Refresh data
on Wednesday, October 28th 2020, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद देहरादून के विधान सभा क्षेत्र-धर्मपुर के अन्तर्गत वार्ड संख्या-71, पूर्वी पटेलनगर एवं वार्ड संख्या-73, विद्या विहार के आन्तरिक मार्गों का सी0सी0 टाईल्स एवं पी0सी0 द्वारा नवीनीकरण का कार्य।
on Tuesday, January 12th 2021, 6:30:00 pm
Technical Sanction
of ₹ 150.76 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. S.E.'s Letter No. 191/334(IX)C-9/21
on Tuesday, June 29th 2021, 6:30:00 pm
0.51%
Financial Progress
1st Expenditure
of ₹ 106305 (1.06 Lacs ) done.
Cummulative ₹ 1.06Lacs ( against 208.08Lacs )
on Sunday, September 5th 2021, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 1st time
on Friday, September 10th 2021, 12:20:00 am
PWD UttarakahndPhoto (ID 1339) from Site Received
Uploader : Mukesh Kumar, Assistant Engineer Civil ,TD Sahiya
Landmark : Dharam kante ke barabar wala marg
Remark : CC tile road
on Wednesday, September 29th 2021, 6:30:00 pm
24.65%
Financial Progress
2nd Expenditure
of ₹ 5022117 (50.22 Lacs ) done.
Cummulative ₹ 51.28Lacs ( against 208.08Lacs )
on Wednesday, October 6th 2021, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, November 29th 2021, 6:30:00 pm
24.82%
Financial Progress
3rd Expenditure
of ₹ 36600 (0.37 Lacs ) done.
Cummulative ₹ 51.65Lacs ( against 208.08Lacs )
on Thursday, December 30th 2021, 6:30:00 pm
36.20%
Financial Progress
4th Expenditure
of ₹ 2367150 (23.67 Lacs ) done.
Cummulative ₹ 75.32Lacs ( against 208.08Lacs )
on Sunday, January 30th 2022, 6:30:00 pm
36.80%
Financial Progress
5th Expenditure
of ₹ 124765 (1.25 Lacs ) done.
Cummulative ₹ 76.57Lacs ( against 208.08Lacs )
on Wednesday, February 23rd 2022, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 3rd time
on Sunday, February 27th 2022, 6:30:00 pm
48.23%
Financial Progress
6th Expenditure
of ₹ 2378499 (23.78 Lacs ) done.
Cummulative ₹ 100.35Lacs ( against 208.08Lacs )
on Wednesday, March 30th 2022, 6:30:00 pm
48.34%
Financial Progress
7th Expenditure
of ₹ 22200 (0.22 Lacs ) done.
Cummulative ₹ 100.58Lacs ( against 208.08Lacs )
on Sunday, April 24th 2022, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 4th time
on Monday, May 30th 2022, 6:30:00 pm
48.64%
Financial Progress
8th Expenditure
of ₹ 63229 (0.63 Lacs ) done.
Cummulative ₹ 101.21Lacs ( against 208.08Lacs )
on Saturday, July 30th 2022, 6:30:00 pm
48.80%
Financial Progress
9th Expenditure
of ₹ 34350 (0.34 Lacs ) done.
Cummulative ₹ 101.55Lacs ( against 208.08Lacs )
on Thursday, September 29th 2022, 6:30:00 pm
48.86%
Financial Progress
10th Expenditure
of ₹ 11100 (0.11 Lacs ) done.
Cummulative ₹ 101.66Lacs ( against 208.08Lacs )
on Sunday, October 30th 2022, 6:30:00 pm
72.70%
Financial Progress
11th Expenditure
of ₹ 4961142 (49.61 Lacs ) done.
Cummulative ₹ 151.27Lacs ( against 208.08Lacs )
on Monday, January 30th 2023, 6:30:00 pm
72.98%
Financial Progress
12th Expenditure
of ₹ 57840 (0.58 Lacs ) done.
Cummulative ₹ 151.85Lacs ( against 208.08Lacs )
on Monday, February 27th 2023, 6:30:00 pm
73.03%
Financial Progress
13th Expenditure
of ₹ 11100 (0.11 Lacs ) done.
Cummulative ₹ 151.96Lacs ( against 208.08Lacs )
on Thursday, March 30th 2023, 6:30:00 pm
86.41%
Financial Progress
14th Expenditure
of ₹ 2782891 (27.83 Lacs ) done.
Cummulative ₹ 179.79Lacs ( against 208.08Lacs )
on Tuesday, April 4th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 5th time
on Friday, December 29th 2023, 6:30:00 pm
91.80%
Financial Progress
15th Expenditure
of ₹ 1123471 (11.23 Lacs ) done.
Cummulative ₹ 191.03Lacs ( against 208.08Lacs )