Refresh data
on Tuesday, October 26th 2021, 6:30:00 pm
Work Sanctioned
केन्द्रीय सड़क अवसंरचना निधि के अन्तर्गत ’’जोगीवाला लाडपुर रायपुर रोड सहस्त्रधारा क्रासिंग होते हुए खैरी मानसिंह के निकट तक सड़क मार्ग का चैड़ीकरण एवं सौन्दर्यीकरण कार्य। (जाॅब नं0 - 37)’’
on Monday, December 6th 2021, 8:31:50 am
Technical Sanction
of ₹ 7753 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 4925/09(408)yata-ster-1(Z.O.)/2021
on Thursday, March 24th 2022, 6:30:00 pm
2.78%
Financial Progress
1st Expenditure
of ₹ 21965600 (219.66 Lacs ) done.
Cummulative ₹ 219.66Lacs ( against 7914.71Lacs )
on Wednesday, March 30th 2022, 6:30:00 pm
3.08%
Financial Progress
2nd Expenditure
of ₹ 2440600 (24.41 Lacs ) done.
Cummulative ₹ 244.06Lacs ( against 7914.71Lacs )
on Monday, May 30th 2022, 6:30:00 pm
4.33%
Financial Progress
3rd Expenditure
of ₹ 9866749 (98.67 Lacs ) done.
Cummulative ₹ 342.73Lacs ( against 7914.71Lacs )
on Saturday, July 30th 2022, 6:30:00 pm
4.33%
Financial Progress
4th Expenditure
of ₹ 24540 (0.25 Lacs ) done.
Cummulative ₹ 342.97Lacs ( against 7914.71Lacs )
on Tuesday, August 30th 2022, 6:30:00 pm
4.64%
Financial Progress
5th Expenditure
of ₹ 2410800 (24.11 Lacs ) done.
Cummulative ₹ 367.08Lacs ( against 7914.71Lacs )
on Thursday, September 29th 2022, 6:30:00 pm
7.49%
Financial Progress
6th Expenditure
of ₹ 22593750 (225.94 Lacs ) done.
Cummulative ₹ 593.02Lacs ( against 7914.71Lacs )
on Sunday, October 30th 2022, 6:30:00 pm
7.60%
Financial Progress
7th Expenditure
of ₹ 882855 (8.83 Lacs ) done.
Cummulative ₹ 601.85Lacs ( against 7914.71Lacs )
on Tuesday, November 29th 2022, 6:30:00 pm
7.73%
Financial Progress
8th Expenditure
of ₹ 968282 (9.68 Lacs ) done.
Cummulative ₹ 611.53Lacs ( against 7914.71Lacs )
on Sunday, December 25th 2022, 6:30:00 pm
4%
Physical Progress
Physical Progress Reported at 1st time
on Friday, December 30th 2022, 6:30:00 pm
8.26%
Financial Progress
9th Expenditure
of ₹ 4226603 (42.27 Lacs ) done.
Cummulative ₹ 653.80Lacs ( against 7914.71Lacs )
on Monday, January 30th 2023, 6:30:00 pm
10.30%
Financial Progress
10th Expenditure
of ₹ 16124953 (161.25 Lacs ) done.
Cummulative ₹ 815.05Lacs ( against 7914.71Lacs )
on Monday, February 27th 2023, 6:30:00 pm
10.49%
Financial Progress
11th Expenditure
of ₹ 1516515 (15.17 Lacs ) done.
Cummulative ₹ 830.21Lacs ( against 7914.71Lacs )
on Thursday, March 30th 2023, 6:30:00 pm
13.19%
Financial Progress
12th Expenditure
of ₹ 21384753 (213.85 Lacs ) done.
Cummulative ₹ 1044.06Lacs ( against 7914.71Lacs )
on Saturday, April 8th 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, June 29th 2023, 6:30:00 pm
17.95%
Financial Progress
13th Expenditure
of ₹ 37663811 (376.64 Lacs ) done.
