on Thursday, September 3rd 2020, 6:30:00 pm
Work Sanctioned
घनसाली-मूलगढ-चिरबिटिया मोटर मार्ग के कि0मी0-17 थौलधार, सरोली-धारगांव-मयाली तक मोटर मार्ग का नव निर्माण कार्य।
on Sunday, February 28th 2021, 6:30:00 pm
0.70%
Financial Progress
1st Expenditure
of ₹ 9912 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 14.19Lacs )
on Tuesday, August 29th 2023, 6:30:00 pm
4.22%
Financial Progress
2nd Expenditure
of ₹ 49973 (0.50 Lacs ) done.
Cummulative ₹ 0.60Lacs ( against 14.19Lacs )
on Sunday, October 29th 2023, 6:30:00 pm
8.13%
Financial Progress
3rd Expenditure
of ₹ 55507 (0.56 Lacs ) done.
Cummulative ₹ 1.15Lacs ( against 14.19Lacs )
on Wednesday, February 28th 2024, 6:30:00 pm
8.59%
Financial Progress
4th Expenditure
of ₹ 6500 (0.07 Lacs ) done.
Cummulative ₹ 1.22Lacs ( against 14.19Lacs )
on Friday, April 18th 2025, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time