on Sunday, July 10th 2005, 6:30:00 pm
Work Sanctioned
जनपद अल्मोड़ा में कालिका- दलमोटी मोटर मार्ग का निर्माण ।
on Tuesday, March 11th 2008, 6:30:00 pm
Technical Sanction
of ₹ 68.54 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2753/505yata/07
on Saturday, February 28th 2009, 6:30:00 pm
28.23%
Financial Progress
1st Expenditure
of ₹ 3658000 (36.58 Lacs ) done.
Cummulative ₹ 36.58Lacs ( against 129.6Lacs )
on Tuesday, June 30th 2009, 6:30:00 pm
29.95%
Financial Progress
2nd Expenditure
of ₹ 224000 (2.24 Lacs ) done.
Cummulative ₹ 38.82Lacs ( against 129.6Lacs )
on Wednesday, September 30th 2009, 6:30:00 pm
30.03%
Financial Progress
3rd Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 38.92Lacs ( against 129.6Lacs )
on Sunday, January 31st 2010, 6:30:00 pm
30.05%
Financial Progress
4th Expenditure
of ₹ 2000 (0.02 Lacs ) done.
Cummulative ₹ 38.94Lacs ( against 129.6Lacs )
on Sunday, February 28th 2010, 6:30:00 pm
30.08%
Financial Progress
5th Expenditure
of ₹ 4000 (0.04 Lacs ) done.
Cummulative ₹ 38.98Lacs ( against 129.6Lacs )
on Friday, April 30th 2010, 6:30:00 pm
30.93%
Financial Progress
6th Expenditure
of ₹ 110000 (1.10 Lacs ) done.
Cummulative ₹ 40.08Lacs ( against 129.6Lacs )
on Monday, May 31st 2010, 6:30:00 pm
31.18%
Financial Progress
7th Expenditure
of ₹ 33000 (0.33 Lacs ) done.
Cummulative ₹ 40.41Lacs ( against 129.6Lacs )
on Wednesday, June 30th 2010, 6:30:00 pm
33.10%
Financial Progress
8th Expenditure
of ₹ 249000 (2.49 Lacs ) done.
Cummulative ₹ 42.90Lacs ( against 129.6Lacs )
on Saturday, July 31st 2010, 6:30:00 pm
35.89%
Financial Progress
9th Expenditure
of ₹ 361000 (3.61 Lacs ) done.
Cummulative ₹ 46.51Lacs ( against 129.6Lacs )
on Tuesday, August 31st 2010, 6:30:00 pm
35.90%
Financial Progress
10th Expenditure
of ₹ 1000 (0.01 Lacs ) done.
Cummulative ₹ 46.52Lacs ( against 129.6Lacs )
on Thursday, September 30th 2010, 6:30:00 pm
36.00%
Financial Progress
11th Expenditure
of ₹ 13000 (0.13 Lacs ) done.
Cummulative ₹ 46.65Lacs ( against 129.6Lacs )
on Sunday, October 31st 2010, 6:30:00 pm
37.04%
Financial Progress
12th Expenditure
of ₹ 135000 (1.35 Lacs ) done.
Cummulative ₹ 48.00Lacs ( against 129.6Lacs )
on Tuesday, November 30th 2010, 6:30:00 pm
38.14%
Financial Progress
13th Expenditure
of ₹ 142562 (1.43 Lacs ) done.
Cummulative ₹ 49.43Lacs ( against 129.6Lacs )
on Monday, January 31st 2011, 6:30:00 pm
38.16%
Financial Progress
14th Expenditure
of ₹ 2490 (0.02 Lacs ) done.
Cummulative ₹ 49.45Lacs ( against 129.6Lacs )
on Monday, February 28th 2011, 6:30:00 pm
47.53%
Financial Progress
15th Expenditure
of ₹ 1215421 (12.15 Lacs ) done.
Cummulative ₹ 61.60Lacs ( against 129.6Lacs )
on Thursday, June 30th 2011, 6:30:00 pm
47.88%
Financial Progress
16th Expenditure
of ₹ 44649 (0.45 Lacs ) done.
Cummulative ₹ 62.05Lacs ( against 129.6Lacs )
on Wednesday, November 30th 2011, 6:30:00 pm
48.59%
Financial Progress
17th Expenditure
of ₹ 91636 (0.92 Lacs ) done.
Cummulative ₹ 62.97Lacs ( against 129.6Lacs )
on Monday, April 30th 2012, 6:30:00 pm
49.29%
Financial Progress
18th Expenditure
of ₹ 90737 (0.91 Lacs ) done.
Cummulative ₹ 63.87Lacs ( against 129.6Lacs )
on Sunday, September 30th 2012, 6:30:00 pm
53.18%
Financial Progress
19th Expenditure
of ₹ 504904 (5.05 Lacs ) done.
