Work Sanctioned
जनपद देहरादून में रोहटा खड्ड से अटाल सम्पर्क मार्ग।

16 years ago

on Saturday, February 28th 2009, 6:30:00 pm
0.20%
Financial Progress

1st Expenditure
of ₹ 11000 (0.11 Lacs ) done.
Cummulative ₹ 0.11Lacs ( against 55.6Lacs )

16 years ago

on Wednesday, September 30th 2009, 6:30:00 pm
0.70%
Financial Progress

2nd Expenditure
of ₹ 28000 (0.28 Lacs ) done.
Cummulative ₹ 0.39Lacs ( against 55.6Lacs )

15 years ago

on Tuesday, August 31st 2010, 6:30:00 pm
0.99%
Financial Progress

3rd Expenditure
of ₹ 16000 (0.16 Lacs ) done.
Cummulative ₹ 0.55Lacs ( against 55.6Lacs )

10 years ago

on Thursday, January 28th 2016, 6:30:00 pm

Technical Sanction
of ₹ 55.6 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 17/1C

8 years ago

on Friday, March 31st 2017, 6:30:00 pm
5.19%
Financial Progress

4th Expenditure
of ₹ 233756 (2.34 Lacs ) done.
Cummulative ₹ 2.89Lacs ( against 55.6Lacs )

8 years ago

on Wednesday, January 31st 2018, 6:30:00 pm
20.73%
Financial Progress

5th Expenditure
of ₹ 863721 (8.64 Lacs ) done.
Cummulative ₹ 11.52Lacs ( against 55.6Lacs )

7 years ago

on Sunday, September 30th 2018, 6:30:00 pm
34.03%
Financial Progress

6th Expenditure
of ₹ 739352 (7.39 Lacs ) done.
Cummulative ₹ 18.92Lacs ( against 55.6Lacs )

5 years ago

on Saturday, February 29th 2020, 6:30:00 pm
42.29%
Financial Progress

7th Expenditure
of ₹ 459471 (4.59 Lacs ) done.
Cummulative ₹ 23.51Lacs ( against 55.6Lacs )

5 years ago

on Wednesday, September 30th 2020, 6:30:00 pm
55.75%
Financial Progress

8th Expenditure
of ₹ 748181 (7.48 Lacs ) done.
Cummulative ₹ 30.99Lacs ( against 55.6Lacs )

5 years ago

on Monday, November 30th 2020, 6:30:00 pm
87.43%
Financial Progress

9th Expenditure
of ₹ 1761836 (17.62 Lacs ) done.
Cummulative ₹ 48.61Lacs ( against 55.6Lacs )

5 years ago

on Thursday, December 31st 2020, 6:30:00 pm
87.96%
Financial Progress

10th Expenditure
of ₹ 29508 (0.30 Lacs ) done.
Cummulative ₹ 48.91Lacs ( against 55.6Lacs )

4 years ago

on Sunday, February 28th 2021, 6:30:00 pm
99.87%
Financial Progress

11th Expenditure
of ₹ 661734 (6.62 Lacs ) done.
Cummulative ₹ 55.53Lacs ( against 55.6Lacs )

4 years ago

on Tuesday, June 29th 2021, 6:30:00 pm
99.87%
Financial Progress

13th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 55.53Lacs ( against 55.6Lacs )

4 years ago

on Tuesday, June 29th 2021, 6:30:00 pm
99.87%
Financial Progress

12th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 55.53Lacs ( against 55.6Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
100.51%
Financial Progress

14th Expenditure
of ₹ 35925 (0.36 Lacs ) done.
Cummulative ₹ 55.88Lacs ( against 55.6Lacs )

3 years ago

on Wednesday, June 8th 2022, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
99.87%
Financial Progress

15th Expenditure
of ₹ -35625 (-0.36 Lacs ) done.
Cummulative ₹ 55.53Lacs ( against 55.6Lacs )

7 months ago

on Thursday, January 30th 2025, 6:30:00 pm
99.87%
Financial Progress

16th Expenditure
of ₹ 177 (0.00 Lacs ) done.
Cummulative ₹ 55.53Lacs ( against 55.6Lacs )

5 months ago

on Saturday, March 29th 2025, 6:30:00 pm
99.82%
Financial Progress

17th Expenditure
of ₹ -3000 (-0.03 Lacs ) done.
Cummulative ₹ 55.50Lacs ( against 55.6Lacs )