Work Sanctioned
गगास-उड़ीमहादेव-शैला- पानी भिकियासैन- मरचूला मोटर मार्ग ।
on Saturday, February 28th 2009, 6:30:00 pm
0.36%
Financial Progress
1st Expenditure
of ₹ 50000 (0.50 Lacs ) done.
Cummulative ₹ 0.50Lacs ( against 139Lacs )
on Wednesday, September 30th 2009, 6:30:00 pm
0.37%
Financial Progress
2nd Expenditure
of ₹ 1000 (0.01 Lacs ) done.
Cummulative ₹ 0.51Lacs ( against 139Lacs )
on Sunday, January 31st 2010, 6:30:00 pm
0.50%
Financial Progress
3rd Expenditure
of ₹ 18000 (0.18 Lacs ) done.
Cummulative ₹ 0.69Lacs ( against 139Lacs )
on Sunday, February 28th 2010, 6:30:00 pm
0.55%
Financial Progress
4th Expenditure
of ₹ 7000 (0.07 Lacs ) done.
Cummulative ₹ 0.76Lacs ( against 139Lacs )
on Sunday, October 31st 2010, 6:30:00 pm
0.65%
Financial Progress
5th Expenditure
of ₹ 15000 (0.15 Lacs ) done.
Cummulative ₹ 0.91Lacs ( against 139Lacs )
on Tuesday, November 30th 2010, 6:30:00 pm
1.11%
Financial Progress
6th Expenditure
of ₹ 63096 (0.63 Lacs ) done.
Cummulative ₹ 1.54Lacs ( against 139Lacs )
on Wednesday, January 19th 2011, 6:30:00 pm
Technical Sanction
of ₹ 108.65 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 426/909C-01/11
on Monday, February 28th 2011, 6:30:00 pm
4.18%
Financial Progress
7th Expenditure
of ₹ 427307 (4.27 Lacs ) done.
Cummulative ₹ 5.81Lacs ( against 139Lacs )
on Tuesday, May 31st 2011, 6:30:00 pm
7.11%
Financial Progress
8th Expenditure
of ₹ 406302 (4.06 Lacs ) done.
Cummulative ₹ 9.88Lacs ( against 139Lacs )
on Wednesday, November 30th 2011, 6:30:00 pm
7.12%
Financial Progress
9th Expenditure
of ₹ 1446 (0.01 Lacs ) done.
Cummulative ₹ 9.89Lacs ( against 139Lacs )
on Saturday, December 31st 2011, 6:30:00 pm
7.13%
Financial Progress
10th Expenditure
of ₹ 2500 (0.03 Lacs ) done.
Cummulative ₹ 9.92Lacs ( against 139Lacs )
on Monday, April 30th 2012, 6:30:00 pm
7.24%
Financial Progress
11th Expenditure
of ₹ 14938 (0.15 Lacs ) done.
Cummulative ₹ 10.07Lacs ( against 139Lacs )
on Thursday, May 31st 2012, 6:30:00 pm
7.32%
Financial Progress
12th Expenditure
of ₹ 11185 (0.11 Lacs ) done.
Cummulative ₹ 10.18Lacs ( against 139Lacs )
on Tuesday, July 31st 2012, 6:30:00 pm
7.33%
Financial Progress
13th Expenditure
of ₹ 1677 (0.02 Lacs ) done.
Cummulative ₹ 10.19Lacs ( against 139Lacs )
on Friday, August 31st 2012, 6:30:00 pm
10.16%
Financial Progress
14th Expenditure
of ₹ 392909 (3.93 Lacs ) done.
Cummulative ₹ 14.12Lacs ( against 139Lacs )
on Sunday, September 30th 2012, 6:30:00 pm
10.16%
Financial Progress
15th Expenditure
of ₹ 456 (0.00 Lacs ) done.
Cummulative ₹ 14.13Lacs ( against 139Lacs )
on Sunday, June 30th 2013, 6:30:00 pm
10.24%
Financial Progress
16th Expenditure
of ₹ 10375 (0.10 Lacs ) done.
Cummulative ₹ 14.23Lacs ( against 139Lacs )
on Sunday, September 30th 2018, 6:30:00 pm
15.19%
Financial Progress
17th Expenditure
of ₹ 687803 (6.88 Lacs ) done.
Cummulative ₹ 21.11Lacs ( against 139Lacs )
on Thursday, February 28th 2019, 6:30:00 pm
16.35%
Financial Progress
18th Expenditure
of ₹ 161175 (1.61 Lacs ) done.
Cummulative ₹ 22.72Lacs ( against 139Lacs )
on Tuesday, December 31st 2019, 6:30:00 pm
16.41%
Financial Progress
19th Expenditure
of ₹ 8800 (0.09 Lacs ) done.
Cummulative ₹ 22.81Lacs ( against 139Lacs )
on Friday, January 31st 2020, 6:30:00 pm
21.33%
Financial Progress
20th Expenditure
of ₹ 683388 (6.83 Lacs ) done.
Cummulative ₹ 29.64Lacs ( against 139Lacs )
on Sunday, February 2nd 2020, 6:30:00 pm
Technical Sanction
of ₹ 30.35 Lacs
2nd Technical Sanction of Work after survey,detailed design and analysis by Latter No. 414/909C-01/20
on Saturday, February 29th 2020, 6:30:00 pm
38.14%
Financial Progress
21st Expenditure
of ₹ 2337620 (23.38 Lacs ) done.
Cummulative ₹ 53.02Lacs ( against 139Lacs )
on Friday, July 30th 2021, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, September 29th 2021, 6:30:00 pm
40.77%
Financial Progress
22nd Expenditure
of ₹ 364856 (3.65 Lacs ) done.
Cummulative ₹ 56.67Lacs ( against 139Lacs )
on Sunday, October 30th 2022, 6:30:00 pm
44.29%
Financial Progress
23rd Expenditure
of ₹ 489540 (4.90 Lacs ) done.
Cummulative ₹ 61.56Lacs ( against 139Lacs )
on Tuesday, November 29th 2022, 6:30:00 pm
44.36%
Financial Progress
24th Expenditure
of ₹ 9730 (0.10 Lacs ) done.
Cummulative ₹ 61.66Lacs ( against 139Lacs )
on Friday, December 30th 2022, 6:30:00 pm
45.77%
Financial Progress
25th Expenditure
of ₹ 195816 (1.96 Lacs ) done.
Cummulative ₹ 63.62Lacs ( against 139Lacs )
on Thursday, March 30th 2023, 6:30:00 pm
47.71%
Financial Progress
26th Expenditure
of ₹ 269119 (2.69 Lacs ) done.
Cummulative ₹ 66.31Lacs ( against 139Lacs )
on Wednesday, April 17th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, August 8th 2024, 7:38:42 am
PWD UttarakahndPhoto (ID 51706) from Site Received
Uploader : Tula Ram, Assistant Engineer Civil ,CD Ranikhet
Landmark : 2nd km
Remark : inspection of MR for HS cutting andNOC permission regarding