@
Refresh data
Refresh data

5 years ago

on Tuesday, May 12th 2020, 6:30:00 pm
Work Sanctioned
जनपद अल्मोड़ा के विधान सभा क्षेत्र द्वाराहाट के अन्तर्गत सिमलगाॅव-सुरईखेत तक मोटर मार्ग का निर्माण कार्य की पुनरीक्षित स्वीकृति

4 years ago

on Thursday, December 24th 2020, 6:42:10 am

Technical Sanction
of ₹ 404.28 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 6792/101 yata-a/2020

4 years ago

on Sunday, February 28th 2021, 6:30:00 pm
0.02%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 404.28Lacs )

4 years ago

on Wednesday, September 29th 2021, 6:30:00 pm
0.17%
Financial Progress

2nd Expenditure
of ₹ 57456 (0.57 Lacs ) done.
Cummulative ₹ 0.67Lacs ( against 404.28Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
8.56%
Financial Progress

3rd Expenditure
of ₹ 3394341 (33.94 Lacs ) done.
Cummulative ₹ 34.62Lacs ( against 404.28Lacs )

3 years ago

on Friday, June 3rd 2022, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Tuesday, August 30th 2022, 6:30:00 pm
8.88%
Financial Progress

4th Expenditure
of ₹ 126702 (1.27 Lacs ) done.
Cummulative ₹ 35.88Lacs ( against 404.28Lacs )

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
9.05%
Financial Progress

5th Expenditure
of ₹ 69452 (0.69 Lacs ) done.
Cummulative ₹ 36.58Lacs ( against 404.28Lacs )

3 years ago

on Sunday, October 30th 2022, 6:30:00 pm
13.01%
Financial Progress

6th Expenditure
of ₹ 1600000 (16.00 Lacs ) done.
Cummulative ₹ 52.58Lacs ( against 404.28Lacs )

2 years ago

on Monday, January 30th 2023, 6:30:00 pm
20.02%
Financial Progress

7th Expenditure
of ₹ 2835213 (28.35 Lacs ) done.
Cummulative ₹ 80.93Lacs ( against 404.28Lacs )

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
25.88%
Financial Progress

8th Expenditure
of ₹ 2369000 (23.69 Lacs ) done.
Cummulative ₹ 104.62Lacs ( against 404.28Lacs )

2 years ago

on Saturday, September 16th 2023, 12:52:05 am
<span class="4">Picture Id:24708</span>
PWD Uttarakahnd
Photo (ID 24708) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Km 7 hm 2-4
Remark : Scupper construction

2 years ago

on Wednesday, October 4th 2023, 6:30:00 pm
75%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Tuesday, October 10th 2023, 12:56:19 am
<span class="4">Picture Id:24718</span>
PWD Uttarakahnd
Photo (ID 24718) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Km 6 ch 5.75 to 5.80
Remark : HP bend cutting

2 years ago

on Tuesday, October 10th 2023, 1:01:31 am
<span class="4">Picture Id:24721</span>
PWD Uttarakahnd
Photo (ID 24721) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Km 6 ch 5.55to 5.60
Remark : Scupper construction

a year ago

on Wednesday, November 29th 2023, 6:30:00 pm
34.07%
Financial Progress

9th Expenditure
of ₹ 3309754 (33.10 Lacs ) done.
Cummulative ₹ 137.72Lacs ( against 404.28Lacs )

a year ago

on Monday, January 1st 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Friday, January 19th 2024, 6:30:00 pm
34.14%
Financial Progress

10th Expenditure
of ₹ 28605 (0.29 Lacs ) done.
Cummulative ₹ 138.01Lacs ( against 404.28Lacs )

a year ago

on Sunday, February 11th 2024, 6:30:00 pm
34.75%
Financial Progress

11th Expenditure
of ₹ 249282 (2.49 Lacs ) done.
Cummulative ₹ 140.50Lacs ( against 404.28Lacs )

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
34.68%
Financial Progress

12th Expenditure
of ₹ -28605 (-0.29 Lacs ) done.
Cummulative ₹ 140.21Lacs ( against 404.28Lacs )

a year ago

on Sunday, May 12th 2024, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 4th time

7 months ago

on Sunday, September 29th 2024, 6:30:00 pm
34.73%
Financial Progress

13th Expenditure
of ₹ 19550 (0.20 Lacs ) done.
Cummulative ₹ 140.41Lacs ( against 404.28Lacs )

5 months ago

on Tuesday, December 3rd 2024, 6:30:00 pm
92%

Physical Progress
Physical Progress Reported at 5th time

5 months ago

on Friday, December 20th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 6th time

