Refresh data
on Monday, July 13th 2020, 6:30:00 pm
Work Sanctioned
मा0मुुु0 घोेषणा घो0सं0 94/2019 के अन्तर्गत जनपद देहरादून के विधान सभा क्षेत्र चकराता के अन्तर्गत कुनावा डांडा से वाया रावना पी.आर.डी. मार्ग का अवशेष 64 कि.मी. मोटर मार्ग का निर्माण (प्रथम चरण)।
on Thursday, March 30th 2023, 6:30:00 pm
7.37%
Financial Progress
1st Expenditure
of ₹ 172426 (1.72 Lacs ) done.
Cummulative ₹ 1.72Lacs ( against 23.38Lacs )
on Friday, April 26th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Saturday, June 29th 2024, 6:30:00 pm
8.37%
Financial Progress
2nd Expenditure
of ₹ 23260 (0.23 Lacs ) done.
Cummulative ₹ 1.96Lacs ( against 23.38Lacs )
on Thursday, February 27th 2025, 6:30:00 pm
8.99%
Financial Progress
3rd Expenditure
of ₹ 14571 (0.15 Lacs ) done.
Cummulative ₹ 2.10Lacs ( against 23.38Lacs )