on Wednesday, July 17th 2024, 6:30:00 pm
Work Sanctioned
ग्राम पंचायत सौडा सरोली में सम्पर्क मार्ग निर्माण कार्य।
on Friday, December 20th 2024, 2:07:56 pm
Technical Sanction
of ₹ 3 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. E.E. No. 3311/6C (T.S.)
on Sunday, March 30th 2025, 6:30:00 pm
50.00%
Financial Progress
1st Expenditure
of ₹ 150000 (1.50 Lacs ) done.
Cummulative ₹ 1.50Lacs ( against 3Lacs )
on Sunday, May 4th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time