18 years ago

on Sunday, March 23rd 2008, 6:30:00 pm
Work Sanctioned
चम्बा मसूरी मोटर मार्ग के चोपड़ियालगांव (चुरेड़धार) ग्राम से नैलबागी मोटर मार्ग का नव निर्माण कार्य एस0सी0पी0

17 years ago

on Saturday, February 28th 2009, 6:30:00 pm
0.04%
Financial Progress

1st Expenditure
of ₹ 12000 (0.12 Lacs ) done.
Cummulative ₹ 0.12Lacs ( against 280Lacs )

16 years ago

on Thursday, April 30th 2009, 6:30:00 pm
0.27%
Financial Progress

2nd Expenditure
of ₹ 63000 (0.63 Lacs ) done.
Cummulative ₹ 0.75Lacs ( against 280Lacs )

16 years ago

on Sunday, May 31st 2009, 6:30:00 pm
0.41%
Financial Progress

3rd Expenditure
of ₹ 40617 (0.41 Lacs ) done.
Cummulative ₹ 1.16Lacs ( against 280Lacs )

16 years ago

on Sunday, January 31st 2010, 6:30:00 pm
0.63%
Financial Progress

4th Expenditure
of ₹ 61815 (0.62 Lacs ) done.
Cummulative ₹ 1.77Lacs ( against 280Lacs )

16 years ago

on Sunday, February 28th 2010, 6:30:00 pm
0.86%
Financial Progress

5th Expenditure
of ₹ 64541 (0.65 Lacs ) done.
Cummulative ₹ 2.42Lacs ( against 280Lacs )

15 years ago

on Monday, January 31st 2011, 6:30:00 pm
0.87%
Financial Progress

6th Expenditure
of ₹ 1800 (0.02 Lacs ) done.
Cummulative ₹ 2.44Lacs ( against 280Lacs )

14 years ago

on Wednesday, August 31st 2011, 6:30:00 pm
0.94%
Financial Progress

7th Expenditure
of ₹ 19996 (0.20 Lacs ) done.
Cummulative ₹ 2.64Lacs ( against 280Lacs )

12 years ago

on Friday, February 28th 2014, 6:30:00 pm
0.96%
Financial Progress

8th Expenditure
of ₹ 3950 (0.04 Lacs ) done.
Cummulative ₹ 2.68Lacs ( against 280Lacs )