Refresh data
on Thursday, September 12th 2024, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद हरिद्वार के विधानसभा क्षेत्र ज्वालापुर के ग्राम मुजाहिदपुर सत्तीवाला में रतमऊ नदी पर 450 मीटर सेतु के सुरक्षातमक कार्य हेतु गाईड बंध व स्पर का निर्माण कार्य (प्रथम चरण)
on Tuesday, September 24th 2024, 8:12:26 am
Technical Sanction
of ₹ 63.6 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE EE Approved Register Sl.no.38
on Tuesday, September 24th 2024, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, September 29th 2024, 6:30:00 pm
47.17%
Financial Progress
1st Expenditure
of ₹ 3000000 (30.00 Lacs ) done.
Cummulative ₹ 30.00Lacs ( against 63.6Lacs )
on Thursday, November 28th 2024, 6:30:00 pm
60.86%
Financial Progress
2nd Expenditure
of ₹ 871000 (8.71 Lacs ) done.
Cummulative ₹ 38.71Lacs ( against 63.6Lacs )
on Thursday, November 28th 2024, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, February 27th 2025, 6:30:00 pm
66.29%
Financial Progress
3rd Expenditure
of ₹ 345000 (3.45 Lacs ) done.
Cummulative ₹ 42.16Lacs ( against 63.6Lacs )
on Saturday, March 29th 2025, 6:30:00 pm
76.34%
Financial Progress
4th Expenditure
of ₹ 639000 (6.39 Lacs ) done.
Cummulative ₹ 48.55Lacs ( against 63.6Lacs )
on Saturday, April 12th 2025, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, July 29th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 4th time