Cummulative ₹ 1420.70Lacs ( against 7914.71Lacs )
on Sunday, July 30th 2023, 6:30:00 pm
18.08%
Financial Progress
14th Expenditure
of ₹ 1031555 (10.32 Lacs ) done.
Cummulative ₹ 1431.01Lacs ( against 7914.71Lacs )
on Wednesday, August 30th 2023, 6:30:00 pm
22.15%
Financial Progress
15th Expenditure
of ₹ 32178272 (321.78 Lacs ) done.
Cummulative ₹ 1752.80Lacs ( against 7914.71Lacs )
on Thursday, September 7th 2023, 6:30:00 pm
17%
Physical Progress
Physical Progress Reported at 3rd time
on Friday, September 29th 2023, 6:30:00 pm
30.83%
Financial Progress
16th Expenditure
of ₹ 68706065 (687.06 Lacs ) done.
Cummulative ₹ 2439.86Lacs ( against 7914.71Lacs )
on Tuesday, October 3rd 2023, 6:30:00 pm
18%
Physical Progress
Physical Progress Reported at 4th time
on Monday, October 30th 2023, 6:30:00 pm
31.14%
Financial Progress
17th Expenditure
of ₹ 2500000 (25.00 Lacs ) done.
Cummulative ₹ 2464.86Lacs ( against 7914.71Lacs )
on Wednesday, November 1st 2023, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 5th time
on Wednesday, November 29th 2023, 6:30:00 pm
47.66%
Financial Progress
18th Expenditure
of ₹ 130738192 (1307.38 Lacs ) done.
Cummulative ₹ 3772.24Lacs ( against 7914.71Lacs )
on Wednesday, December 6th 2023, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 6th time
on Saturday, December 30th 2023, 6:30:00 pm
58.15%
Financial Progress
19th Expenditure
of ₹ 82977371 (829.77 Lacs ) done.
Cummulative ₹ 4602.01Lacs ( against 7914.71Lacs )
on Wednesday, January 3rd 2024, 6:30:00 pm
58.15%
Financial Progress
21st Expenditure
of ₹ 3599 (0.04 Lacs ) done.
Cummulative ₹ 4602.32Lacs ( against 7914.71Lacs )
on Wednesday, January 3rd 2024, 6:30:00 pm
58.15%
Financial Progress
20th Expenditure
of ₹ 26700 (0.27 Lacs ) done.
Cummulative ₹ 4602.28Lacs ( against 7914.71Lacs )
on Saturday, January 6th 2024, 6:30:00 pm
42%
Physical Progress
Physical Progress Reported at 7th time
on Tuesday, January 9th 2024, 6:30:00 pm
62.79%
Financial Progress
22nd Expenditure
of ₹ 36762900 (367.63 Lacs ) done.
Cummulative ₹ 4969.94Lacs ( against 7914.71Lacs )
on Tuesday, January 9th 2024, 6:30:00 pm
62.80%
Financial Progress
23rd Expenditure
of ₹ 61000 (0.61 Lacs ) done.
Cummulative ₹ 4970.55Lacs ( against 7914.71Lacs )
on Wednesday, January 10th 2024, 6:30:00 pm
62.80%
Financial Progress
24th Expenditure
of ₹ 1354 (0.01 Lacs ) done.
Cummulative ₹ 4970.57Lacs ( against 7914.71Lacs )
on Wednesday, January 10th 2024, 6:30:00 pm
62.81%
Financial Progress
25th Expenditure
of ₹ 72236 (0.72 Lacs ) done.
Cummulative ₹ 4971.29Lacs ( against 7914.71Lacs )
on Wednesday, January 10th 2024, 6:30:00 pm
62.84%
Financial Progress
26th Expenditure
of ₹ 249275 (2.49 Lacs ) done.
Cummulative ₹ 4973.78Lacs ( against 7914.71Lacs )
on Monday, January 15th 2024, 6:30:00 pm
65%
Physical Progress
Physical Progress Reported at 8th time
on Wednesday, January 17th 2024, 6:30:00 pm
62.85%
Financial Progress
27th Expenditure
of ₹ 27900 (0.28 Lacs ) done.
