs )

6 months ago

on Sunday, March 16th 2025, 6:30:00 pm
95.35%
Financial Progress

47th Expenditure
of ₹ 498201 (4.98 Lacs ) done.
Cummulative ₹ 134.05Lacs ( against 140.59Lacs )

6 months ago

on Sunday, March 16th 2025, 6:30:00 pm
91.81%
Financial Progress

46th Expenditure
of ₹ 462560 (4.63 Lacs ) done.
Cummulative ₹ 129.07Lacs ( against 140.59Lacs )

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable
refresh data by PWD Uttarakhand Engineeres | View code by HandsOnDataViz with Leaflet | © OpenStreetMap contributors