Work Sanctioned
मा0 मुख्यमंत्री जी की घोषणा संख्या 1035/2021 के अन्तर्गत जनपद टिहरी गढवाल के विधानसभा क्षेत्र नरेन्द्रनगर में आमपाटा-अडाना-पाली मोटर मार्ग का डामरीकरण कार्य।
on Sunday, July 14th 2024, 6:30:00 pm
10.23%
Financial Progress
1st Expenditure
of ₹ 2338145 (23.38 Lacs ) done.
Cummulative ₹ 23.38Lacs ( against 228.53Lacs )
on Tuesday, September 3rd 2024, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, October 3rd 2024, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, October 8th 2024, 7:30:38 am
PWD UttarakahndPhoto (ID 54485) from Site Received
Uploader : Gambeer Singh Aswal, Assistant Engineer Civil ,CD Narendnagar
Landmark : 2.70
Remark : Construction of rcc slab supper under progress
on Tuesday, October 8th 2024, 7:40:43 am
PWD UttarakahndPhoto (ID 54490) from Site Received
Uploader : Gambeer Singh Aswal, Assistant Engineer Civil ,CD Narendnagar
Landmark : KM 2.325
Remark : Construction of rcc supper under progress
on Tuesday, October 8th 2024, 7:56:28 am
PWD UttarakahndPhoto (ID 54494) from Site Received
Uploader : Gambeer Singh Aswal, Assistant Engineer Civil ,CD Narendnagar
Landmark : 2.30
Remark : WBM G1 work in progress
on Wednesday, November 6th 2024, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 3rd time
on Thursday, November 28th 2024, 10:29:16 am
PWD UttarakahndPhoto (ID 59862) from Site Received
Uploader : Gambeer Singh Aswal, Assistant Engineer Civil ,CD Narendnagar
Landmark : 1.800 Adana
Remark : G2 work in progress
on Monday, December 2nd 2024, 6:30:00 pm
35%
Physical Progress
Physical Progress Reported at 4th time
on Tuesday, December 3rd 2024, 10:23:36 am
PWD UttarakahndPhoto (ID 60263) from Site Received
Uploader : Vijay Kumar Mogha, Executive Engineer Civil ,CD Narendnagar
Landmark : 2.700
Remark : Crust checking
on Tuesday, December 3rd 2024, 10:33:32 am
PWD UttarakahndPhoto (ID 60292) from Site Received
Uploader : Vijay Kumar Mogha, Executive Engineer Civil ,CD Narendnagar
Landmark : 2.500
Remark : Crust checking
on Tuesday, December 10th 2024, 9:12:32 am
PWD UttarakahndPhoto (ID 60799) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 0.100 Aampata
Remark : G-1, Sieve Analysis
on Tuesday, December 10th 2024, 10:17:10 am
PWD UttarakahndPhoto (ID 60804) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 0.400,Aampata
Remark : G-1, Laying Work ongoing in Ampata Adana Pali Motor Road
on Wednesday, December 11th 2024, 6:30:00 pm
31.11%
Financial Progress
2nd Expenditure
of ₹ 4771137 (47.71 Lacs ) done.
Cummulative ₹ 71.09Lacs ( against 228.53Lacs )
on Tuesday, December 17th 2024, 10:12:49 am
PWD UttarakahndPhoto (ID 61341) from Site Received
Uploader : Gambeer Singh Aswal, Assistant Engineer Civil ,CD Narendnagar
Landmark : 0.300
Remark : G1 laying work in progress
on Tuesday, December 17th 2024, 10:54:24 am
PWD UttarakahndPhoto (ID 61345) from Site Received
Uploader : Gambeer Singh Aswal, Assistant Engineer Civil ,CD Narendnagar
Landmark : 2.650
Remark : Supper work in progress
on Monday, December 30th 2024, 6:30:00 pm
31.11%
Financial Progress
3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 71.09Lacs ( against 228.53Lacs )
on Wednesday, January 29th 2025, 6:30:00 pm
46.66%
Financial Progress
4th Expenditure
of ₹ 3553755 (35.54 Lacs ) done.
Cummulative ₹ 106.63Lacs ( against 228.53Lacs )
on Thursday, February 13th 2025, 10:04:26 am
PWD UttarakahndPhoto (ID 64398) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 1.250 Aampata
Remark : G2, Laying work in Aampata Adana Pali Motor Road
on Thursday, February 13th 2025, 10:08:24 am
PWD UttarakahndPhoto (ID 64399) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 1.250 Aampata
Remark : G2 Laying work at Aampata Adana Pali Motor Road
on Thursday, February 13th 2025, 10:19:47 am
PWD UttarakahndPhoto (ID 64401) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 1.275Aampata
Remark : G2 Laying work in Progress at Aampata Adana Pali Motor Road
on Friday, February 21st 2025, 6:30:00 pm
66.61%
Financial Progress
5th Expenditure
of ₹ 4559491 (45.59 Lacs ) done.
