12 years ago

on Wednesday, November 13th 2013, 6:30:00 pm
Work Sanctioned
जनपद देहरादून के विकासखण्ड -सहसपुर में ग्राम पंचायत रिखोली के हल्दूवाला से ग्राम पंचायत चैकी विरावड़ी तक सेतु सहित मोटर मार्ग का निर्माण।

11 years ago

on Tuesday, July 29th 2014, 6:30:00 pm

Technical Sanction
of ₹ 16.31 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 158/1C

11 years ago

on Saturday, January 31st 2015, 6:30:00 pm
13.43%
Financial Progress

1st Expenditure
of ₹ 219000 (2.19 Lacs ) done.
Cummulative ₹ 2.19Lacs ( against 16.31Lacs )

10 years ago

on Sunday, January 31st 2016, 6:30:00 pm
21.34%
Financial Progress

2nd Expenditure
of ₹ 129000 (1.29 Lacs ) done.
Cummulative ₹ 3.48Lacs ( against 16.31Lacs )

9 years ago

on Sunday, July 31st 2016, 6:30:00 pm
25.87%
Financial Progress

3rd Expenditure
of ₹ 74000 (0.74 Lacs ) done.
Cummulative ₹ 4.22Lacs ( against 16.31Lacs )

7 years ago

on Thursday, February 28th 2019, 6:30:00 pm
26.00%
Financial Progress

4th Expenditure
of ₹ 2000 (0.02 Lacs ) done.
Cummulative ₹ 4.24Lacs ( against 16.31Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
310.85%
Financial Progress

5th Expenditure
of ₹ 4646000 (46.46 Lacs ) done.
Cummulative ₹ 50.70Lacs ( against 16.31Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
26.00%
Financial Progress

6th Expenditure
of ₹ -4646000 (-46.46 Lacs ) done.
Cummulative ₹ 4.24Lacs ( against 16.31Lacs )

a year ago

on Wednesday, June 19th 2024, 3:43:16 am
<span class="4">Picture Id:45910</span>
PWD Uttarakahnd
Photo (ID 45910) from Site Received
Uploader : Vineet Saini, Additional Assistant Engineer Civil ,CD Chamba
Landmark : 1.35
Remark : Road joint inspection with forest and public representative and pradhan

a year ago

on Thursday, August 15th 2024, 6:30:00 pm
26.00%
Financial Progress

7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 4.24Lacs ( against 16.31Lacs )

a year ago

on Wednesday, August 21st 2024, 6:30:00 pm
42.49%
Financial Progress

8th Expenditure
of ₹ 269019 (2.69 Lacs ) done.
Cummulative ₹ 6.93Lacs ( against 16.31Lacs )

8 months ago

on Monday, December 23rd 2024, 6:30:00 pm
57.63%
Financial Progress

9th Expenditure
of ₹ 246900 (2.47 Lacs ) done.
Cummulative ₹ 9.40Lacs ( against 16.31Lacs )

5 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
72.77%
Financial Progress

10th Expenditure
of ₹ 247014 (2.47 Lacs ) done.
Cummulative ₹ 11.87Lacs ( against 16.31Lacs )

2 months ago

on Sunday, July 13th 2025, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

AI layer

AI Road
AI Bridge
50 m
100 ft
Unavailable