10 years ago

on Monday, February 1st 2016, 6:30:00 pm
Work Sanctioned
जनपद टिहरी गढवाल के विधानसभा क्षेत्र धनोल्टी के अन्तर्गत महेड़ा से अनुसूचित बस्ती दौड़का तक मोटर मार्ग का नव निर्माण कार्य।

9 years ago

on Sunday, October 23rd 2016, 6:30:00 pm

Technical Sanction
of ₹ 19.88 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. E.E. No- 303/23C

8 years ago

on Sunday, April 30th 2017, 6:30:00 pm
2.01%
Financial Progress

1st Expenditure
of ₹ 39900 (0.40 Lacs ) done.
Cummulative ₹ 0.40Lacs ( against 19.88Lacs )

7 years ago

on Thursday, February 28th 2019, 6:30:00 pm
4.89%
Financial Progress

2nd Expenditure
of ₹ 57246 (0.57 Lacs ) done.
Cummulative ₹ 0.97Lacs ( against 19.88Lacs )

a year ago

on Friday, September 6th 2024, 6:30:00 pm
11.53%
Financial Progress

3rd Expenditure
of ₹ 132000 (1.32 Lacs ) done.
Cummulative ₹ 2.29Lacs ( against 19.88Lacs )

a year ago

on Friday, September 6th 2024, 6:30:00 pm
63.10%
Financial Progress

9th Expenditure
of ₹ 55200 (0.55 Lacs ) done.
Cummulative ₹ 12.54Lacs ( against 19.88Lacs )

a year ago

on Friday, September 6th 2024, 6:30:00 pm
60.32%
Financial Progress

8th Expenditure
of ₹ 77000 (0.77 Lacs ) done.
Cummulative ₹ 11.99Lacs ( against 19.88Lacs )

a year ago

on Friday, September 6th 2024, 6:30:00 pm
56.45%
Financial Progress

7th Expenditure
of ₹ 93500 (0.94 Lacs ) done.
Cummulative ₹ 11.22Lacs ( against 19.88Lacs )

a year ago

on Friday, September 6th 2024, 6:30:00 pm
51.74%
Financial Progress

6th Expenditure
of ₹ 676500 (6.76 Lacs ) done.
Cummulative ₹ 10.29Lacs ( against 19.88Lacs )

a year ago

on Friday, September 6th 2024, 6:30:00 pm
17.71%
Financial Progress

5th Expenditure
of ₹ 46000 (0.46 Lacs ) done.
Cummulative ₹ 3.52Lacs ( against 19.88Lacs )

a year ago

on Friday, September 6th 2024, 6:30:00 pm
15.40%
Financial Progress

4th Expenditure
of ₹ 77000 (0.77 Lacs ) done.
Cummulative ₹ 3.06Lacs ( against 19.88Lacs )

a year ago

on Friday, September 6th 2024, 6:30:00 pm
76.72%
Financial Progress

11th Expenditure
of ₹ 17000 (0.17 Lacs ) done.
Cummulative ₹ 15.25Lacs ( against 19.88Lacs )

a year ago

on Friday, September 6th 2024, 6:30:00 pm
75.87%
Financial Progress

10th Expenditure
of ₹ 253900 (2.54 Lacs ) done.
Cummulative ₹ 15.08Lacs ( against 19.88Lacs )

a year ago

on Sunday, September 29th 2024, 6:30:00 pm
84.99%
Financial Progress

13th Expenditure
of ₹ 95686 (0.96 Lacs ) done.
Cummulative ₹ 16.90Lacs ( against 19.88Lacs )

a year ago

on Sunday, September 29th 2024, 6:30:00 pm
80.17%
Financial Progress

12th Expenditure
of ₹ 68605 (0.69 Lacs ) done.
Cummulative ₹ 15.94Lacs ( against 19.88Lacs )

9 months ago

on Friday, November 22nd 2024, 6:30:00 pm
84.99%
Financial Progress

14th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 16.90Lacs ( against 19.88Lacs )

8 months ago

on Sunday, December 22nd 2024, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 1st time