7 years ago

on Monday, October 22nd 2018, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री जी की घोषणा सं0:- 71/2017 के अंतर्गत जनपद टिहरी गढ़वाल के विधानसभा क्षेत्र देवप्रयाग के विकासखण्ड कीर्तिनगर के अन्तर्गत राड़ागाड़ से टोला तक मोटर मार्ग का नवनिर्माण कार्य (प्रथम चरण)

6 years ago

on Thursday, February 28th 2019, 6:30:00 pm
0.33%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 30Lacs )

6 years ago

on Saturday, November 30th 2019, 6:30:00 pm
0.67%
Financial Progress

2nd Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.20Lacs ( against 30Lacs )

5 years ago

on Saturday, October 31st 2020, 6:30:00 pm
3.73%
Financial Progress

3rd Expenditure
of ₹ 91910 (0.92 Lacs ) done.
Cummulative ₹ 1.12Lacs ( against 30Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
8.30%
Financial Progress

4th Expenditure
of ₹ 137000 (1.37 Lacs ) done.
Cummulative ₹ 2.49Lacs ( against 30Lacs )

2 years ago

on Thursday, May 25th 2023, 6:30:00 pm
23.27%
Financial Progress

5th Expenditure
of ₹ 449300 (4.49 Lacs ) done.
Cummulative ₹ 6.98Lacs ( against 30Lacs )

2 years ago

on Thursday, June 29th 2023, 6:30:00 pm
44.37%
Financial Progress

6th Expenditure
of ₹ 633000 (6.33 Lacs ) done.
Cummulative ₹ 13.31Lacs ( against 30Lacs )

2 years ago

on Tuesday, January 30th 2024, 6:30:00 pm
29.40%
Financial Progress

7th Expenditure
of ₹ -449300 (-4.49 Lacs ) done.
Cummulative ₹ 8.82Lacs ( against 30Lacs )

a year ago

on Sunday, July 14th 2024, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Friday, August 2nd 2024, 6:30:00 pm
35%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Wednesday, September 11th 2024, 6:30:00 pm
29.40%
Financial Progress

8th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 8.82Lacs ( against 30Lacs )

a year ago

on Sunday, September 29th 2024, 6:30:00 pm
32.69%
Financial Progress

9th Expenditure
of ₹ 98704 (0.99 Lacs ) done.
Cummulative ₹ 9.81Lacs ( against 30Lacs )

9 months ago

on Friday, November 29th 2024, 6:30:00 pm
70.56%
Financial Progress

10th Expenditure
of ₹ 1136152 (11.36 Lacs ) done.
Cummulative ₹ 21.17Lacs ( against 30Lacs )

3 months ago

on Tuesday, May 13th 2025, 6:30:00 pm
101.16%
Financial Progress

11th Expenditure
of ₹ 917949 (9.18 Lacs ) done.
Cummulative ₹ 30.35Lacs ( against 30Lacs )