19 years ago

on Tuesday, September 19th 2006, 6:30:00 pm
Work Sanctioned
नार्गाजुन-डहल-जालली मोटर मार्ग का नव निर्माण।

18 years ago

on Wednesday, May 9th 2007, 6:30:00 pm

Technical Sanction
of ₹ 187.53 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 37/YATA

17 years ago

on Saturday, February 28th 2009, 6:30:00 pm
50.49%
Financial Progress

1st Expenditure
of ₹ 11840000 (118.40 Lacs ) done.
Cummulative ₹ 118.40Lacs ( against 234.51Lacs )

16 years ago

on Tuesday, June 30th 2009, 6:30:00 pm
51.02%
Financial Progress

2nd Expenditure
of ₹ 124000 (1.24 Lacs ) done.
Cummulative ₹ 119.64Lacs ( against 234.51Lacs )

16 years ago

on Wednesday, September 30th 2009, 6:30:00 pm
51.03%
Financial Progress

3rd Expenditure
of ₹ 4000 (0.04 Lacs ) done.
Cummulative ₹ 119.68Lacs ( against 234.51Lacs )

16 years ago

on Monday, November 30th 2009, 6:30:00 pm
51.38%
Financial Progress

4th Expenditure
of ₹ 82000 (0.82 Lacs ) done.
Cummulative ₹ 120.50Lacs ( against 234.51Lacs )

16 years ago

on Sunday, January 31st 2010, 6:30:00 pm
54.57%
Financial Progress

5th Expenditure
of ₹ 747000 (7.47 Lacs ) done.
Cummulative ₹ 127.97Lacs ( against 234.51Lacs )

16 years ago

on Sunday, February 28th 2010, 6:30:00 pm
54.61%
Financial Progress

6th Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 128.07Lacs ( against 234.51Lacs )

15 years ago

on Wednesday, March 31st 2010, 6:30:00 pm
56.79%
Financial Progress

7th Expenditure
of ₹ 510000 (5.10 Lacs ) done.
Cummulative ₹ 133.17Lacs ( against 234.51Lacs )

15 years ago

on Friday, April 30th 2010, 6:30:00 pm
57.35%
Financial Progress

8th Expenditure
of ₹ 132000 (1.32 Lacs ) done.
Cummulative ₹ 134.49Lacs ( against 234.51Lacs )

15 years ago

on Monday, May 31st 2010, 6:30:00 pm
57.63%
Financial Progress

9th Expenditure
of ₹ 66000 (0.66 Lacs ) done.
Cummulative ₹ 135.15Lacs ( against 234.51Lacs )

15 years ago

on Wednesday, June 30th 2010, 6:30:00 pm
59.36%
Financial Progress

10th Expenditure
of ₹ 405000 (4.05 Lacs ) done.
Cummulative ₹ 139.20Lacs ( against 234.51Lacs )

15 years ago

on Saturday, July 31st 2010, 6:30:00 pm
61.17%
Financial Progress

11th Expenditure
of ₹ 426000 (4.26 Lacs ) done.
Cummulative ₹ 143.46Lacs ( against 234.51Lacs )

15 years ago

on Tuesday, August 31st 2010, 6:30:00 pm
61.18%
Financial Progress

12th Expenditure
of ₹ 1000 (0.01 Lacs ) done.
Cummulative ₹ 143.47Lacs ( against 234.51Lacs )

15 years ago

on Sunday, October 31st 2010, 6:30:00 pm
61.26%
Financial Progress

13th Expenditure
of ₹ 19000 (0.19 Lacs ) done.
Cummulative ₹ 143.66Lacs ( against 234.51Lacs )

15 years ago

on Tuesday, November 30th 2010, 6:30:00 pm
61.49%
Financial Progress

14th Expenditure
of ₹ 55000 (0.55 Lacs ) done.
Cummulative ₹ 144.21Lacs ( against 234.51Lacs )

15 years ago

on Friday, December 31st 2010, 6:30:00 pm
62.56%
Financial Progress

15th Expenditure
of ₹ 250133 (2.50 Lacs ) done.
Cummulative ₹ 146.71Lacs ( against 234.51Lacs )

15 years ago

on Monday, February 28th 2011, 6:30:00 pm
62.60%
Financial Progress

16th Expenditure
of ₹ 8118 (0.08 Lacs ) done.
Cummulative ₹ 146.79Lacs ( against 234.51Lacs )

