on Monday, September 27th 2021, 6:30:00 pm
Work Sanctioned
केन्द्रीय सड़क अवसंरचना के निधि के अन्तर्गत सड़क सुरक्षा के अन्तर्गत जालीखान-उत्तमछानी-नौबाड़ा मोटर मार्ग में पैरापिट, डेलीनेटर व साईन बोर्ड का कार्य। श्री दान सिंह सहायक अभियन्ता/श्री अशोक कुमार, कनिष्ठ अभियन्ता (संविदा
on Monday, November 22nd 2021, 7:55:58 am
Technical Sanction
of ₹ 25.98 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2925/1C
on Sunday, January 30th 2022, 6:30:00 pm
35.16%
Financial Progress
1st Expenditure
of ₹ 913446 (9.13 Lacs ) done.
Cummulative ₹ 9.13Lacs ( against 25.98Lacs )
on Monday, March 28th 2022, 6:52:26 am
PWD UttarakahndPhoto (ID 5056) from Site Received
Uploader : Shweta Kardam, Junior Engineer Civil ,PD Nainital
Landmark : 3.250
Remark : Road safety work( CRIf)
on Monday, March 28th 2022, 7:12:19 am
PWD UttarakahndPhoto (ID 5058) from Site Received
Uploader : Shweta Kardam, Junior Engineer Civil ,PD Nainital
Landmark : 0.050km
Remark : Road safety work(CRIF)
on Wednesday, March 30th 2022, 6:30:00 pm
40.03%
Financial Progress
2nd Expenditure
of ₹ 126416 (1.26 Lacs ) done.
Cummulative ₹ 10.40Lacs ( against 25.98Lacs )
on Sunday, May 29th 2022, 6:30:00 pm
70.82%
Financial Progress
3rd Expenditure
of ₹ 800000 (8.00 Lacs ) done.
Cummulative ₹ 18.40Lacs ( against 25.98Lacs )
on Monday, August 1st 2022, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, August 30th 2022, 6:30:00 pm
93.16%
Financial Progress
4th Expenditure
of ₹ 580428 (5.80 Lacs ) done.
Cummulative ₹ 24.20Lacs ( against 25.98Lacs )
on Thursday, September 29th 2022, 6:30:00 pm
95.84%
Financial Progress
5th Expenditure
of ₹ 69706 (0.70 Lacs ) done.
Cummulative ₹ 24.90Lacs ( against 25.98Lacs )