2 years ago

on Wednesday, October 25th 2023, 6:30:00 pm
Work Sanctioned
निक्षेप मद (इन्वेटस्टर समिट) के अन्तर्गत ऋषिकेश भानियावाला (एस0एच0-24) के किमी0 16 से 21 के मध्य मार्ग पर बी0एम0, बी0सी0 द्वारा सतह सुधार एवं विभिन्न मरम्मत तथा साज सज्जा का कार्य।

2 years ago

on Saturday, November 25th 2023, 12:40:25 pm

Technical Sanction
of ₹ 485.23 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE C.E. No. 7729/09 (511) Yata- (Zone-Off)/2023 Dated 25/11/2023

2 years ago

on Wednesday, December 6th 2023, 6:30:00 pm
92%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Saturday, January 6th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Wednesday, February 28th 2024, 6:30:00 pm
1.01%
Financial Progress

1st Expenditure
of ₹ 491009 (4.91 Lacs ) done.
Cummulative ₹ 4.91Lacs ( against 485.23Lacs )

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
59.54%
Financial Progress

2nd Expenditure
of ₹ 28401757 (284.02 Lacs ) done.
Cummulative ₹ 288.93Lacs ( against 485.23Lacs )

a year ago

on Thursday, May 30th 2024, 6:30:00 pm
61.55%
Financial Progress

3rd Expenditure
of ₹ 973516 (9.74 Lacs ) done.
Cummulative ₹ 298.66Lacs ( against 485.23Lacs )

a year ago

on Thursday, August 29th 2024, 6:30:00 pm
71.86%
Financial Progress

4th Expenditure
of ₹ 5000000 (50.00 Lacs ) done.
Cummulative ₹ 348.66Lacs ( against 485.23Lacs )

a year ago

on Friday, August 30th 2024, 6:30:00 pm
82.16%
Financial Progress

5th Expenditure
of ₹ 5000000 (50.00 Lacs ) done.
Cummulative ₹ 398.66Lacs ( against 485.23Lacs )

a year ago

on Sunday, September 29th 2024, 6:30:00 pm
82.27%
Financial Progress

6th Expenditure
of ₹ 53100 (0.53 Lacs ) done.
Cummulative ₹ 399.19Lacs ( against 485.23Lacs )

a year ago

on Tuesday, October 15th 2024, 6:30:00 pm
84.49%
Financial Progress

7th Expenditure
of ₹ 1077585 (10.78 Lacs ) done.
Cummulative ₹ 409.97Lacs ( against 485.23Lacs )

10 months ago

on Thursday, October 24th 2024, 6:30:00 pm
107.59%
Financial Progress

10th Expenditure
of ₹ 1077585 (10.78 Lacs ) done.
Cummulative ₹ 522.05Lacs ( against 485.23Lacs )

10 months ago

on Thursday, October 24th 2024, 6:30:00 pm
101.62%
Financial Progress

8th Expenditure
of ₹ 8312989 (83.13 Lacs ) done.
Cummulative ₹ 493.10Lacs ( against 485.23Lacs )

10 months ago

on Thursday, October 24th 2024, 6:30:00 pm
105.37%
Financial Progress

9th Expenditure
of ₹ 1817498 (18.17 Lacs ) done.
Cummulative ₹ 511.27Lacs ( against 485.23Lacs )

5 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
107.99%
Financial Progress

11th Expenditure
of ₹ 193520 (1.94 Lacs ) done.
Cummulative ₹ 523.99Lacs ( against 485.23Lacs )

5 months ago

on Sunday, March 30th 2025, 6:30:00 pm
95.46%
Financial Progress

12th Expenditure
of ₹ -6077585 (-60.78 Lacs ) done.
Cummulative ₹ 463.21Lacs ( against 485.23Lacs )