on Monday, February 27th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत चकराता-लाखामण्डल मोटर मार्ग राज्य मार्ग सं0-18, के कि.मी. 65 चै0सं0 64.025 पर (राठू-गुठाड़) पूर्व में निर्मित क्लास ‘बी‘ लोडिंग सेतु के स्थान पर क्लास ‘ए‘ लोडिंग (डेढ़ लेन )सेतु का निर्माण कार्य (स्पान 16मी0) (प्रथम चरण)।
on Thursday, March 30th 2023, 6:30:00 pm
0.00%
Financial Progress
1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 4.8Lacs )
on Wednesday, August 30th 2023, 6:30:00 pm
10.51%
Financial Progress
2nd Expenditure
of ₹ 50450 (0.50 Lacs ) done.
Cummulative ₹ 0.50Lacs ( against 4.8Lacs )
on Friday, September 29th 2023, 6:30:00 pm
15.77%
Financial Progress
3rd Expenditure
of ₹ 25225 (0.25 Lacs ) done.
Cummulative ₹ 0.76Lacs ( against 4.8Lacs )
on Saturday, March 30th 2024, 6:30:00 pm
53.47%
Financial Progress
4th Expenditure
of ₹ 180974 (1.81 Lacs ) done.
Cummulative ₹ 2.57Lacs ( against 4.8Lacs )
on Tuesday, April 30th 2024, 6:30:00 pm
65%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, July 18th 2024, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, December 25th 2024, 6:30:00 pm
61.49%
Financial Progress
5th Expenditure
of ₹ 38498 (0.38 Lacs ) done.
Cummulative ₹ 2.95Lacs ( against 4.8Lacs )
on Thursday, February 27th 2025, 6:30:00 pm
64.84%
Financial Progress
6th Expenditure
of ₹ 16065 (0.16 Lacs ) done.
Cummulative ₹ 3.11Lacs ( against 4.8Lacs )