Cummulative ₹ 68.92Lacs ( against 129.6Lacs )
on Thursday, January 31st 2013, 6:30:00 pm
58.26%
Financial Progress
20th Expenditure
of ₹ 658653 (6.59 Lacs ) done.
Cummulative ₹ 75.51Lacs ( against 129.6Lacs )
on Thursday, February 28th 2013, 6:30:00 pm
59.75%
Financial Progress
21st Expenditure
of ₹ 192978 (1.93 Lacs ) done.
Cummulative ₹ 77.44Lacs ( against 129.6Lacs )
on Friday, February 28th 2014, 6:30:00 pm
61.97%
Financial Progress
22nd Expenditure
of ₹ 286804 (2.87 Lacs ) done.
Cummulative ₹ 80.31Lacs ( against 129.6Lacs )
on Thursday, July 31st 2014, 6:30:00 pm
62.27%
Financial Progress
23rd Expenditure
of ₹ 39630 (0.40 Lacs ) done.
Cummulative ₹ 80.70Lacs ( against 129.6Lacs )
on Sunday, October 12th 2014, 6:30:00 pm
Technical Sanction
of ₹ 40.34 Lacs
2nd Technical Sanction of Work after survey,detailed design and analysis by Latter No. 4786/941C-01/14
on Saturday, February 28th 2015, 6:30:00 pm
65.62%
Financial Progress
24th Expenditure
of ₹ 433776 (4.34 Lacs ) done.
Cummulative ₹ 85.04Lacs ( against 129.6Lacs )
on Sunday, May 31st 2015, 6:30:00 pm
68.97%
Financial Progress
25th Expenditure
of ₹ 434032 (4.34 Lacs ) done.
Cummulative ₹ 89.38Lacs ( against 129.6Lacs )
on Monday, August 31st 2015, 6:30:00 pm
69.03%
Financial Progress
26th Expenditure
of ₹ 7600 (0.08 Lacs ) done.
Cummulative ₹ 89.46Lacs ( against 129.6Lacs )
on Saturday, October 31st 2015, 6:30:00 pm
71.04%
Financial Progress
27th Expenditure
of ₹ 261078 (2.61 Lacs ) done.
Cummulative ₹ 92.07Lacs ( against 129.6Lacs )
on Thursday, March 31st 2016, 6:30:00 pm
73.14%
Financial Progress
28th Expenditure
of ₹ 271409 (2.71 Lacs ) done.
Cummulative ₹ 94.78Lacs ( against 129.6Lacs )
on Saturday, April 30th 2016, 6:30:00 pm
74.29%
Financial Progress
29th Expenditure
of ₹ 150000 (1.50 Lacs ) done.
Cummulative ₹ 96.28Lacs ( against 129.6Lacs )
on Wednesday, August 31st 2016, 6:30:00 pm
74.45%
Financial Progress
30th Expenditure
of ₹ 19845 (0.20 Lacs ) done.
Cummulative ₹ 96.48Lacs ( against 129.6Lacs )
on Saturday, December 31st 2016, 6:30:00 pm
74.72%
Financial Progress
31st Expenditure
of ₹ 34941 (0.35 Lacs ) done.
Cummulative ₹ 96.83Lacs ( against 129.6Lacs )
on Tuesday, January 31st 2017, 6:30:00 pm
74.73%
Financial Progress
32nd Expenditure
of ₹ 2500 (0.03 Lacs ) done.
Cummulative ₹ 96.86Lacs ( against 129.6Lacs )
on Monday, July 31st 2017, 6:30:00 pm
74.90%
Financial Progress
33rd Expenditure
of ₹ 21756 (0.22 Lacs ) done.
Cummulative ₹ 97.07Lacs ( against 129.6Lacs )
on Wednesday, January 31st 2018, 6:30:00 pm
80.42%
Financial Progress
34th Expenditure
of ₹ 714384 (7.14 Lacs ) done.
Cummulative ₹ 104.22Lacs ( against 129.6Lacs )
on Sunday, January 2nd 2022, 7:36:40 am
PWD UttarakahndPhoto (ID 3983) from Site Received
Uploader : Liladhar Mathela, Executive Engineer Civil ,CD Ranikhet
Landmark : 4.150
Remark : Thickness of p c checked found 2 cm
on Sunday, January 2nd 2022, 7:55:22 am
PWD UttarakahndPhoto (ID 3984) from Site Received
Uploader : Liladhar Mathela, Executive Engineer Civil ,CD Ranikhet
Landmark : 4.150
Remark : Inspection ce alm
on Wednesday, April 17th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time