2 years ago

on Monday, October 9th 2023, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा संख्या - 322/2020 के अन्तर्गत जनपद देहरादून के विधान सभा क्षेत्र सहसपुर के अन्तर्गत माण्डूवाला से कैरन फैक्ट्री होते हुए कांसवाली कण्डोली पौंधा सम्पर्क मार्ग का निर्माण कार्य।

a year ago

on Sunday, February 4th 2024, 6:30:00 pm

Technical Sanction
of ₹ 312.46 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 8464/9(519)YATA/2024

a year ago

on Tuesday, March 19th 2024, 6:30:00 pm
0.03%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 312.46Lacs )

a year ago

on Monday, May 6th 2024, 6:30:00 pm
13.17%
Financial Progress

2nd Expenditure
of ₹ 4105078 (41.05 Lacs ) done.
Cummulative ₹ 41.15Lacs ( against 312.46Lacs )

a year ago

on Wednesday, May 8th 2024, 6:30:00 pm
13.25%
Financial Progress

3rd Expenditure
of ₹ 24946 (0.25 Lacs ) done.
Cummulative ₹ 41.40Lacs ( against 312.46Lacs )

a year ago

on Wednesday, May 29th 2024, 6:30:00 pm
13.25%
Financial Progress

4th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 41.40Lacs ( against 312.46Lacs )

a year ago

on Sunday, June 2nd 2024, 6:30:00 pm
13.76%
Financial Progress

5th Expenditure
of ₹ 159795 (1.60 Lacs ) done.
Cummulative ₹ 43.00Lacs ( against 312.46Lacs )

a year ago

on Monday, June 17th 2024, 6:30:00 pm
13.82%
Financial Progress

6th Expenditure
of ₹ 18878 (0.19 Lacs ) done.
Cummulative ₹ 43.19Lacs ( against 312.46Lacs )

a year ago

on Sunday, June 23rd 2024, 6:30:00 pm
13.82%
Financial Progress

7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 43.19Lacs ( against 312.46Lacs )

a year ago

on Tuesday, June 25th 2024, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Wednesday, June 26th 2024, 6:30:00 pm
13.90%
Financial Progress

8th Expenditure
of ₹ 25172 (0.25 Lacs ) done.
Cummulative ₹ 43.44Lacs ( against 312.46Lacs )

10 months ago

on Saturday, June 29th 2024, 12:18:34 am
<span class="4">Picture Id:48545</span>
PWD Uttarakahnd
Photo (ID 48545) from Site Received
Uploader : Mohd Amir , Assistant Engineer Civil ,NH Div Dehradun
Landmark : 5.700
Remark : End

10 months ago

on Thursday, July 25th 2024, 6:30:00 pm
13.90%
Financial Progress

9th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 43.44Lacs ( against 312.46Lacs )

9 months ago

on Tuesday, July 30th 2024, 6:30:00 pm
13.96%
Financial Progress

10th Expenditure
of ₹ 18250 (0.18 Lacs ) done.
Cummulative ₹ 43.62Lacs ( against 312.46Lacs )

9 months ago

on Tuesday, July 30th 2024, 6:30:00 pm
14.01%
Financial Progress

11th Expenditure
of ₹ 15000 (0.15 Lacs ) done.
Cummulative ₹ 43.77Lacs ( against 312.46Lacs )

8 months ago

on Thursday, August 29th 2024, 6:30:00 pm
14.03%
Financial Progress

12th Expenditure
of ₹ 6490 (0.06 Lacs ) done.
Cummulative ₹ 43.84Lacs ( against 312.46Lacs )

8 months ago

on Thursday, August 29th 2024, 6:30:00 pm
23.23%
Financial Progress

13th Expenditure
of ₹ 2875654 (28.76 Lacs ) done.
Cummulative ₹ 72.59Lacs ( against 312.46Lacs )

8 months ago

on Tuesday, September 3rd 2024, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 2nd time

7 months ago

on Monday, October 21st 2024, 6:30:00 pm
28.77%
Financial Progress

14th Expenditure
of ₹ 1729321 (17.29 Lacs ) done.
Cummulative ₹ 89.89Lacs ( against 312.46Lacs )

7 months ago

on Thursday, October 24th 2024, 6:30:00 pm
28.83%
Financial Progress

15th Expenditure
of ₹ 20060 (0.20 Lacs ) done.
Cummulative ₹ 90.09Lacs ( against 312.46Lacs )

6 months ago

on Thursday, November 7th 2024, 6:30:00 pm
29.18%
Financial Progress

16th Expenditure
of ₹ 108167 (1.08 Lacs ) done.
Cummulative ₹ 91.17Lacs ( against 312.46Lacs )

6 months ago

on Thursday, November 7th 2024, 6:30:00 pm
29.54%
Financial Progress

17th Expenditure
of ₹ 112149 (1.12 Lacs ) done.
Cummulative ₹ 92.29Lacs ( against 312.46Lacs )

5 months ago

on Friday, November 29th 2024, 6:30:00 pm
29.69%
Financial Progress

18th Expenditure
of ₹ 49106 (0.49 Lacs ) done.
Cummulative ₹ 92.78Lacs ( against 312.46Lacs )

