on Thursday, January 6th 2022, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा संख्या-1030/2021 के अन्तर्गत जनपद टिहरी गढवाल के विधानसभा क्षेत्र नरेन्द्रनगर के अन्तर्गत सौण्डी पवैथ नैल मोटर मार्ग के कि0मी0 1 से 5 में सुधारीकरण एवं डामरीकरण कार्य।
on Monday, March 21st 2022, 6:49:28 am
Technical Sanction
of ₹ 346.89 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 100/8(200)/yata-pauri/2021
on Tuesday, February 28th 2023, 6:30:00 pm
30.35%
Financial Progress
1st Expenditure
of ₹ 10528329 (105.28 Lacs ) done.
Cummulative ₹ 105.28Lacs ( against 346.89Lacs )
on Thursday, August 31st 2023, 6:30:00 pm
30.35%
Financial Progress
2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 105.28Lacs ( against 346.89Lacs )
on Tuesday, September 26th 2023, 6:30:00 pm
39.83%
Financial Progress
3rd Expenditure
of ₹ 3287827 (32.88 Lacs ) done.
Cummulative ₹ 138.16Lacs ( against 346.89Lacs )
on Thursday, October 5th 2023, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 1st time
on Monday, January 22nd 2024, 6:30:00 pm
49.40%
Financial Progress
5th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 171.37Lacs ( against 346.89Lacs )
on Monday, January 22nd 2024, 6:30:00 pm
49.40%
Financial Progress
4th Expenditure
of ₹ 3321302 (33.21 Lacs ) done.
Cummulative ₹ 171.37Lacs ( against 346.89Lacs )
on Monday, January 29th 2024, 6:30:00 pm
49.5%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, March 20th 2024, 6:30:00 pm
50.21%
Financial Progress
7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 174.16Lacs ( against 346.89Lacs )
on Wednesday, March 20th 2024, 6:30:00 pm
50.21%
Financial Progress
6th Expenditure
of ₹ 278761 (2.79 Lacs ) done.
Cummulative ₹ 174.16Lacs ( against 346.89Lacs )
on Sunday, March 24th 2024, 6:30:00 pm
67.28%
Financial Progress
8th Expenditure
of ₹ 5922907 (59.23 Lacs ) done.
Cummulative ₹ 233.39Lacs ( against 346.89Lacs )
on Tuesday, May 14th 2024, 7:54:01 am
PWD UttarakahndPhoto (ID 38544) from Site Received
Uploader : Pankaj Tiwari, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 4.50
Remark : For demo test
on Wednesday, May 15th 2024, 6:30:00 pm
63%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, May 28th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 4th time
on Thursday, May 30th 2024, 6:30:00 pm
71.30%
Financial Progress
9th Expenditure
of ₹ 1394099 (13.94 Lacs ) done.
Cummulative ₹ 247.33Lacs ( against 346.89Lacs )
on Tuesday, June 25th 2024, 6:30:00 pm
71.18%
Financial Progress
10th Expenditure
of ₹ -42000 (-0.42 Lacs ) done.
Cummulative ₹ 246.91Lacs ( against 346.89Lacs )
on Wednesday, July 3rd 2024, 6:30:00 pm
77.73%
Financial Progress
11th Expenditure
of ₹ 2271174 (22.71 Lacs ) done.
Cummulative ₹ 269.62Lacs ( against 346.89Lacs )
on Tuesday, September 3rd 2024, 6:30:00 pm
77.16%
Financial Progress
12th Expenditure
of ₹ -195000 (-1.95 Lacs ) done.
Cummulative ₹ 267.67Lacs ( against 346.89Lacs )
on Wednesday, September 11th 2024, 6:30:00 pm
91.15%
Financial Progress
13th Expenditure
of ₹ 4851924 (48.52 Lacs ) done.
Cummulative ₹ 316.19Lacs ( against 346.89Lacs )
on Monday, October 28th 2024, 6:30:00 pm
96.34%
Financial Progress
14th Expenditure
of ₹ 1800852 (18.01 Lacs ) done.
Cummulative ₹ 334.20Lacs ( against 346.89Lacs )
on Wednesday, January 29th 2025, 6:30:00 pm
96.56%
Financial Progress
15th Expenditure
of ₹ 76634 (0.77 Lacs ) done.
Cummulative ₹ 334.97Lacs ( against 346.89Lacs )
on Wednesday, February 5th 2025, 6:30:00 pm
96.78%
Financial Progress
18th Expenditure
of ₹ 31960 (0.32 Lacs ) done.
Cummulative ₹ 335.73Lacs ( against 346.89Lacs )
on Wednesday, February 5th 2025, 6:30:00 pm
96.69%
Financial Progress
17th Expenditure
of ₹ 40604 (0.41 Lacs ) done.
Cummulative ₹ 335.41Lacs ( against 346.89Lacs )
on Wednesday, February 5th 2025, 6:30:00 pm
96.57%
Financial Progress
16th Expenditure
of ₹ 4070 (0.04 Lacs ) done.
Cummulative ₹ 335.01Lacs ( against 346.89Lacs )
on Monday, February 17th 2025, 6:30:00 pm
97.28%
Financial Progress
19th Expenditure
of ₹ 170752 (1.71 Lacs ) done.
Cummulative ₹ 337.44Lacs ( against 346.89Lacs )
on Monday, March 10th 2025, 6:30:00 pm
99.80%
Financial Progress
20th Expenditure
of ₹ 875044 (8.75 Lacs ) done.
Cummulative ₹ 346.19Lacs ( against 346.89Lacs )
on Tuesday, March 25th 2025, 6:30:00 pm
99.99%
Financial Progress
22nd Expenditure
of ₹ 18526 (0.19 Lacs ) done.
Cummulative ₹ 346.86Lacs ( against 346.89Lacs )
on Tuesday, March 25th 2025, 6:30:00 pm
99.94%
Financial Progress
21st Expenditure
of ₹ 48718 (0.49 Lacs ) done.
Cummulative ₹ 346.68Lacs ( against 346.89Lacs )
on Friday, April 4th 2025, 8:10:19 am
PWD UttarakahndPhoto (ID 67404) from Site Received
Uploader : Pankaj Tiwari, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 1/39
Remark : Maintenance inspection