a year ago

on Wednesday, March 6th 2024, 6:30:00 pm
Work Sanctioned
राज्य योजना 2023-24 के अन्तर्गत जनपद हरिद्वार के वि0स0 क्षेत्र हरिद्वार ग्रामीण के ग्राम पीलीपड़ाव में दिलेराम से मन्नू की पुलिया की ओर इंटरलाॅकिंग टाईल्स द्वारा सड़क निर्माण कार्य।

a year ago

on Tuesday, March 12th 2024, 10:19:09 am

Technical Sanction
of ₹ 63.7 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE EE Approved Register Sl.no.23

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
0.17%
Financial Progress

1st Expenditure
of ₹ 11000 (0.11 Lacs ) done.
Cummulative ₹ 0.11Lacs ( against 63.7Lacs )

a year ago

on Monday, June 24th 2024, 6:30:00 pm
0.24%
Financial Progress

2nd Expenditure
of ₹ 4552 (0.05 Lacs ) done.
Cummulative ₹ 0.16Lacs ( against 63.7Lacs )

a year ago

on Tuesday, June 25th 2024, 6:30:00 pm
0.33%
Financial Progress

3rd Expenditure
of ₹ 5668 (0.06 Lacs ) done.
Cummulative ₹ 0.21Lacs ( against 63.7Lacs )

9 months ago

on Monday, November 25th 2024, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

8 months ago

on Friday, December 20th 2024, 6:30:00 pm
0.95%
Financial Progress

4th Expenditure
of ₹ 39000 (0.39 Lacs ) done.
Cummulative ₹ 0.60Lacs ( against 63.7Lacs )

8 months ago

on Friday, December 27th 2024, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 2nd time

7 months ago

on Tuesday, January 28th 2025, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 3rd time

7 months ago

on Thursday, January 30th 2025, 6:30:00 pm
24.95%
Financial Progress

5th Expenditure
of ₹ 1529000 (15.29 Lacs ) done.
Cummulative ₹ 15.89Lacs ( against 63.7Lacs )

6 months ago

on Thursday, February 27th 2025, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 4th time

6 months ago

on Thursday, February 27th 2025, 6:30:00 pm
26.41%
Financial Progress

6th Expenditure
of ₹ 93281 (0.93 Lacs ) done.
Cummulative ₹ 16.83Lacs ( against 63.7Lacs )

5 months ago

on Sunday, March 16th 2025, 6:30:00 pm
27.27%
Financial Progress

7th Expenditure
of ₹ 54355 (0.54 Lacs ) done.
Cummulative ₹ 17.37Lacs ( against 63.7Lacs )

5 months ago

on Sunday, March 16th 2025, 6:30:00 pm
48.25%
Financial Progress

9th Expenditure
of ₹ 1086589 (10.87 Lacs ) done.
Cummulative ₹ 30.73Lacs ( against 63.7Lacs )

5 months ago

on Sunday, March 16th 2025, 6:30:00 pm
31.19%
Financial Progress

8th Expenditure
of ₹ 249936 (2.50 Lacs ) done.
Cummulative ₹ 19.87Lacs ( against 63.7Lacs )

5 months ago

on Wednesday, March 26th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 5th time

3 months ago

on Sunday, May 18th 2025, 6:30:00 pm
48.65%
Financial Progress

10th Expenditure
of ₹ 25311 (0.25 Lacs ) done.
Cummulative ₹ 30.99Lacs ( against 63.7Lacs )

24 days ago

on Wednesday, July 30th 2025, 6:30:00 pm
54.92%
Financial Progress

11th Expenditure
of ₹ 400000 (4.00 Lacs ) done.
Cummulative ₹ 34.99Lacs ( against 63.7Lacs )