Refresh data
on Monday, January 1st 2024, 6:30:00 pm
Work Sanctioned
निक्षेप मद के अन्तर्गत देहरादून हवाई अड्डे पर स्थित राज्य अतिथि गृह को परिचालन क्षेत्र से पृथक किये जाने के फलस्वरूप मार्ग का निर्माण कार्य।
on Wednesday, June 5th 2024, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, June 27th 2024, 6:30:00 pm
14.92%
Financial Progress
1st Expenditure
of ₹ 2212508 (22.13 Lacs ) done.
Cummulative ₹ 22.13Lacs ( against 148.33Lacs )
on Friday, June 28th 2024, 5:17:54 am
PWD UttarakahndPhoto (ID 48097) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0/40
Remark : BM work at near airport road
on Friday, June 28th 2024, 5:32:32 am
PWD UttarakahndPhoto (ID 48113) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 1.34
Remark : Scbc work in progress at airport road
on Friday, June 28th 2024, 12:56:48 pm
PWD UttarakahndPhoto (ID 48404) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.700
Remark : SDBC work in progress at airport road
on Friday, June 28th 2024, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 2nd time
on Saturday, June 29th 2024, 6:30:00 pm
36.94%
Financial Progress
2nd Expenditure
of ₹ 3266514 (32.67 Lacs ) done.
Cummulative ₹ 54.79Lacs ( against 148.33Lacs )
on Sunday, June 30th 2024, 10:24:18 am
PWD UttarakahndPhoto (ID 49132) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.550
Remark : SDBC work
on Tuesday, July 16th 2024, 3:41:05 am
PWD UttarakahndPhoto (ID 50783) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.100
Remark : Inter loking tiles work in progress..
on Tuesday, July 16th 2024, 3:42:36 am
PWD UttarakahndPhoto (ID 50784) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.160
Remark : Shoulder inter loking tiles work in progress
on Tuesday, July 16th 2024, 4:13:12 am
PWD UttarakahndPhoto (ID 50785) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.275
Remark : Shoulder inter loking tiles work in progress
on Tuesday, July 23rd 2024, 6:57:02 am
PWD UttarakahndPhoto (ID 51020) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.175
Remark : Kc drain and tiles work in progress
on Tuesday, July 23rd 2024, 7:00:59 am
PWD UttarakahndPhoto (ID 51021) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.150
Remark : Tiles work and KC drain...
on Tuesday, July 23rd 2024, 7:11:04 am
PWD UttarakahndPhoto (ID 51023) from Site Received
Uploader : Rajesh Kumar Chauhan, Assistant Engineer Civil ,TD Rishikesh
Landmark : 0.125
Remark : Shoulder tile work in progress
on Friday, July 26th 2024, 8:30:46 am
PWD UttarakahndPhoto (ID 51165) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.25
Remark : Tiles work in progress
on Wednesday, July 31st 2024, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, August 6th 2024, 5:25:08 am
PWD UttarakahndPhoto (ID 51615) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.100
Remark : Work in progress
on Tuesday, August 6th 2024, 5:28:39 am
PWD UttarakahndPhoto (ID 51616) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.150
Remark : Work in progress
on Friday, August 9th 2024, 5:21:22 am
PWD UttarakahndPhoto (ID 51722) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.275
Remark : Core cutting BM SDBC work
on Friday, August 9th 2024, 5:31:51 am
PWD UttarakahndPhoto (ID 51723) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.275
Remark : Core cutting BM SDBC work
on Friday, August 9th 2024, 5:37:00 am
PWD UttarakahndPhoto (ID 51724) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0..275
Remark : Core cutting BM SDBC work
on Friday, August 9th 2024, 5:40:42 am
PWD UttarakahndPhoto (ID 51725) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.300
Remark : Testing
on Friday, August 9th 2024, 5:53:48 am
PWD UttarakahndPhoto (ID 51726) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.450
Remark : BM SDBC work core cutting testing
on Friday, August 9th 2024, 5:57:06 am
PWD UttarakahndPhoto (ID 51727) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.450
Remark : Airport road testing
on Saturday, August 10th 2024, 6:05:03 am
PWD UttarakahndPhoto (ID 51756) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.325
Remark : Work in progress..
on Friday, August 30th 2024, 6:30:00 pm
37.13%
Financial Progress
3rd Expenditure
of ₹ 27900 (0.28 Lacs ) done.
Cummulative ₹ 55.07Lacs ( against 148.33Lacs )
on Friday, August 30th 2024, 6:30:00 pm
37.23%
Financial Progress
4th Expenditure
of ₹ 15632 (0.16 Lacs ) done.
Cummulative ₹ 55.23Lacs ( against 148.33Lacs )
on Monday, September 2nd 2024, 6:30:00 pm
95%
Physical Progress
Physical Progress Reported at 4th time
on Wednesday, October 23rd 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 5th time
on Sunday, November 3rd 2024, 6:30:00 pm
55.04%
Financial Progress
5th Expenditure
of ₹ 2641470 (26.41 Lacs ) done.
Cummulative ₹ 81.64Lacs ( against 148.33Lacs )
on Friday, November 29th 2024, 6:30:00 pm
55.04%
Financial Progress
6th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 81.64Lacs ( against 148.33Lacs )
on Thursday, December 26th 2024, 6:30:00 pm
87.87%
Financial Progress
7th Expenditure
of ₹ 4869866 (48.70 Lacs ) done.
Cummulative ₹ 130.34Lacs ( against 148.33Lacs )