Cummulative ₹ 152.23Lacs ( against 228.53Lacs )
on Wednesday, March 5th 2025, 6:30:00 pm
68%
Physical Progress
Physical Progress Reported at 5th time
on Tuesday, April 1st 2025, 9:38:49 am
PWD UttarakahndPhoto (ID 66744) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 0.450 Aampata
Remark : G3 Laying work in Aampata Adana Pali Motor Road
on Tuesday, April 1st 2025, 9:42:54 am
PWD UttarakahndPhoto (ID 66745) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 0.400 to 0.450/Aampata
Remark : WBM.Grading-3 Laying work in Aampata Adana Pali Motor Road
on Tuesday, April 1st 2025, 10:42:06 am
PWD UttarakahndPhoto (ID 66749) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : Ch -0.450/Aampata
Remark : WBM, Grading 3 Laying in Aampata Adana Pali Motor Road
on Tuesday, April 1st 2025, 6:30:00 pm
75%
Physical Progress
Physical Progress Reported at 6th time
on Tuesday, April 15th 2025, 9:20:11 am
PWD UttarakahndPhoto (ID 67338) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : Ch.2.625,Adana
Remark : Tack coat at ch.2.625 Aampata Adana Pali Motor Road
on Tuesday, April 15th 2025, 9:38:39 am
PWD UttarakahndPhoto (ID 67339) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : Ch.2.625,Adana
Remark : P.C.Work on going at Aampata Adana Pali Motor Road ch.2.625
on Tuesday, April 15th 2025, 10:10:00 am
PWD UttarakahndPhoto (ID 67346) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 2.625/Adana
Remark : PC work on going at Aampata Adana Pali Motor Road
on Tuesday, April 15th 2025, 12:10:25 pm
PWD UttarakahndPhoto (ID 67356) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 2.800/Adana
Remark : Seal Coat at Aampata Adana Pali Motor Road
on Thursday, April 17th 2025, 6:57:17 am
PWD UttarakahndPhoto (ID 67432) from Site Received
Uploader : Gambeer Singh Aswal, Assistant Engineer Civil ,CD Narendnagar
Landmark : 2.400 Adana
Remark : PC work in progress
on Saturday, April 19th 2025, 10:00:22 am
PWD UttarakahndPhoto (ID 67681) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 2.100/Adana
Remark : PC work on going in Aampata Adana Pali Motor Road
on Saturday, April 19th 2025, 10:08:58 am
PWD UttarakahndPhoto (ID 67682) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 2.225/Adana
Remark : PC work ongoing in Aampata Adana Pali Motor Road
on Tuesday, April 22nd 2025, 7:28:28 am
PWD UttarakahndPhoto (ID 67850) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 1.450/Adana
Remark : PC work ongoing in Aampata Adana Pali Motor Road
on Tuesday, April 22nd 2025, 7:32:25 am
PWD UttarakahndPhoto (ID 67852) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 1.425/Adana
Remark : PC work ongoing in Aampata Adana Pali Motor Road
on Friday, April 25th 2025, 7:23:09 am
PWD UttarakahndPhoto (ID 68175) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 1.750/Adana
Remark : PC work ongoing in Aampata Adana Pali Motor Road
on Friday, April 25th 2025, 10:33:13 am
PWD UttarakahndPhoto (ID 68234) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 1.625/Adana
Remark : PC,Seal Coat ongoing in Aampata Adana Pali Motor Road
on Thursday, May 8th 2025, 7:04:19 am
PWD UttarakahndPhoto (ID 70044) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 0.950/Aampata
Remark : PC Work on going in Aampata Adana Pali Motor Road
on Thursday, May 8th 2025, 7:31:24 am
PWD UttarakahndPhoto (ID 70049) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : Km.1.00/Aampata
Remark : P.C.Work on going in Aampata Adana Pali Motor Road
on Monday, May 12th 2025, 7:07:14 am
PWD UttarakahndPhoto (ID 70407) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 0.325/Aampata
Remark : PC work ongoing in Aampata Adana Pali Motor Road
on Monday, May 12th 2025, 7:16:57 am
PWD UttarakahndPhoto (ID 70408) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 0.125/Aampata
Remark : PC Work on going in Aampata Adana Pali Motor Road
on Monday, May 12th 2025, 10:34:24 am
PWD UttarakahndPhoto (ID 70429) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 0.100/Aampata
Remark : PC Work on going in Aampata Adana Pali Motor Road
on Monday, May 12th 2025, 10:41:18 am
PWD UttarakahndPhoto (ID 70432) from Site Received
Uploader : Vinod Kumar Nautiyal, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : 0.075/Aampata
Remark : PC work ongoing in Aampata Adana Pali Motor Road
on Monday, May 12th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 7th time
on Friday, May 16th 2025, 12:09:25 pm
PWD UttarakahndPhoto (ID 71379) from Site Received
Uploader : Gambeer Singh Aswal, Assistant Engineer Civil ,CD Narendnagar
Landmark : 0.00 Ampata kafolgoan road junction
Remark : PC work completed.
on Wednesday, May 28th 2025, 6:30:00 pm
76.91%
Financial Progress
6th Expenditure
of ₹ 2354208 (23.54 Lacs ) done.
Cummulative ₹ 175.77Lacs ( against 228.53Lacs )
on Sunday, June 29th 2025, 6:30:00 pm
89.48%
Financial Progress
7th Expenditure
of ₹ 2872325 (28.72 Lacs ) done.
Cummulative ₹ 204.49Lacs ( against 228.53Lacs )