19 years ago

on Sunday, September 24th 2006, 6:30:00 pm
Work Sanctioned
सारनी मोटर मार्ग का विस्तार।

16 years ago

on Saturday, February 28th 2009, 6:30:00 pm
0.39%
Financial Progress

1st Expenditure
of ₹ 29000 (0.29 Lacs ) done.
Cummulative ₹ 0.29Lacs ( against 73.78Lacs )

4 years ago

on Friday, October 29th 2021, 9:08:46 am

Technical Sanction
of ₹ 73.78 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 108/1सी

4 years ago

on Friday, October 29th 2021, 9:10:23 am

Technical Sanction
of ₹ 73.78 Lacs

2nd Technical Sanction of Work after survey,detailed design and analysis by Latter No. 108/1सी

3 years ago

on Sunday, February 27th 2022, 6:30:00 pm
0.96%
Financial Progress

2nd Expenditure
of ₹ 41496 (0.41 Lacs ) done.
Cummulative ₹ 0.70Lacs ( against 73.78Lacs )

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
0.96%
Financial Progress

3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.70Lacs ( against 73.78Lacs )

2 years ago

on Thursday, June 29th 2023, 6:30:00 pm
31.73%
Financial Progress

4th Expenditure
of ₹ 2270870 (22.71 Lacs ) done.
Cummulative ₹ 23.41Lacs ( against 73.78Lacs )

2 years ago

on Sunday, July 30th 2023, 6:30:00 pm
44.09%
Financial Progress

5th Expenditure
of ₹ 911275 (9.11 Lacs ) done.
Cummulative ₹ 32.53Lacs ( against 73.78Lacs )

2 years ago

on Wednesday, August 30th 2023, 6:30:00 pm
44.20%
Financial Progress

6th Expenditure
of ₹ 8400 (0.08 Lacs ) done.
Cummulative ₹ 32.61Lacs ( against 73.78Lacs )

2 years ago

on Thursday, September 21st 2023, 6:30:00 pm
28%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Saturday, December 30th 2023, 6:30:00 pm
64.23%
Financial Progress

7th Expenditure
of ₹ 1477677 (14.78 Lacs ) done.
Cummulative ₹ 47.39Lacs ( against 73.78Lacs )

a year ago

on Thursday, January 4th 2024, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Wednesday, February 28th 2024, 6:30:00 pm
84.95%
Financial Progress

8th Expenditure
of ₹ 1528730 (15.29 Lacs ) done.
Cummulative ₹ 62.67Lacs ( against 73.78Lacs )

10 months ago

on Saturday, June 29th 2024, 6:30:00 pm
90.24%
Financial Progress

9th Expenditure
of ₹ 390244 (3.90 Lacs ) done.
Cummulative ₹ 66.58Lacs ( against 73.78Lacs )

8 months ago

on Monday, September 9th 2024, 6:30:00 pm
90.64%
Financial Progress

10th Expenditure
of ₹ 29760 (0.30 Lacs ) done.
Cummulative ₹ 66.87Lacs ( against 73.78Lacs )

8 months ago

on Tuesday, September 10th 2024, 6:30:00 pm
92.00%
Financial Progress

11th Expenditure
of ₹ 100000 (1.00 Lacs ) done.
Cummulative ₹ 67.87Lacs ( against 73.78Lacs )

5 months ago

on Friday, November 29th 2024, 6:30:00 pm
92.29%
Financial Progress

12th Expenditure
of ₹ 22066 (0.22 Lacs ) done.
Cummulative ₹ 68.10Lacs ( against 73.78Lacs )

4 months ago

on Saturday, December 28th 2024, 6:30:00 pm
93.54%
Financial Progress

13th Expenditure
of ₹ 92160 (0.92 Lacs ) done.
Cummulative ₹ 69.02Lacs ( against 73.78Lacs )

4 months ago

on Tuesday, December 31st 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

4 months ago

on Wednesday, January 1st 2025, 6:30:00 pm
93.14%
Financial Progress

14th Expenditure
of ₹ -29760 (-0.30 Lacs ) done.
Cummulative ₹ 68.72Lacs ( against 73.78Lacs )