on Sunday, February 2nd 2020, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद टिहरी गढ़वाल के विधान सभा क्षेत्र देवप्रयाग के अन्तर्गत भ्वींट गधेरे से तुणगी भटकोट मार्ग का नव निर्माण कार्य।
on Tuesday, May 12th 2020, 6:30:00 pm
Technical Sanction
of ₹ 237.07 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. SE No. 1438/898C-8/2020
on Saturday, October 31st 2020, 6:30:00 pm
0.44%
Financial Progress
1st Expenditure
of ₹ 104486 (1.04 Lacs ) done.
Cummulative ₹ 1.04Lacs ( against 237.07Lacs )
on Sunday, February 28th 2021, 6:30:00 pm
13.54%
Financial Progress
2nd Expenditure
of ₹ 3104640 (31.05 Lacs ) done.
Cummulative ₹ 32.09Lacs ( against 237.07Lacs )
on Wednesday, March 30th 2022, 6:30:00 pm
46.36%
Financial Progress
3rd Expenditure
of ₹ 7781000 (77.81 Lacs ) done.
Cummulative ₹ 109.90Lacs ( against 237.07Lacs )
on Monday, January 30th 2023, 6:30:00 pm
52.88%
Financial Progress
4th Expenditure
of ₹ 1545000 (15.45 Lacs ) done.
Cummulative ₹ 125.35Lacs ( against 237.07Lacs )
on Monday, February 27th 2023, 6:30:00 pm
57.09%
Financial Progress
5th Expenditure
of ₹ 1000000 (10.00 Lacs ) done.
Cummulative ₹ 135.35Lacs ( against 237.07Lacs )
on Wednesday, March 29th 2023, 6:30:00 pm
63.38%
Financial Progress
7th Expenditure
of ₹ 1490000 (14.90 Lacs ) done.
Cummulative ₹ 150.25Lacs ( against 237.07Lacs )
on Wednesday, March 29th 2023, 6:30:00 pm
57.09%
Financial Progress
6th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 135.35Lacs ( against 237.07Lacs )
on Monday, May 29th 2023, 6:30:00 pm
64.59%
Financial Progress
8th Expenditure
of ₹ 286729 (2.87 Lacs ) done.
Cummulative ₹ 153.12Lacs ( against 237.07Lacs )
on Thursday, June 29th 2023, 6:30:00 pm
65.72%
Financial Progress
9th Expenditure
of ₹ 267775 (2.68 Lacs ) done.
Cummulative ₹ 155.80Lacs ( against 237.07Lacs )
on Saturday, July 29th 2023, 6:30:00 pm
69.40%
Financial Progress
10th Expenditure
of ₹ 873496 (8.73 Lacs ) done.
Cummulative ₹ 164.53Lacs ( against 237.07Lacs )
on Wednesday, October 4th 2023, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 1st time
on Monday, October 30th 2023, 6:30:00 pm
76.57%
Financial Progress
11th Expenditure
of ₹ 1699061 (16.99 Lacs ) done.
Cummulative ₹ 181.52Lacs ( against 237.07Lacs )
on Wednesday, November 29th 2023, 6:30:00 pm
76.67%
Financial Progress
12th Expenditure
of ₹ 23000 (0.23 Lacs ) done.
