on Sunday, February 16th 2020, 6:30:00 pm
Work Sanctioned
केन्द्रीय सड़क निधि के अन्तर्गत पिरान कलियर-हद्दीवाला-मानूबांस-मुजाहिदपुर-सत्तीवाला-कुडकावाला मोटर मार्ग का बी0एम0 व एस0डी0बी0सी0 द्वारा सुदृढीकरण का कार्य।
on Sunday, May 3rd 2020, 6:30:00 pm
Technical Sanction
of ₹ 878.39 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. CE level-1 D.Dun Letter no. 938/240/K.S.N.-Level-1(Zone)/2020
on Monday, August 31st 2020, 6:30:00 pm
29.15%
Financial Progress
1st Expenditure
of ₹ 25609000 (256.09 Lacs ) done.
Cummulative ₹ 256.09Lacs ( against 878.39Lacs )
on Saturday, October 31st 2020, 6:30:00 pm
40.07%
Financial Progress
2nd Expenditure
of ₹ 9591000 (95.91 Lacs ) done.
Cummulative ₹ 352.00Lacs ( against 878.39Lacs )
on Sunday, February 28th 2021, 6:30:00 pm
73.32%
Financial Progress
3rd Expenditure
of ₹ 29200000 (292.00 Lacs ) done.
Cummulative ₹ 644.00Lacs ( against 878.39Lacs )
on Wednesday, July 28th 2021, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, August 12th 2021, 6:30:00 pm
96.08%
Financial Progress
4th Expenditure
of ₹ 20000000 (200.00 Lacs ) done.
Cummulative ₹ 844.00Lacs ( against 878.39Lacs )
on Sunday, August 15th 2021, 7:28:20 am
PWD UttarakahndPhoto (ID 762) from Site Received
Uploader : Narendra Kumar, Assistant Engineer Civil ,CD Ukhimath
Landmark : Ch 9.1 fetehpur
Remark : BM SDBC completed
on Sunday, August 15th 2021, 10:18:45 pm
PWD UttarakahndPhoto (ID 748) from Site Received
Uploader : Narendra Kumar, Assistant Engineer Civil ,CD Ukhimath
Landmark : 0.300 piranklear
Remark : BM and SDBC work completed
on Monday, August 16th 2021, 2:02:24 am
PWD UttarakahndPhoto (ID 772) from Site Received
Uploader : Narendra Kumar, Assistant Engineer Civil ,CD Ukhimath
Landmark : Ch 12.70
Remark : BM SDBC completed
on Wednesday, August 30th 2023, 6:30:00 pm
98.60%
Financial Progress
5th Expenditure
of ₹ 2212000 (22.12 Lacs ) done.
Cummulative ₹ 866.12Lacs ( against 878.39Lacs )
on Thursday, October 19th 2023, 6:30:00 pm
99.50%
Financial Progress
6th Expenditure
of ₹ 788000 (7.88 Lacs ) done.
Cummulative ₹ 874.00Lacs ( against 878.39Lacs )