14 years ago

on Tuesday, May 31st 2011, 6:30:00 pm
62.65%
Financial Progress

17th Expenditure
of ₹ 13750 (0.14 Lacs ) done.
Cummulative ₹ 146.93Lacs ( against 234.51Lacs )

14 years ago

on Thursday, June 30th 2011, 6:30:00 pm
63.22%
Financial Progress

18th Expenditure
of ₹ 133360 (1.33 Lacs ) done.
Cummulative ₹ 148.26Lacs ( against 234.51Lacs )

14 years ago

on Monday, August 29th 2011, 6:30:00 pm

Technical Sanction
of ₹ 46.98 Lacs

2nd Technical Sanction of Work after survey,detailed design and analysis by Latter No. 9736/505yata-Ku.

14 years ago

on Friday, September 30th 2011, 6:30:00 pm
63.66%
Financial Progress

19th Expenditure
of ₹ 102568 (1.03 Lacs ) done.
Cummulative ₹ 149.29Lacs ( against 234.51Lacs )

14 years ago

on Wednesday, November 30th 2011, 6:30:00 pm
66.10%
Financial Progress

20th Expenditure
of ₹ 572334 (5.72 Lacs ) done.
Cummulative ₹ 155.01Lacs ( against 234.51Lacs )

14 years ago

on Saturday, December 31st 2011, 6:30:00 pm
68.85%
Financial Progress

21st Expenditure
of ₹ 643729 (6.44 Lacs ) done.
Cummulative ₹ 161.45Lacs ( against 234.51Lacs )

14 years ago

on Tuesday, January 31st 2012, 6:30:00 pm
71.27%
Financial Progress

22nd Expenditure
of ₹ 568270 (5.68 Lacs ) done.
Cummulative ₹ 167.13Lacs ( against 234.51Lacs )

14 years ago

on Wednesday, February 29th 2012, 6:30:00 pm
71.78%
Financial Progress

23rd Expenditure
of ₹ 119550 (1.20 Lacs ) done.
Cummulative ₹ 168.33Lacs ( against 234.51Lacs )

13 years ago

on Monday, April 30th 2012, 6:30:00 pm
78.56%
Financial Progress

24th Expenditure
of ₹ 1590999 (15.91 Lacs ) done.
Cummulative ₹ 184.24Lacs ( against 234.51Lacs )

13 years ago

on Saturday, June 30th 2012, 6:30:00 pm
79.46%
Financial Progress

25th Expenditure
of ₹ 209726 (2.10 Lacs ) done.
Cummulative ₹ 186.34Lacs ( against 234.51Lacs )

13 years ago

on Tuesday, July 31st 2012, 6:30:00 pm
79.71%
Financial Progress

26th Expenditure
of ₹ 59868 (0.60 Lacs ) done.
Cummulative ₹ 186.93Lacs ( against 234.51Lacs )

13 years ago

on Friday, August 31st 2012, 6:30:00 pm
79.92%
Financial Progress

27th Expenditure
of ₹ 49229 (0.49 Lacs ) done.
Cummulative ₹ 187.43Lacs ( against 234.51Lacs )

13 years ago

on Sunday, September 30th 2012, 6:30:00 pm
81.14%
Financial Progress

28th Expenditure
of ₹ 286450 (2.86 Lacs ) done.
Cummulative ₹ 190.29Lacs ( against 234.51Lacs )

13 years ago

on Monday, December 31st 2012, 6:30:00 pm
81.32%
Financial Progress

29th Expenditure
of ₹ 42058 (0.42 Lacs ) done.
Cummulative ₹ 190.71Lacs ( against 234.51Lacs )

13 years ago

on Thursday, January 31st 2013, 6:30:00 pm
81.32%
Financial Progress

30th Expenditure
of ₹ 174 (0.00 Lacs ) done.
Cummulative ₹ 190.71Lacs ( against 234.51Lacs )

13 years ago

on Thursday, February 28th 2013, 6:30:00 pm
81.80%
Financial Progress

31st Expenditure
of ₹ 111387 (1.11 Lacs ) done.
Cummulative ₹ 191.83Lacs ( against 234.51Lacs )

12 years ago

on Sunday, June 30th 2013, 6:30:00 pm
82.41%
Financial Progress

32nd Expenditure
of ₹ 142218 (1.42 Lacs ) done.
Cummulative ₹ 193.25Lacs ( against 234.51Lacs )