5 months ago

on Monday, December 23rd 2024, 6:30:00 pm
37.79%
Financial Progress

19th Expenditure
of ₹ 2530410 (25.30 Lacs ) done.
Cummulative ₹ 118.08Lacs ( against 312.46Lacs )

4 months ago

on Sunday, December 29th 2024, 6:30:00 pm
45.36%
Financial Progress

20th Expenditure
of ₹ 2364590 (23.65 Lacs ) done.
Cummulative ₹ 141.73Lacs ( against 312.46Lacs )

4 months ago

on Tuesday, December 31st 2024, 6:30:00 pm
61%

Physical Progress
Physical Progress Reported at 3rd time

4 months ago

on Tuesday, December 31st 2024, 6:30:00 pm
53.05%
Financial Progress

21st Expenditure
of ₹ 2402113 (24.02 Lacs ) done.
Cummulative ₹ 165.75Lacs ( against 312.46Lacs )

4 months ago

on Sunday, January 19th 2025, 6:30:00 pm
75%

Physical Progress
Physical Progress Reported at 4th time

3 months ago

on Tuesday, February 11th 2025, 6:30:00 pm
53.18%
Financial Progress

23rd Expenditure
of ₹ 23590 (0.24 Lacs ) done.
Cummulative ₹ 166.18Lacs ( against 312.46Lacs )

3 months ago

on Tuesday, February 11th 2025, 6:30:00 pm
53.11%
Financial Progress

22nd Expenditure
of ₹ 19313 (0.19 Lacs ) done.
Cummulative ₹ 165.94Lacs ( against 312.46Lacs )

3 months ago

on Tuesday, February 11th 2025, 6:30:00 pm
60.66%
Financial Progress

24th Expenditure
of ₹ 2334731 (23.35 Lacs ) done.
Cummulative ₹ 189.53Lacs ( against 312.46Lacs )

3 months ago

on Tuesday, February 11th 2025, 6:30:00 pm
67.80%
Financial Progress

25th Expenditure
of ₹ 2231100 (22.31 Lacs ) done.
Cummulative ₹ 211.84Lacs ( against 312.46Lacs )

3 months ago

on Tuesday, February 18th 2025, 6:30:00 pm
68.13%
Financial Progress

26th Expenditure
of ₹ 102790 (1.03 Lacs ) done.
Cummulative ₹ 212.87Lacs ( against 312.46Lacs )

3 months ago

on Sunday, February 23rd 2025, 6:30:00 pm
68.16%
Financial Progress

27th Expenditure
of ₹ 10707 (0.11 Lacs ) done.
Cummulative ₹ 212.97Lacs ( against 312.46Lacs )

2 months ago

on Tuesday, March 11th 2025, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 5th time

2 months ago

on Tuesday, March 11th 2025, 6:30:00 pm
69.51%
Financial Progress

28th Expenditure
of ₹ 422999 (4.23 Lacs ) done.
Cummulative ₹ 217.20Lacs ( against 312.46Lacs )

2 months ago

on Sunday, March 16th 2025, 6:30:00 pm
69.64%
Financial Progress

29th Expenditure
of ₹ 40052 (0.40 Lacs ) done.
Cummulative ₹ 217.60Lacs ( against 312.46Lacs )

2 months ago

on Monday, March 17th 2025, 6:30:00 pm
90.53%
Financial Progress

30th Expenditure
of ₹ 6527235 (65.27 Lacs ) done.
Cummulative ₹ 282.88Lacs ( against 312.46Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
90.72%
Financial Progress

31st Expenditure
of ₹ 59932 (0.60 Lacs ) done.
Cummulative ₹ 283.48Lacs ( against 312.46Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
91.37%
Financial Progress

32nd Expenditure
of ₹ 201409 (2.01 Lacs ) done.
Cummulative ₹ 285.49Lacs ( against 312.46Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
91.54%
Financial Progress

33rd Expenditure
of ₹ 52774 (0.53 Lacs ) done.
Cummulative ₹ 286.02Lacs ( against 312.46Lacs )

2 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
91.57%
Financial Progress

34th Expenditure
of ₹ 11200 (0.11 Lacs ) done.
Cummulative ₹ 286.13Lacs ( against 312.46Lacs )

2 months ago

on Monday, March 24th 2025, 6:30:00 pm
92.03%
Financial Progress

36th Expenditure
of ₹ 58203 (0.58 Lacs ) done.
Cummulative ₹ 287.55Lacs ( against 312.46Lacs )

2 months ago

on Monday, March 24th 2025, 6:30:00 pm
91.84%
Financial Progress

35th Expenditure
of ₹ 84219 (0.84 Lacs ) done.
Cummulative ₹ 286.97Lacs ( against 312.46Lacs )

2 months ago

on Monday, March 24th 2025, 6:30:00 pm
94.78%
Financial Progress

38th Expenditure
of ₹ 180000 (1.80 Lacs ) done.
Cummulative ₹ 296.16Lacs ( against 312.46Lacs )

2 months ago

on Monday, March 24th 2025, 6:30:00 pm
94.21%
Financial Progress

37th Expenditure
of ₹ 680250 (6.80 Lacs ) done.
Cummulative ₹ 294.36Lacs ( against 312.46Lacs )

a month ago

on Monday, March 31st 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 6th time