Cummulative ₹ 4974.06Lacs ( against 7914.71Lacs )
on Friday, February 9th 2024, 6:30:00 pm
62.85%
Financial Progress
28th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 4974.06Lacs ( against 7914.71Lacs )
on Tuesday, February 20th 2024, 6:30:00 pm
69.24%
Financial Progress
29th Expenditure
of ₹ 50637775 (506.38 Lacs ) done.
Cummulative ₹ 5480.44Lacs ( against 7914.71Lacs )
on Tuesday, February 20th 2024, 6:30:00 pm
75%
Physical Progress
Physical Progress Reported at 9th time
on Saturday, March 30th 2024, 6:30:00 pm
73.84%
Financial Progress
30th Expenditure
of ₹ 36362327 (363.62 Lacs ) done.
Cummulative ₹ 5844.06Lacs ( against 7914.71Lacs )
on Monday, April 29th 2024, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 10th time
on Thursday, May 9th 2024, 6:30:00 pm
88%
Physical Progress
Physical Progress Reported at 11th time
on Thursday, May 30th 2024, 10:46:33 am
PWD UttarakahndPhoto (ID 40625) from Site Received
Uploader : Bhrigunath Dwivedi, Executive Engineer Civil ,TD Rishikesh
Landmark : 12234
Remark : Thermoplaste and median Work in progress at km 11
on Thursday, May 30th 2024, 11:02:02 am
PWD UttarakahndPhoto (ID 40628) from Site Received
Uploader : Bhrigunath Dwivedi, Executive Engineer Civil ,TD Rishikesh
Landmark : 11600
Remark : Checking of Thermoplast paint at ch 11600
on Thursday, May 30th 2024, 11:09:25 am
PWD UttarakahndPhoto (ID 40629) from Site Received
Uploader : Bhrigunath Dwivedi, Executive Engineer Civil ,TD Rishikesh
Landmark : 10700
Remark : 6 MTR span culvert work in progress at ch 10700
on Thursday, May 30th 2024, 6:30:00 pm
73.84%
Financial Progress
31st Expenditure
of ₹ 20302 (0.20 Lacs ) done.
Cummulative ₹ 5844.27Lacs ( against 7914.71Lacs )
on Friday, May 31st 2024, 6:15:19 am
PWD UttarakahndPhoto (ID 40805) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700 IT park
Remark : Rebound hammer test at ch 10700 IT park for strength test of 6 MTR span culvert
on Friday, May 31st 2024, 8:56:38 am
PWD UttarakahndPhoto (ID 40811) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700
Remark : Rebound hammer test at ch 10700 LHS for strength
on Wednesday, June 5th 2024, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 12th time
on Friday, June 7th 2024, 7:39:21 am
PWD UttarakahndPhoto (ID 41968) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10.700 IT park
Remark : Dismantaling work in progress at km 13 ch 10.700 LHS for 6 MTR span RCC culvert
on Tuesday, June 11th 2024, 1:05:35 pm
PWD UttarakahndPhoto (ID 43230) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10.700 chLHS
Remark : 10700 LHS raft in 6 MTR span culvert
on Saturday, June 22nd 2024, 10:24:22 am
PWD UttarakahndPhoto (ID 46336) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700chainage
Remark : आईटी पार्क के सामने 6 मी कन्वर्ट के राइट हैंड साइड पर वॉल की तीसरी लिफ्ट का कार्य
on Wednesday, June 26th 2024, 8:44:16 am
PWD UttarakahndPhoto (ID 47029) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700 ch
Remark : आईटी पार्क बरसा पानी क्रॉस करते हुए एवं 6 मीटर स्थान की आरसीसी पुलिया का निर्माण कार्य प्रगति
on Wednesday, June 26th 2024, 2:09:34 pm
PWD UttarakahndPhoto (ID 47347) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700
Remark : Wall casting work for 6 MTR span bridge at it park
on Saturday, June 29th 2024, 6:30:00 pm
80.49%
Financial Progress
32nd Expenditure
of ₹ 52600000 (526.00 Lacs ) done.
