on Thursday, February 20th 2014, 6:30:00 pm
Work Sanctioned
जनपद टिहरी गढवाल के विधान सभा क्षेत्र धनौल्टी में मसौन काण्डी द्वारगढ हल्का वाहन मार्ग का मोटर मार्ग में परिवर्तन एंव डामरीकरण का कार्य।
on Friday, February 28th 2014, 6:30:00 pm
0.43%
Financial Progress
1st Expenditure
of ₹ 9947 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 23.19Lacs )
on Wednesday, April 30th 2014, 6:30:00 pm
1.76%
Financial Progress
2nd Expenditure
of ₹ 30915 (0.31 Lacs ) done.
Cummulative ₹ 0.41Lacs ( against 23.19Lacs )
on Saturday, May 31st 2014, 6:30:00 pm
21.17%
Financial Progress
3rd Expenditure
of ₹ 450000 (4.50 Lacs ) done.
Cummulative ₹ 4.91Lacs ( against 23.19Lacs )
on Sunday, August 31st 2014, 6:30:00 pm
23.46%
Financial Progress
4th Expenditure
of ₹ 53187 (0.53 Lacs ) done.
Cummulative ₹ 5.44Lacs ( against 23.19Lacs )
on Friday, October 31st 2014, 6:30:00 pm
24.09%
Financial Progress
5th Expenditure
of ₹ 14532 (0.15 Lacs ) done.
Cummulative ₹ 5.59Lacs ( against 23.19Lacs )
on Saturday, January 31st 2015, 6:30:00 pm
34.29%
Financial Progress
6th Expenditure
of ₹ 236549 (2.37 Lacs ) done.
Cummulative ₹ 7.95Lacs ( against 23.19Lacs )
on Saturday, February 28th 2015, 6:30:00 pm
76.61%
Financial Progress
7th Expenditure
of ₹ 981524 (9.82 Lacs ) done.
Cummulative ₹ 17.77Lacs ( against 23.19Lacs )
on Tuesday, March 31st 2015, 6:30:00 pm
78.34%
Financial Progress
8th Expenditure
of ₹ 40000 (0.40 Lacs ) done.
Cummulative ₹ 18.17Lacs ( against 23.19Lacs )
on Sunday, May 31st 2015, 6:30:00 pm
77.32%
Financial Progress
9th Expenditure
of ₹ -23542 (-0.24 Lacs ) done.
Cummulative ₹ 17.93Lacs ( against 23.19Lacs )
on Sunday, October 16th 2016, 6:30:00 pm
Technical Sanction
of ₹ 23.9 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE-1634/1C
on Tuesday, February 28th 2017, 6:30:00 pm
79.32%
Financial Progress
10th Expenditure
of ₹ 46326 (0.46 Lacs ) done.
Cummulative ₹ 18.39Lacs ( against 23.19Lacs )
on Thursday, August 31st 2017, 6:30:00 pm
79.98%
Financial Progress
11th Expenditure
of ₹ 15355 (0.15 Lacs ) done.
Cummulative ₹ 18.55Lacs ( against 23.19Lacs )
on Wednesday, January 31st 2018, 6:30:00 pm
80.22%
Financial Progress
12th Expenditure
of ₹ 5500 (0.06 Lacs ) done.
Cummulative ₹ 18.60Lacs ( against 23.19Lacs )
on Sunday, February 5th 2023, 6:30:00 pm
85%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, August 11th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Friday, March 14th 2025, 6:30:00 pm
84.48%
Financial Progress
13th Expenditure
of ₹ 98800 (0.99 Lacs ) done.
Cummulative ₹ 19.59Lacs ( against 23.19Lacs )
on Sunday, March 23rd 2025, 6:30:00 pm
95.45%
Financial Progress
14th Expenditure
of ₹ 254362 (2.54 Lacs ) done.
Cummulative ₹ 22.13Lacs ( against 23.19Lacs )
on Wednesday, April 9th 2025, 6:30:00 pm
96%
Physical Progress
Physical Progress Reported at 3rd time