on Tuesday, January 20th 2004, 6:30:00 pm
Work Sanctioned
अल्मोड़ा में सोनली- खनेटा -जैठा-खुरड़ी मोटर मार्ग।
on Friday, July 21st 2006, 6:30:00 pm
Technical Sanction
of ₹ 27.8 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2294/63c
on Saturday, February 28th 2009, 6:30:00 pm
40.25%
Financial Progress
1st Expenditure
of ₹ 1119000 (11.19 Lacs ) done.
Cummulative ₹ 11.19Lacs ( against 27.8Lacs )
on Sunday, January 31st 2010, 6:30:00 pm
46.15%
Financial Progress
2nd Expenditure
of ₹ 164000 (1.64 Lacs ) done.
Cummulative ₹ 12.83Lacs ( against 27.8Lacs )
on Friday, April 30th 2010, 6:30:00 pm
46.26%
Financial Progress
3rd Expenditure
of ₹ 3000 (0.03 Lacs ) done.
Cummulative ₹ 12.86Lacs ( against 27.8Lacs )
on Sunday, October 31st 2010, 6:30:00 pm
50.95%
Financial Progress
4th Expenditure
of ₹ 130425 (1.30 Lacs ) done.
Cummulative ₹ 14.16Lacs ( against 27.8Lacs )
on Monday, February 28th 2011, 6:30:00 pm
50.96%
Financial Progress
5th Expenditure
of ₹ 200 (0.00 Lacs ) done.
Cummulative ₹ 14.17Lacs ( against 27.8Lacs )
on Wednesday, August 31st 2011, 6:30:00 pm
58.91%
Financial Progress
6th Expenditure
of ₹ 221183 (2.21 Lacs ) done.
Cummulative ₹ 16.38Lacs ( against 27.8Lacs )
on Saturday, December 31st 2011, 6:30:00 pm
64.11%
Financial Progress
7th Expenditure
of ₹ 144386 (1.44 Lacs ) done.
Cummulative ₹ 17.82Lacs ( against 27.8Lacs )
on Wednesday, February 29th 2012, 6:30:00 pm
64.15%
Financial Progress
8th Expenditure
of ₹ 1135 (0.01 Lacs ) done.
Cummulative ₹ 17.83Lacs ( against 27.8Lacs )
on Sunday, January 31st 2016, 6:30:00 pm
68.61%
Financial Progress
9th Expenditure
of ₹ 124000 (1.24 Lacs ) done.
Cummulative ₹ 19.07Lacs ( against 27.8Lacs )
on Thursday, June 30th 2016, 6:30:00 pm
72.96%
Financial Progress
10th Expenditure
of ₹ 120850 (1.21 Lacs ) done.
Cummulative ₹ 20.28Lacs ( against 27.8Lacs )