Cummulative ₹ 6370.27Lacs ( against 7914.71Lacs )
on Monday, July 1st 2024, 1:36:44 pm
PWD UttarakahndPhoto (ID 49925) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700
Remark : 6 MTR span RCC Culvert work in progress at km 11
on Monday, July 1st 2024, 6:30:00 pm
95%
Physical Progress
Physical Progress Reported at 13th time
on Tuesday, July 2nd 2024, 10:46:33 am
PWD UttarakahndPhoto (ID 50081) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700
Remark : 6 MTR span RCC Culvert work in progress
on Friday, July 5th 2024, 6:24:33 pm
PWD UttarakahndPhoto (ID 50397) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 7525
Remark : Drain work in progress
on Monday, July 8th 2024, 12:09:51 pm
PWD UttarakahndPhoto (ID 50482) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700
Remark : 6MTR span culvert work in progress at km 11
on Thursday, July 11th 2024, 6:30:00 pm
80.49%
Financial Progress
34th Expenditure
of ₹ 17027 (0.17 Lacs ) done.
Cummulative ₹ 6370.53Lacs ( against 7914.71Lacs )
on Thursday, July 11th 2024, 6:30:00 pm
80.49%
Financial Progress
33rd Expenditure
of ₹ 9712 (0.10 Lacs ) done.
Cummulative ₹ 6370.36Lacs ( against 7914.71Lacs )
on Saturday, July 13th 2024, 9:49:06 am
PWD UttarakahndPhoto (ID 50724) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10710
Remark : Drain work in progress at10710
on Sunday, July 14th 2024, 6:30:00 pm
88.18%
Financial Progress
35th Expenditure
of ₹ 60837275 (608.37 Lacs ) done.
Cummulative ₹ 6978.91Lacs ( against 7914.71Lacs )
on Monday, July 15th 2024, 8:58:53 am
PWD UttarakahndPhoto (ID 50764) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10720
Remark : Drain work in progress at km 11
on Thursday, July 25th 2024, 6:30:00 pm
88.19%
Financial Progress
36th Expenditure
of ₹ 84481 (0.84 Lacs ) done.
Cummulative ₹ 6979.75Lacs ( against 7914.71Lacs )
on Sunday, July 28th 2024, 6:30:24 am
PWD UttarakahndPhoto (ID 51266) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700
Remark : protectin work for cd
on Sunday, August 4th 2024, 7:57:47 am
PWD UttarakahndPhoto (ID 51576) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700
Remark : पुलिया निर्माण के दौरान भरे मलवे की निकासी हेतु जेसीबी मशीन नाली सफाई
on Monday, August 5th 2024, 6:30:00 pm
98%
Physical Progress
Physical Progress Reported at 14th time
on Friday, August 9th 2024, 6:30:00 pm
90.23%
Financial Progress
37th Expenditure
of ₹ 16171000 (161.71 Lacs ) done.
Cummulative ₹ 7141.46Lacs ( against 7914.71Lacs )
on Friday, August 9th 2024, 6:30:00 pm
90.23%
Financial Progress
38th Expenditure
of ₹ 25072 (0.25 Lacs ) done.
Cummulative ₹ 7141.71Lacs ( against 7914.71Lacs )
on Friday, August 9th 2024, 6:30:00 pm
92.62%
Financial Progress
39th Expenditure
of ₹ 18883953 (188.84 Lacs ) done.
Cummulative ₹ 7330.55Lacs ( against 7914.71Lacs )
on Friday, August 9th 2024, 6:30:00 pm
92.63%
Financial Progress
40th Expenditure
of ₹ 80990 (0.81 Lacs ) done.
Cummulative ₹ 7331.36Lacs ( against 7914.71Lacs )
on Friday, August 9th 2024, 6:30:00 pm
92.64%
Financial Progress
41st Expenditure
of ₹ 84481 (0.84 Lacs ) done.