12 years ago

on Saturday, August 31st 2013, 6:30:00 pm
82.66%
Financial Progress

33rd Expenditure
of ₹ 59406 (0.59 Lacs ) done.
Cummulative ₹ 193.84Lacs ( against 234.51Lacs )

12 years ago

on Thursday, October 31st 2013, 6:30:00 pm
83.12%
Financial Progress

34th Expenditure
of ₹ 107681 (1.08 Lacs ) done.
Cummulative ₹ 194.92Lacs ( against 234.51Lacs )

12 years ago

on Tuesday, December 31st 2013, 6:30:00 pm
83.17%
Financial Progress

35th Expenditure
of ₹ 11439 (0.11 Lacs ) done.
Cummulative ₹ 195.03Lacs ( against 234.51Lacs )

12 years ago

on Friday, January 31st 2014, 6:30:00 pm
84.09%
Financial Progress

36th Expenditure
of ₹ 216158 (2.16 Lacs ) done.
Cummulative ₹ 197.20Lacs ( against 234.51Lacs )

12 years ago

on Friday, February 28th 2014, 6:30:00 pm
86.72%
Financial Progress

37th Expenditure
of ₹ 617665 (6.18 Lacs ) done.
Cummulative ₹ 203.37Lacs ( against 234.51Lacs )

11 years ago

on Friday, October 31st 2014, 6:30:00 pm
87.59%
Financial Progress

38th Expenditure
of ₹ 204020 (2.04 Lacs ) done.
Cummulative ₹ 205.41Lacs ( against 234.51Lacs )

11 years ago

on Sunday, November 30th 2014, 6:30:00 pm
88.85%
Financial Progress

39th Expenditure
of ₹ 293996 (2.94 Lacs ) done.
Cummulative ₹ 208.35Lacs ( against 234.51Lacs )

11 years ago

on Wednesday, December 31st 2014, 6:30:00 pm
88.89%
Financial Progress

40th Expenditure
of ₹ 11008 (0.11 Lacs ) done.
Cummulative ₹ 208.46Lacs ( against 234.51Lacs )

11 years ago

on Saturday, January 31st 2015, 6:30:00 pm
89.45%
Financial Progress

41st Expenditure
of ₹ 129710 (1.30 Lacs ) done.
Cummulative ₹ 209.76Lacs ( against 234.51Lacs )

11 years ago

on Saturday, February 28th 2015, 6:30:00 pm
93.95%
Financial Progress

42nd Expenditure
of ₹ 1055174 (10.55 Lacs ) done.
Cummulative ₹ 220.31Lacs ( against 234.51Lacs )

10 years ago

on Sunday, May 31st 2015, 6:30:00 pm
94.79%
Financial Progress

43rd Expenditure
of ₹ 199048 (1.99 Lacs ) done.
Cummulative ₹ 222.30Lacs ( against 234.51Lacs )

10 years ago

on Tuesday, June 30th 2015, 6:30:00 pm
97.38%
Financial Progress

44th Expenditure
of ₹ 605683 (6.06 Lacs ) done.
Cummulative ₹ 228.36Lacs ( against 234.51Lacs )

10 years ago

on Friday, July 31st 2015, 6:30:00 pm
97.39%
Financial Progress

45th Expenditure
of ₹ 3800 (0.04 Lacs ) done.
Cummulative ₹ 228.40Lacs ( against 234.51Lacs )

10 years ago

on Sunday, January 31st 2016, 6:30:00 pm
97.46%
Financial Progress

46th Expenditure
of ₹ 16397 (0.16 Lacs ) done.
Cummulative ₹ 228.56Lacs ( against 234.51Lacs )

9 years ago

on Wednesday, August 31st 2016, 6:30:00 pm
98.20%
Financial Progress

47th Expenditure
of ₹ 173111 (1.73 Lacs ) done.
Cummulative ₹ 230.29Lacs ( against 234.51Lacs )

8 years ago

on Wednesday, February 28th 2018, 6:30:00 pm
95.64%
Financial Progress

48th Expenditure
of ₹ -600683 (-6.01 Lacs ) done.
Cummulative ₹ 224.29Lacs ( against 234.51Lacs )

7 years ago

on Monday, December 31st 2018, 6:30:00 pm
96.65%
Financial Progress

49th Expenditure
of ₹ 236307 (2.36 Lacs ) done.
Cummulative ₹ 226.65Lacs ( against 234.51Lacs )