Work Sanctioned
मा0 मुख्यमंत्री घोषणा संख्या-775/2012 के अन्तर्गत कुसरैला से बखरोटी मोटर मार्ग के अवशेष भाग का निर्माण कार्य।(प्रथम चरण)
on Monday, April 30th 2018, 6:30:00 pm
43.81%
Financial Progress
1st Expenditure
of ₹ 1500000 (15.00 Lacs ) done.
Cummulative ₹ 15.00Lacs ( against 34.24Lacs )
on Thursday, March 30th 2023, 6:30:00 pm
68.52%
Financial Progress
2nd Expenditure
of ₹ 846000 (8.46 Lacs ) done.
Cummulative ₹ 23.46Lacs ( against 34.24Lacs )
on Wednesday, May 22nd 2024, 6:30:00 pm
73.65%
Financial Progress
3rd Expenditure
of ₹ 175791 (1.76 Lacs ) done.
Cummulative ₹ 25.22Lacs ( against 34.24Lacs )
on Thursday, August 29th 2024, 6:30:00 pm
73.65%
Financial Progress
4th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 25.22Lacs ( against 34.24Lacs )
on Wednesday, January 29th 2025, 6:30:00 pm
82.41%
Financial Progress
5th Expenditure
of ₹ 300000 (3.00 Lacs ) done.
Cummulative ₹ 28.22Lacs ( against 34.24Lacs )
on Monday, April 7th 2025, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 1st time