Cummulative ₹ 7332.21Lacs ( against 7914.71Lacs )
on Thursday, August 22nd 2024, 6:10:19 am
PWD UttarakahndPhoto (ID 52152) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700
Remark : भारी बरसात के बाद रेस्टोरेशन के कार्य निर्माण अधिनियम पुलिया के दोनों और
on Wednesday, August 28th 2024, 6:02:55 am
PWD UttarakahndPhoto (ID 52248) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700
Remark : निर्माणाधीन पुलिया में एप्रोच लेकर एप्रोच स्लैब का कार्य प्रगति पर
on Thursday, August 29th 2024, 9:36:38 am
PWD UttarakahndPhoto (ID 52293) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700
Remark : Approach slab casting
on Saturday, August 31st 2024, 5:44:01 pm
PWD UttarakahndPhoto (ID 52340) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700
Remark : LHS Approach slab casting work in progress at km 11 it park
on Saturday, September 14th 2024, 8:36:11 am
PWD UttarakahndPhoto (ID 52922) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10.800
Remark : It park drain cover work
on Thursday, September 26th 2024, 5:49:46 am
PWD UttarakahndPhoto (ID 53596) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 6.350
Remark : 53W1551
on Friday, September 27th 2024, 6:30:00 pm
92.69%
Financial Progress
42nd Expenditure
of ₹ 356896 (3.57 Lacs ) done.
Cummulative ₹ 7335.78Lacs ( against 7914.71Lacs )
on Sunday, September 29th 2024, 9:17:26 pm
PWD UttarakahndPhoto (ID 53597) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 6350
Remark : Work in progress
on Sunday, September 29th 2024, 6:30:00 pm
92.68%
Financial Progress
43rd Expenditure
of ₹ -34139 (-0.34 Lacs ) done.
Cummulative ₹ 7335.43Lacs ( against 7914.71Lacs )
on Friday, October 4th 2024, 11:49:59 am
PWD UttarakahndPhoto (ID 53911) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10700
Remark : 6 mtr span culvert work in progress
on Thursday, October 24th 2024, 6:30:00 pm
95.60%
Financial Progress
45th Expenditure
of ₹ 23080829 (230.81 Lacs ) done.
Cummulative ₹ 7566.24Lacs ( against 7914.71Lacs )
on Thursday, October 24th 2024, 6:30:00 pm
92.68%
Financial Progress
44th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 7335.43Lacs ( against 7914.71Lacs )
on Friday, November 29th 2024, 6:30:00 pm
96.05%
Financial Progress
46th Expenditure
of ₹ 3615907 (36.16 Lacs ) done.
Cummulative ₹ 7602.40Lacs ( against 7914.71Lacs )
on Wednesday, December 18th 2024, 6:30:00 pm
96.09%
Financial Progress
47th Expenditure
of ₹ 248272 (2.48 Lacs ) done.
Cummulative ₹ 7604.88Lacs ( against 7914.71Lacs )
on Thursday, January 30th 2025, 6:30:00 pm
96.09%
Financial Progress
48th Expenditure
of ₹ 27079 (0.27 Lacs ) done.
Cummulative ₹ 7605.15Lacs ( against 7914.71Lacs )
on Wednesday, February 26th 2025, 8:12:47 pm
PWD UttarakahndPhoto (ID 65113) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : km 7.700 RHS
Remark : रोड कटिंग कार्य के सापेक्ष अवशेष BC कार्य
on Thursday, February 27th 2025, 6:30:00 pm
96.66%
Financial Progress
49th Expenditure
of ₹ 4532079 (45.32 Lacs ) done.
Cummulative ₹ 7650.48Lacs ( against 7914.71Lacs )
on Wednesday, March 5th 2025, 6:18:09 pm
PWD UttarakahndPhoto (ID 65431) from Site Received
Uploader : Hemant Kumar Nautiyal, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : 10600
Remark : BC work in progress
on Sunday, March 30th 2025, 6:30:00 pm
99.90%
Financial Progress
50th Expenditure
of ₹ 25661731 (256.62 Lacs ) done.
Cummulative ₹ 7907.09Lacs ( against 7914.71Lacs )
on Saturday, April 5th 2025, 6:30:00 pm
99%
Physical Progress
Physical Progress Reported at 15th time