2 months ago

on Sunday, March 16th 2025, 6:30:00 pm
34.82%
Financial Progress

15th Expenditure
of ₹ 21858 (0.22 Lacs ) done.
Cummulative ₹ 140.76Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 16th 2025, 6:30:00 pm
47.34%
Financial Progress

19th Expenditure
of ₹ 4810814 (48.11 Lacs ) done.
Cummulative ₹ 191.37Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 16th 2025, 6:30:00 pm
35.44%
Financial Progress

18th Expenditure
of ₹ 18054 (0.18 Lacs ) done.
Cummulative ₹ 143.26Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 16th 2025, 6:30:00 pm
35.39%
Financial Progress

17th Expenditure
of ₹ 24940 (0.25 Lacs ) done.
Cummulative ₹ 143.08Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 16th 2025, 6:30:00 pm
35.33%
Financial Progress

16th Expenditure
of ₹ 207090 (2.07 Lacs ) done.
Cummulative ₹ 142.83Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 16th 2025, 6:30:00 pm
34.76%
Financial Progress

14th Expenditure
of ₹ 13500 (0.14 Lacs ) done.
Cummulative ₹ 140.54Lacs ( against 404.28Lacs )

2 months ago

on Monday, March 17th 2025, 6:30:00 pm
47.53%
Financial Progress

20th Expenditure
of ₹ 78000 (0.78 Lacs ) done.
Cummulative ₹ 192.15Lacs ( against 404.28Lacs )

2 months ago

on Thursday, March 20th 2025, 6:30:00 pm
47.99%
Financial Progress

21st Expenditure
of ₹ 187500 (1.88 Lacs ) done.
Cummulative ₹ 194.03Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
49.73%
Financial Progress

27th Expenditure
of ₹ 242880 (2.43 Lacs ) done.
Cummulative ₹ 201.06Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
48.02%
Financial Progress

22nd Expenditure
of ₹ 11750 (0.12 Lacs ) done.
Cummulative ₹ 194.14Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
48.22%
Financial Progress

23rd Expenditure
of ₹ 79000 (0.79 Lacs ) done.
Cummulative ₹ 194.93Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
49.13%
Financial Progress

26th Expenditure
of ₹ 167500 (1.68 Lacs ) done.
Cummulative ₹ 198.63Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
49.78%
Financial Progress

28th Expenditure
of ₹ 19840 (0.20 Lacs ) done.
Cummulative ₹ 201.26Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
49.91%
Financial Progress

29th Expenditure
of ₹ 52000 (0.52 Lacs ) done.
Cummulative ₹ 201.78Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
48.72%
Financial Progress

25th Expenditure
of ₹ 40000 (0.40 Lacs ) done.
Cummulative ₹ 196.96Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
50.01%
Financial Progress

30th Expenditure
of ₹ 41300 (0.41 Lacs ) done.
Cummulative ₹ 202.19Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
50.05%
Financial Progress

31st Expenditure
of ₹ 15126 (0.15 Lacs ) done.
Cummulative ₹ 202.34Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
50.10%
Financial Progress

32nd Expenditure
of ₹ 19520 (0.20 Lacs ) done.
Cummulative ₹ 202.54Lacs ( against 404.28Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
48.62%
Financial Progress

24th Expenditure
of ₹ 162500 (1.63 Lacs ) done.
Cummulative ₹ 196.56Lacs ( against 404.28Lacs )

2 months ago

on Monday, March 24th 2025, 6:30:00 pm
50.34%
Financial Progress

34th Expenditure
of ₹ 19520 (0.20 Lacs ) done.
Cummulative ₹ 203.50Lacs ( against 404.28Lacs )

2 months ago

on Monday, March 24th 2025, 6:30:00 pm
50.29%
Financial Progress

33rd Expenditure
of ₹ 76464 (0.76 Lacs ) done.
Cummulative ₹ 203.30Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
54.29%
Financial Progress

60th Expenditure
of ₹ 11250 (0.11 Lacs ) done.
Cummulative ₹ 219.50Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
50.36%
Financial Progress

35th Expenditure
of ₹ 8000 (0.08 Lacs ) done.
Cummulative ₹ 203.58Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
50.72%
Financial Progress

36th Expenditure
of ₹ 147500 (1.48 Lacs ) done.
Cummulative ₹ 205.05Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
50.76%
Financial Progress

37th Expenditure
of ₹ 16250 (0.16 Lacs ) done.
Cummulative ₹ 205.22Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
50.81%
Financial Progress

38th Expenditure
of ₹ 20500 (0.20 Lacs ) done.
Cummulative ₹ 205.42Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
51.07%
Financial Progress

39th Expenditure
of ₹ 102500 (1.02 Lacs ) done.
Cummulative ₹ 206.45Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
54.56%
Financial Progress

61st Expenditure
of ₹ 108750 (1.09 Lacs ) done.
Cummulative ₹ 220.59Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
51.37%
Financial Progress

