6 years ago

on Wednesday, February 6th 2019, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा संख्य - 402/2018 के अन्तर्गत जनपद देहरादून के विधान सभा क्षेत्र विकासनगर में रूद्रपुर बड़वा मार्ग में गौना नदी पर सेतु निर्माण (प्रथम चरण)

6 years ago

on Sunday, November 10th 2019, 6:30:00 pm

Technical Sanction
of ₹ 15.02 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE TS No 219/1C

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
30.76%
Financial Progress

1st Expenditure
of ₹ 462000 (4.62 Lacs ) done.
Cummulative ₹ 4.62Lacs ( against 15.02Lacs )

2 years ago

on Tuesday, November 7th 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Monday, April 29th 2024, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 2nd time