Cummulative ₹ 181.75Lacs ( against 237.07Lacs )
on Wednesday, October 23rd 2024, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 2nd time
on Friday, November 29th 2024, 6:30:00 pm
76.67%
Financial Progress
13th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 181.75Lacs ( against 237.07Lacs )
on Tuesday, December 3rd 2024, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 3rd time
on Saturday, December 7th 2024, 9:46:15 am
PWD UttarakahndPhoto (ID 60624) from Site Received
Uploader : Yatendra Singh Rawat, Assistant Engineer Civil ,TD Kirtinagar
Landmark : 0.025
Remark : Retaining wall
on Saturday, December 7th 2024, 9:49:22 am
PWD UttarakahndPhoto (ID 60625) from Site Received
Uploader : Yatendra Singh Rawat, Assistant Engineer Civil ,TD Kirtinagar
Landmark : 0.350
Remark : Construction of parapets
on Saturday, December 7th 2024, 9:52:57 am
PWD UttarakahndPhoto (ID 60626) from Site Received
Uploader : Yatendra Singh Rawat, Assistant Engineer Civil ,TD Kirtinagar
Landmark : 0.650
Remark : Construction of scupper
on Saturday, December 7th 2024, 10:03:39 am
PWD UttarakahndPhoto (ID 60628) from Site Received
Uploader : Yatendra Singh Rawat, Assistant Engineer Civil ,TD Kirtinagar
Landmark : 1.525
Remark : Passing place
on Wednesday, December 11th 2024, 3:15:34 am
PWD UttarakahndPhoto (ID 60828) from Site Received
Uploader : Manoj Singh Panwar, Assistant Engineer Civil ,8th Circle Tehri
Landmark : Km 3
Remark : SE sir visit
on Wednesday, December 11th 2024, 3:18:01 am
PWD UttarakahndPhoto (ID 60829) from Site Received
Uploader : Dinesh Singh Bisht, JE Civil (Samvida) ,TD Kirtinagar
Landmark : Km 2
Remark : Km 2
on Monday, December 30th 2024, 6:30:00 pm
85.14%
Financial Progress
14th Expenditure
of ₹ 2008075 (20.08 Lacs ) done.
Cummulative ₹ 201.83Lacs ( against 237.07Lacs )
on Sunday, January 26th 2025, 6:30:00 pm
85.14%
Financial Progress
15th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 201.83Lacs ( against 237.07Lacs )
on Monday, February 10th 2025, 6:30:00 pm
87.72%
Financial Progress
16th Expenditure
of ₹ 612661 (6.13 Lacs ) done.
Cummulative ₹ 207.96Lacs ( against 237.07Lacs )
on Monday, February 10th 2025, 6:30:00 pm
85.14%
Financial Progress
17th Expenditure
of ₹ -612661 (-6.13 Lacs ) done.
Cummulative ₹ 201.83Lacs ( against 237.07Lacs )
on Wednesday, February 12th 2025, 6:30:00 pm
87.79%
Financial Progress
18th Expenditure
of ₹ 629181 (6.29 Lacs ) done.
Cummulative ₹ 208.12Lacs ( against 237.07Lacs )
on Tuesday, March 4th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 4th time
on Wednesday, March 12th 2025, 6:30:00 pm
88.34%
Financial Progress
19th Expenditure
of ₹ 129422 (1.29 Lacs ) done.
Cummulative ₹ 209.42Lacs ( against 237.07Lacs )
on Friday, March 14th 2025, 6:30:00 pm
89.69%
Financial Progress
20th Expenditure
of ₹ 321156 (3.21 Lacs ) done.
Cummulative ₹ 212.63Lacs ( against 237.07Lacs )
on Friday, March 14th 2025, 6:30:00 pm
98.77%
Financial Progress
23rd Expenditure
of ₹ 248508 (2.49 Lacs ) done.
Cummulative ₹ 234.15Lacs ( against 237.07Lacs )
on Friday, March 14th 2025, 6:30:00 pm
97.72%
Financial Progress
22nd Expenditure
of ₹ 500568 (5.01 Lacs ) done.
Cummulative ₹ 231.66Lacs ( against 237.07Lacs )
on Friday, March 14th 2025, 6:30:00 pm
95.61%
Financial Progress
21st Expenditure
of ₹ 1402671 (14.03 Lacs ) done.
Cummulative ₹ 226.66Lacs ( against 237.07Lacs )
on Sunday, March 23rd 2025, 6:30:00 pm
97.17%
Financial Progress
24th Expenditure
of ₹ -377984 (-3.78 Lacs ) done.
Cummulative ₹ 230.37Lacs ( against 237.07Lacs )