41st Expenditure
of ₹ 26750 (0.27 Lacs ) done.
Cummulative ₹ 207.67Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
54.27%
Financial Progress

59th Expenditure
of ₹ 55000 (0.55 Lacs ) done.
Cummulative ₹ 219.39Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
53.25%
Financial Progress

52nd Expenditure
of ₹ 150000 (1.50 Lacs ) done.
Cummulative ₹ 215.28Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
51.45%
Financial Progress

42nd Expenditure
of ₹ 33000 (0.33 Lacs ) done.
Cummulative ₹ 208.00Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
51.67%
Financial Progress

43rd Expenditure
of ₹ 88750 (0.89 Lacs ) done.
Cummulative ₹ 208.89Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
51.97%
Financial Progress

44th Expenditure
of ₹ 120000 (1.20 Lacs ) done.
Cummulative ₹ 210.09Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
51.99%
Financial Progress

45th Expenditure
of ₹ 8750 (0.09 Lacs ) done.
Cummulative ₹ 210.18Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
52.02%
Financial Progress

46th Expenditure
of ₹ 11000 (0.11 Lacs ) done.
Cummulative ₹ 210.29Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
52.06%
Financial Progress

47th Expenditure
of ₹ 18500 (0.18 Lacs ) done.
Cummulative ₹ 210.47Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
52.12%
Financial Progress

48th Expenditure
of ₹ 23000 (0.23 Lacs ) done.
Cummulative ₹ 210.70Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
52.14%
Financial Progress

49th Expenditure
of ₹ 10620 (0.11 Lacs ) done.
Cummulative ₹ 210.81Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
51.30%
Financial Progress

40th Expenditure
of ₹ 96000 (0.96 Lacs ) done.
Cummulative ₹ 207.41Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
52.24%
Financial Progress

50th Expenditure
of ₹ 39905 (0.40 Lacs ) done.
Cummulative ₹ 211.21Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
52.88%
Financial Progress

51st Expenditure
of ₹ 257500 (2.58 Lacs ) done.
Cummulative ₹ 213.78Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
54.13%
Financial Progress

58th Expenditure
of ₹ 26000 (0.26 Lacs ) done.
Cummulative ₹ 218.84Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
53.60%
Financial Progress

53rd Expenditure
of ₹ 140150 (1.40 Lacs ) done.
Cummulative ₹ 216.69Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
53.68%
Financial Progress

54th Expenditure
of ₹ 35000 (0.35 Lacs ) done.
Cummulative ₹ 217.04Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
53.82%
Financial Progress

55th Expenditure
of ₹ 54000 (0.54 Lacs ) done.
Cummulative ₹ 217.58Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
53.88%
Financial Progress

56th Expenditure
of ₹ 23750 (0.24 Lacs ) done.
Cummulative ₹ 217.81Lacs ( against 404.28Lacs )

a month ago

on Thursday, March 27th 2025, 6:30:00 pm
54.07%
Financial Progress

57th Expenditure
of ₹ 76500 (0.77 Lacs ) done.
Cummulative ₹ 218.58Lacs ( against 404.28Lacs )

a month ago

on Friday, March 28th 2025, 6:30:00 pm
55.30%
Financial Progress

66th Expenditure
of ₹ 22000 (0.22 Lacs ) done.
Cummulative ₹ 223.58Lacs ( against 404.28Lacs )

a month ago

on Friday, March 28th 2025, 6:30:00 pm
55.25%
Financial Progress

65th Expenditure
of ₹ 142500 (1.43 Lacs ) done.
Cummulative ₹ 223.36Lacs ( against 404.28Lacs )

a month ago

on Friday, March 28th 2025, 6:30:00 pm
54.90%
Financial Progress

64th Expenditure
of ₹ 62500 (0.63 Lacs ) done.
Cummulative ₹ 221.93Lacs ( against 404.28Lacs )

a month ago

on Friday, March 28th 2025, 6:30:00 pm
54.74%
Financial Progress

63rd Expenditure
of ₹ 41200 (0.41 Lacs ) done.
Cummulative ₹ 221.31Lacs ( against 404.28Lacs )

a month ago

on Friday, March 28th 2025, 6:30:00 pm
54.64%
Financial Progress

62nd Expenditure
of ₹ 30800 (0.31 Lacs ) done.
Cummulative ₹ 220.90Lacs ( against 404.28Lacs )

a month ago

on Sunday, March 30th 2025, 6:30:00 pm
61.66%
Financial Progress

67th Expenditure
of ₹ 2572000 (25.72 Lacs ) done.
Cummulative ₹ 249.30Lacs ( against 404.28Lacs )

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable
refresh data by PWD Uttarakhand Engineeres | View code by HandsOnDataViz with Leaflet | © OpenStreetMap contributors